Penthouse1p · 1 filing · 3 docs
Architecture
INTERIOR WORK IN PH B. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
3 documents · 1 drawing sheet
Floor 4414p · 3 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
Boiler Equipment · General Construction
INTERIOR WORK IN PH B. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
3 documents
Installation of boiler. No change in occupancy, use or egress. Filed in conjunction with NB #121204552
On file for this project
7 documents · 1 drawing sheet
Installation of boiler. No change in occupancy, use or egress. Filed in conjunction with NB #121204552
On file for this project
25 documents · 1 drawing sheet
Floor 431p · 1 filing · 3 docs
Architecture
Issued Permit Scope
General Construction
INTERIOR WORK IN PH B. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
On file for this project
3 documents
Floor 427p · 1 filing · 5 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Plumbing
plumbing work for apt PHC only
On file for this project
5 documents
Floor 417p · 1 filing · 5 docs
ArchitecturePlumbing
Issued Permit Scope
General Construction · Plumbing
plumbing work for apt PHC only
On file for this project
5 documents
Floor 40
Floor 39
Floor 38
Floor 37
Floor 36
Floor 35
Floor 34
Floor 33
Floor 32
Floor 31
Floor 30
Floor 29
Floor 28
Floor 27
Floor 26
Floor 25
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 41p · 1 filing · 2 docs
Structural
INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD SHALL COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
On file for this project
2 documents · 1 drawing sheet
Floor 3
Floor 24p · 4 filings · 14 docs
ArchitectureDMEquipmentMechanical
Issued Permit Scope
Mechanical Systems · Supported Scaffold
plumbing work for apt PHC only
On file for this project
5 documents · 1 drawing sheet
Installation of emergency generator. No change in occupancy, use or egress. Filed in conjunction with NB #121204552
On file for this project
2 documents
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Floor 18p · 3 filings · 12 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence
INSTALLATION OF A FENCE AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2014.
On file for this project
3 documents
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2014.
On file for this project
5 documents
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
4 documents
Cellar1 filing · 2 docs
Issued Permit Scope
Supported Scaffold
INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD SHALL COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
On file for this project
2 documents
Site & exteriorUnder Construction29p · 12 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY 40' HIGH PIPE SCAFFOLD ORIGINATING (OFF ROOF) FOR NEW BUILDING CONSTRUCTION WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY, PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.
On file for this project
3 documents · 5 drawing sheets
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE,EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 12 filings on this floor.
Filed — no permit issued14p · 2 filings · 6 docs
ArchitectureCivilGeneralOther
General construction associated with renovations to lobby. No change on occupancy, use or egress.
On file for this project
4 documents · 10 drawing sheets
Limited facade repairs as per plans filed. No change in occupancy, use or egress.
On file for this project
2 documents · 4 drawing sheets