1899Year Built
2Stories
A9Building Class
R7-1Zoning
2,695 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Miscellaneous one family · 1,640 sf lot · 1.64 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofRenovate existing single family house with stairs and bulkhe47p · 6 filings · 20 docs
BulkheadSister existing wood joist with new LVL2p · 2 filings · 19 docs
Floor 3Renovate existing single family house with stairs and bulkhe15p · 1 filing · 20 docs
Floor 2Renovate existing single family house with stairs and bulkhe51p · 6 filings · 20 docs
Floor 1Renovate existing single family house with stairs and bulkhe48p · 6 filings · 20 docs
CellarRenovate existing single family house with stairs and bulkhe52p · 6 filings · 20 docs
Sub-BasementSister existing wood joist with new LVL7p · 1 filing · 12 docs
Site & exteriorRenovate existing single family house with stairs and bulkhe31p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/20/2022$5.5M—Private party → Private party$2,041/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Stephen McNamara Architecture909/14/2026
EP Engineering409/03/2026
Silman408/01/2025
Gza Geoenvironmental of New York205/23/2024
DTLS Architecture102/01/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB Building Consulting3203/21/2026
Kushner Studios203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Steering House ConstructionGeneral Contractor2207/08/2026
Steering House ConstructionScaffold807/08/2026
Dynamic Blue Water MechanicalPlumbing208/14/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Tristate Planning Engineering8344809/14/2026
Macia Inspection & Testin402703/03/2026
Gza Geoenvironmental of N1179205/23/2024
Building Lifecycle
10/30/2026
Signed off — Alteration
Propose to renovate the existing single-family house with general construction works; excavate and expand the existing cellar area as per plan. No change in use, egress and occupancy.
B08031174-I1
10/22/2026
Signed off — Alteration
Plumbing Scope of work as per plan, filed in conjunction with GC # B08031174-I1. No change of use, occupancy or egress under this application.
B01095417-I1
09/25/2026
Signed off — Alteration
Foundation filing as per plan in conjunction with GC # B08031174-P1.
B01055278-I1
09/24/2026
Signed off — Alteration
Propose Structural work for the renovation of existing single family house with GC # B08031174-P1. ST scope includes new openings in exist. masonry wall; new stair opening in exist. slab, new lintels; new cold formed metal framing as per plan.
B08032647-I1
09/14/2026
Filed — Alteration CO
Proposed renovate existing single family house. Most of GC scope was filed under ALT-GC # B08031174 except new works for stairs & new bulkhead in this building are under this ALT-CO application. Obtain a new C of O.
B00805099-P3
132 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offDynamic Blue Water Mechanical08/13/2026
DOB NOWGeneral ConstructionPermit IssuedSteering House Construction05/14/2026
DOB NOWMechanical SystemsSigned-offSteering House Construction05/08/2026
DOB NOWMechanical SystemsSigned-offSteering House Construction02/04/2026
DOB NOWConstruction FenceSigned-offSteering House Construction12/31/2025
DOB NOWGeneral ConstructionPermit IssuedSteering House Construction09/05/2025
DOB NOWStructuralSigned-offSteering House Construction08/20/2025
DOB NOWGeneral ConstructionSigned-offSteering House Construction08/08/2025
DOB NOWPlumbingSigned-offSuper Plumbers07/18/2025
DOB NOWStructuralSigned-offSteering House Construction08/07/2024
DOB NOWStructuralSigned-offSteering House Construction08/07/2024
DOB NOWFoundationSigned-offSteering House Construction07/10/2024
DOB NOWConstruction FenceSigned-offSteering House Construction06/27/2024
DOB NOWGeneral ConstructionSigned-offSteering House Construction06/27/2024
DOB NOWConstruction FenceSigned-offSteering House Construction05/13/2024
DOB NOWGeneral ConstructionSigned-offSteering House Construction05/13/2024
DOB NOWGeneral ConstructionSigned-offSteering House Construction03/21/2024
DOB NOWConstruction FenceSigned-offSteering House Construction03/19/2024
1 project · most recent 09/03/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/03/2026Signed-offDynamic Blue Water MechanicalGas, Storm, Water/Sanitary
1 project · most recent 03/19/2026
General Wiring
FiledStatusContractorScope
03/19/2026CompleteFSM ElectricalGeneral Wiring
4 projects · most recent 08/01/2025
Steel
FiledStatusContractorScope
08/01/2025Signed-offSteering House Construction—
05/15/2025Signed-offSteering House ConstructionSteel
08/05/2024Signed-offSteering House Construction—
04/25/2024———
1 project · most recent 09/14/2026
Fence
FiledStatusContractorScope
09/14/2026Permit IssuedSteering House ConstructionFence
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
09/10/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/18/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/24/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/26/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/22/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/22/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 65
DateRequirementInspectorRole
09/11/2026Structural Stability – Alterations of existing buildingsNICHOLAS PALUMBOspecial
09/11/2026Fire-Resistance Rated ConstructionNICHOLAS PALUMBOprogress
09/11/2026Fire-Resistant Penetrations and JointsNICHOLAS PALUMBOspecial
09/02/2026Fire-Resistant Penetrations and JointsNICHOLAS PALUMBOspecial
03/16/2026Fire-Resistant Penetrations and JointsCHUNG CHING JENspecial
02/26/2026Fire-Resistant Penetrations and JointsCHUNG CHING JENspecial
09/04/2025Footing and FoundationNicholas Palumboprogress
09/04/2025FinalNicholas Palumboprogress
08/22/2025Structural Stability – Alterations of existing buildingsNicholas Palumbospecial
08/22/2025Fire-Resistant Penetrations and JointsNicholas Palumbospecial
08/22/2025Fire-Resistance Rated ConstructionNicholas Palumboprogress
07/11/2025Structural Stability – Alterations of existing buildingsCHUNG CHING JENspecial
07/11/2025Fire-Resistant Penetrations and JointsCHUNG CHING JENspecial
07/11/2025Fire-Resistance Rated ConstructionCHUNG CHING JENprogress
06/26/2025Footing and FoundationJeffrey Stonesprogress
06/26/2025FinalJeffrey Stonesprogress
06/10/2025Insulation placement and R values—energy_progress
06/10/2025Fenestration and door U-factor and product ratings—energy_progress
06/10/2025Lighting in dwelling units—energy_progress
06/10/2025Interior lighting power—energy_progress
06/10/2025Air barrier - visual inspection—energy_progress
06/10/2025Structural Stability – Alterations of existing buildingsJeffrey Stonesspecial
06/10/2025Air barrier — testing —energy_progress
06/10/2025Energy Code Compliance InspectionsJeffrey Stonesprogress
06/10/2025FinalJeffrey Stonesprogress