| Owner | Filings | Most Recent |
|---|---|---|
| RAF GENERAL CONTRACTING | 2 | 09/23/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| A TECH ENGINEERING NYC, PLLC. | 1 | 07/29/2026 |
| RAMPULLA ASSOCIATES ARCHITECTS, LLP | 3 | 05/07/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| RAMPULLA ASSOCIATES ARCHITECTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RAF GENERAL CONTRACTING C | General Contractor | 2 | 04/10/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 2 | 09/23/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 1 | 12/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 09/22/2026 |
| DOB NOW | Plumbing | Permit Issued | FLOW-RIGHT PLBG & HTG COR | 05/12/2026 |
| DOB NOW | General Construction | Permit Issued | RAF GENERAL CONTRACTING C | 04/08/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | RAF GENERAL CONTRACTING C | 04/07/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/07/2026 | Permit Issued | RAF GENERAL CONTRACTING C | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2026 | Permit Issued | FLOW-RIGHT PLBG & HTG COR | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/01/2026 | Permit Issued | RIDGE ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2026 | Permit Issued | FLOW-RIGHT PLBG & HTG COR | Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/06/2026 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 11/18/2025 | Final | Stanislav Pilipenko | progress |
| 11/18/2025 | Lowest Floor Elevation | Stanislav Pilipenko | progress |
| 11/18/2025 | Footing and Foundation | Stanislav Pilipenko | progress |
| 11/18/2025 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 11/18/2025 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 11/18/2025 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 11/18/2025 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Mechanical Systems | Stanislav Pilipenko | special |
| 11/18/2025 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | HVAC-R and service water piping design and insulation | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Fenestration and door U-factor and product ratings | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 11/18/2025 | Air barrier — testing | Stanislav Pilipenko | energy_progress |