← Back
Zoned residential, not Manhattan
3-16 125TH STREET
QUEENS · BIN 4624946
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R3AZoning
0 sfGross Floor Area
0Units
Zoned residential, not Manhattan · Owner of record: CP PEARL LLC · 3,400 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalCivil
Permit Issued — active, not yet Signed-off
Floor 2Under Construction2p · 1 filing · 20 docs
Floor 1
CellarUnder Construction9p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMERILAND BROOK LLC1005/13/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AMERILAND BROOK LLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HY DESIGN & DEVELOPMENT LLC.General Contractor804/09/2026
ARC CM LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AMERILAND BROOK LLC1506805/13/2025
BRIAN ILL DEVELOPMENT LLC1402109/08/2024
Building Lifecycle
All (45)Filed (10)Permit Issued (5)Special Inspection (30)
06/09/2026
Permit issued — Construction Fence
Q01022114-S5-FN
10/01/2025
Permit issued — Construction Fence
Q01022114-S5-FN
06/13/2025
Special inspection requirement — Duct leakage testing, insulation and design
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Air barrier - visual inspection
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Fenestration air leakage
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Insulation placement and R values
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Permanent certificate
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Interior lighting power
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — HVAC-R and service water heating equipment
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Mechanical Systems
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Subgrade Inspections
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
TONY ONYEAGORO
06/13/2025
Special inspection requirement — Masonry
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Heating Systems
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Final
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Fire-Resistance Rated Construction
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Energy Code Compliance Inspections
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Metering
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Air barrier — testing
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — HVAC-R and service water heating system controls
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Ventilation and air distribution system
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Fenestration areas
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Electric vehicle service equipment requirements
XIAOHONG ZHAO
06/13/2025
Special inspection requirement — Maintenance information
XIAOHONG ZHAO
05/13/2025
Filed — New Building
Q01022114-P1
05/05/2025
Filed — New Building
Q01022114-P3
05/05/2025
Filed — New Building
Q01022114-P2
05/05/2025
Special inspection requirement — Subgrade Inspections
XIAOHONG ZHAO
05/05/2025
Special inspection requirement — Final
XIAOHONG ZHAO
05/05/2025
Special inspection requirement — Footing and Foundation
XIAOHONG ZHAO
05/05/2025
Special inspection requirement — Masonry
XIAOHONG ZHAO
05/05/2025
Special inspection requirement — Structural Steel - Details
XIAOHONG ZHAO
10/21/2024
Permit issued — Support of Excavation
Q01022114-S3-SE
10/15/2024
Permit issued — Earth Work
Q01022114-S1-FO-EA
10/09/2024
Permit issued — Construction Fence
Q01022114-S5-FN
09/08/2024
Filed — New Building
Q01022114-S7
07/25/2024
Filed — New Building
Q01022114-S3
07/20/2024
Filed — New Building
Q01022114-S4
07/10/2024
Filed — New Building
Q01022114-S2
07/08/2024
Filed — New Building
Q01022114-S1
06/26/2024
Filed — New Building
Q01022114-S5
03/24/2024
Filed — New Building
Q01022114-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedARC CM LLC06/09/2026
DOB NOWConstruction FencePermit IssuedFANG YE10/01/2025
DOB NOWSupport of ExcavationPermit IssuedFANG YE10/21/2024
DOB NOWEarth WorkPermit IssuedFANG YE10/15/2024
DOB NOWConstruction FencePermit IssuedFANG YE10/09/2024
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
06/13/2025Duct leakage testing, insulation and designXIAOHONG ZHAOenergy_progress
