| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2026 | Permit Issued | ILG MECH SERVICES,INC | 68 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/29/2026 | Permit Issued | ILG MECH SERVICES, INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2025 | Permit Issued | ALL AMERICAN ELEC'L CORP | General Wiring |
| 12/14/2025 | Permit Issued | ALL AMERICAN ELEC'L CORP | General Wiring |
| 09/05/2024 | Complete | PETER J. CATANZARO, INC. | General Wiring |
| 12/02/2022 | Complete | P & M ELECT'L CONTR. CORP | General Wiring |
| 06/21/2018 | Permit Issued | LEKTRIC INSTALLATIONS COR | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2019 | — | — | Scaffold |
| Owner | Filings | Most Recent |
|---|---|---|
| NYC DEPARTMENT OF ENVIRONMENTAL PROTECTION | 19 | 09/23/2026 |
| ACE GROUP NY CORP. | 5 | 03/22/2026 |
| OWNER OF 30 PIKE ST. 810 | 1 | 03/22/2026 |
| K2NYC SERVICES | 2 | 03/21/2026 |
| DEPARTMENT OF DESIGN AND CONST | 2 | 03/21/2026 |
| DEP | 11 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KNF SERVICES CROP | 11 | 04/29/2026 |
| LIRO ENGINEERS, INC. | 2 | 06/14/2024 |
| VOLUME SPACE CONSULTING INC. | 1 | 04/19/2024 |
| BRONZINO ENGINEERING, P.C. | 1 | 10/04/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 06/22/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| PNP MANAGEMENT AND CONSULTING INC | 16 | 03/21/2026 |
| P WOLFE CONSULTANTS | 4 | 03/21/2026 |
| HRF SERVICES CORP | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACE GROUP NY CORP | General Contractor | 3 | 03/21/2026 |
| GLASS ARMOR OF NEW YORK I | General Contractor | 3 | 07/08/2026 |
| AVENUE CONTRACTING INC | General Contractor | 2 | 04/09/2026 |
| IRA L GRAND | Plumbing | 2 | 03/21/2026 |
| SUMMERVILLE, ERROL | Electrical | 2 | 03/21/2026 |
| NYCMC CORP | General Contractor | 2 | 03/21/2026 |
| PJP INSTALLERS INC | General Contractor | 2 | 07/08/2026 |
| START UP COOLING NY CORP | General Contractor | 2 | 07/08/2026 |
| ILG MECH SERVICES, INC | Plumbing | 1 | 06/28/2026 |
| ILG MECH SERVICES,INC | Fire Protection | 1 | 06/28/2026 |
| PETER CATANZARO III | Electrical | 1 | 03/21/2026 |
| PETER J CATANZARO INC 001146 | General Contractor | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 4 | 03/17/2026 |
| ADNAN ENGINEERING, PC | 6814 | 3 | 12/06/2024 |
| TECTONIC ENGINEERING CONS | 106 | 3 | 06/14/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | START UP COOLING NY CORP | 05/14/2026 |
| DOB NOW | General Construction | Permit Issued | AVENUE CONTRACTING INC | 12/30/2025 |
| DOB NOW | Sprinklers | Permit Issued | ILG MECH SERVICES,INC | 10/27/2025 |
| DOB NOW | Plumbing | Permit Issued | IRA L GRAND | 10/27/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | START UP COOLING NY CORP | 10/16/2025 |
| DOB NOW | General Construction | Permit Issued | AVENUE CONTRACTING INC | 08/11/2025 |
| DOB NOW | Structural | Signed-off | NYCMC CORP | 05/29/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ACE GROUP NY CORP | 04/22/2024 |
| DOB NOW | Support of Excavation | Signed-off | GLASS ARMOR OF NEW YORK I | 12/14/2023 |
| DOB NOW | Structural | Signed-off | GLASS ARMOR OF NEW YORK I | 11/09/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 01/03/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | PJP INSTALLERS INC | 06/22/2018 |
| BIS | OT | ISSUED | EMPIRE CONTROL ABATEMENT | 08/07/2019 |
| BIS | FP | ISSUED | FIREMASTERS | 06/25/2009 |
| BIS | EQ | ISSUED | COLGATE SCAFFOLDING & EQUIPMENT | 01/22/2008 |
| BIS | EQ | ISSUED | B & S RESTORATION INC | 08/17/2007 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2026 | Duct leakage testing, insulation and design | Rajasekhar Sakhamuri | energy_progress |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 03/18/2026 | Mechanical Systems | Rajasekhar Sakhamuri | special |
| 03/18/2026 | Final | Rajasekhar Sakhamuri | progress |
| 03/16/2026 | Duct leakage testing, insulation and design | Rajasekhar Sakhamuri | energy_progress |
| 03/16/2026 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 03/16/2026 | Mechanical Systems | Rajasekhar Sakhamuri | special |
| 03/16/2026 | Final | Rajasekhar Sakhamuri | progress |
| 12/15/2025 | Post-installed Anchors | Rajasekhar Sakhamuri | special |
| 12/15/2025 | Post-installed Anchors | Rajasekhar Sakhamuri | special |
| 12/15/2025 | Sprinkler Systems | Rajasekhar Sakhamuri | special |
| 12/15/2025 | Sprinkler Systems | Rajasekhar Sakhamuri | special |
| 06/14/2024 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 06/14/2024 | Excavations - Sheeting, Shoring, and Bracing | GEORGE GHEBRYAL | special |
| 06/14/2024 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 06/14/2024 | Energy Code Compliance Inspections | GEORGE GHEBRYAL | progress |
| 06/14/2024 | Final | GEORGE GHEBRYAL | progress |
| 06/12/2024 | Energy Code Compliance Inspections | GEORGE GHEBRYAL | progress |
| 06/12/2024 | Final | GEORGE GHEBRYAL | progress |
| 06/12/2024 | Maintenance information | GEORGE GHEBRYAL | energy_progress |
| 06/12/2024 | Concrete - Cast-In-Place | GEORGE GHEBRYAL | special |
| 06/12/2024 | Excavations - Sheeting, Shoring, and Bracing | GEORGE GHEBRYAL | special |
| 03/12/2024 | Fenestration air leakage | Adnan Aljuamily | energy_progress |
| 03/12/2024 | Interior lighting power | Adnan Aljuamily | energy_progress |
| 03/12/2024 | Fenestration areas | Adnan Aljuamily | energy_progress |