06/13/2025Fenestration and door U-factor and product ratingsXIAOHONG ZHAOenergy_progress
06/13/2025Air barrier - visual inspectionXIAOHONG ZHAOenergy_progress
06/13/2025Fenestration air leakageXIAOHONG ZHAOenergy_progress
06/13/2025Insulation placement and R valuesXIAOHONG ZHAOenergy_progress
06/13/2025Permanent certificateXIAOHONG ZHAOenergy_progress
06/13/2025Interior lighting powerXIAOHONG ZHAOenergy_progress
06/13/2025HVAC-R and service water heating equipmentXIAOHONG ZHAOenergy_progress
06/13/2025Mechanical SystemsXIAOHONG ZHAOspecial
06/13/2025Subgrade InspectionsXIAOHONG ZHAOspecial
06/13/2025Fire-Resistant Penetrations and JointsXIAOHONG ZHAOspecial
06/13/2025Subsurface Investigations (Borings/Test Pits)TONY ONYEAGOROspecial
06/13/2025MasonryXIAOHONG ZHAOspecial
06/13/2025Heating SystemsXIAOHONG ZHAOspecial
06/13/2025FinalXIAOHONG ZHAOprogress
06/13/2025Fire-Resistance Rated ConstructionXIAOHONG ZHAOprogress
06/13/2025Energy Code Compliance InspectionsXIAOHONG ZHAOprogress
06/13/2025HVAC-R and service water piping design and insulationXIAOHONG ZHAOenergy_progress
06/13/2025MeteringXIAOHONG ZHAOenergy_progress
06/13/2025Air barrier — testing XIAOHONG ZHAOenergy_progress
06/13/2025HVAC-R and service water heating system controlsXIAOHONG ZHAOenergy_progress
06/13/2025Ventilation and air distribution systemXIAOHONG ZHAOenergy_progress
06/13/2025Fenestration areasXIAOHONG ZHAOenergy_progress
06/13/2025Electric vehicle service equipment requirementsXIAOHONG ZHAOenergy_progress
06/13/2025Maintenance informationXIAOHONG ZHAOenergy_progress
Latest 25 of 46.
▾Documents — 98 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/21/2026Q01022114-P3Request digital key ↗
08/21/2026Q01022114-P2Request digital key ↗
08/21/2026Q01022114-P1Request digital key ↗
Showing 3 of 10 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
12/05/2024440820578Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
01/22/2026440820578Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q01022114-P1Open ↗
08/13/2026Q01022114-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026Q01022114-I1Open ↗
08/13/2026Q01022114-P1Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
12/05/2024440820578Open ↗
▸Seals & Professional Certifications57
▸DOB NOWProgress Inspector Seal & Signature29
09/13/2026Q01022114-P2Open ↗
09/13/2026Q01022114-P2Open ↗
09/13/2026Q01022114-P2Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/13/2026Q01022114-P2Open ↗
09/13/2026Q01022114-P2Open ↗
09/13/2026Q01022114-P2Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/21/2026Q01022114-S1Open ↗
08/21/2026Q01022114-P3Open ↗
08/21/2026Q01022114-P2Open ↗
Showing 3 of 10 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
12/05/2024440820578Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
12/05/2024440820578Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026Q01022114-P1Open ↗
08/13/2026Q01022114-I1Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
01/22/2026440820578Open ↗
12/05/2024440820578Open ↗
▸DOB NOWStreet Tree Checklist2
08/21/2026Q01022114-P1Open ↗
08/21/2026Q01022114-I1Open ↗
▸BISBPP: STREET TREES SITE PLAN1
01/22/2026440820578Open ↗
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT2
08/13/2026Q01022114-P1Open ↗
08/13/2026Q01022114-I1Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
12/05/2024440820578Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
12/05/2024440820578Open ↗
▸Other Documents13
▸DOB NOWProperty Ownership Certification2
08/21/2026Q01022114-P1Open ↗
08/21/2026Q01022114-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q01022114-P1Open ↗
08/13/2026Q01022114-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01022114-P1Open ↗
08/13/2026Q01022114-I1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q01022114-S1Open ↗
08/13/2026Q01022114-S3Open ↗
▸BISCURB CUT: PROVIDE EXISTING NUMBER1
01/22/2026440820578Open ↗
▸BISVERIFY DOB PLAN NAMING STANDARD IS MET1
01/22/2026440820578Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
01/22/2026440820578Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
01/22/2026440820578Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
12/05/2024440820578Open ↗