← Back
Large suburban residence
301 GRAVESEND NECK ROAD
BROOKLYN · BIN 3193874
💬 Discuss this project
1960Year Built
3Stories
A3Building Class
R4Zoning
4,079 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Large suburban residence · Owner of record: 2261 EAST 3RD STREET LLC · 3,070 sf lot · 1.33 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Floor 345p · 1 filing · 20 docs
Floor 245p · 1 filing · 20 docs
Floor 150p · 1 filing · 20 docs
Cellar53p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GF ASSOCIATES 15208/29/2026
BARUCH BUILDERS103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/28/2023$2.8M—Private party → 2261 EAST 3RD STREET LLC$693/sf building
06/21/2022$2.8M—Private party → Private party$693/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHER ARCHITECT704/24/2026
SAMY ABOUZID601/28/2025
HESHAM ELSHAMY305/23/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
4444 PPPP CORP3003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BARUCH BUILDERS CORPGeneral Contractor1307/08/2026
NESS MECHANICAL P & H INCPlumbing307/08/2026
NOPHIER PLUMBING & HTG INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HESHAM ELSHAMY ENGINEERIN15081404/24/2026
Building Lifecycle
All (114)Filed (16)Permit Issued (13)Signed Off (8)Violation (1)Inspection (12)Objection (34)Special Inspection (30)
07/16/2026
Signed off — Alteration CO
interior renovation and enlargement to create a third floor
B07994195-I1
04/27/2026
Special inspection requirement — Fire-Resistance Rated Construction
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Energy Code Compliance Inspections
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Sprayed fire-resistant materials
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Masonry
HESHAM ELSHAMY
04/27/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
HESHAM ELSHAMY
04/24/2026
Filed — Alteration CO
interior renovation and enlargement to create a third floor
B07994195-A1
04/23/2026
Special inspection requirement — Masonry
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Energy Code Compliance Inspections
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Sprayed fire-resistant materials
HESHAM ELSHAMY
04/23/2026
Special inspection requirement — Fire-Resistance Rated Construction
HESHAM ELSHAMY
02/12/2026
Filed — Alteration CO
interior renovation and enlargement to create a third floor
B07994195-P9
02/11/2026
Special inspection requirement — Fire-Resistance Rated Construction
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Energy Code Compliance Inspections
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Sprayed fire-resistant materials
HESHAM ELSHAMY
02/11/2026
Special inspection requirement — Masonry
HESHAM ELSHAMY
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
12/04/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
11/04/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/29/2025
Objection resolved — Addressed
10/28/2025
Objection raised — Structural
10/28/2025
Objection raised — Energy
10/28/2025
Objection raised — Zoning
10/28/2025
Objection raised — Scope
10/28/2025
Objection raised — Admin
10/28/2025
Objection raised — Admin
10/28/2025
Objection raised — Admin
10/28/2025
Objection raised — Zoning
10/28/2025
Objection raised — Zoning
10/28/2025
Objection raised — Energy
07/29/2025
Objection raised — Scope
07/16/2025
Filed — Alteration CO
interior renovation and enlargement to create a third floor
B07994195-P7
06/27/2025
Signed off — Alteration CO
interior renovation and enlargement to create a third floor
B07994195-S5
06/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/10/2025
Permit issued — Plumbing
B07994195-S5-PL
02/04/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/03/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/31/2025
Permit issued — Plumbing
B07994195-S5-PL
01/30/2025
Special inspection requirement — Post-installed Anchors
HESHAM ELSHAMY
01/30/2025
Special inspection requirement — Energy Code Compliance Inspections
HESHAM ELSHAMY
01/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
HESHAM ELSHAMY
01/30/2025
Special inspection requirement — HVAC-R and service water heating system controls
HESHAM ELSHAMY
01/30/2025
Special inspection requirement — HVAC-R and service water heating equipment
HESHAM ELSHAMY
01/30/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
HESHAM ELSHAMY
Latest 60 of 114 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offNOPHIER PLUMBING & HTG IN04/10/2025
DOB NOWPlumbingSigned-offNESS MECHANICAL P & H INC01/31/2025
DOB NOWMechanical SystemsSigned-offBARUCH BUILDERS CORP09/23/2024
DOB NOWPlumbingSigned-offNESS MECHANICAL P & H INC08/05/2024
DOB NOWCurb CutSigned-offBARUCH BUILDERS CORP06/03/2024
DOB NOWGeneral ConstructionPermit IssuedBARUCH BUILDERS CORP05/06/2024
DOB NOWPlumbingSigned-offNESS MECHANICAL P & H INC02/28/2024
DOB NOWConstruction FenceSigned-offBARUCH BUILDERS CORP01/16/2024
DOB NOWFoundationSigned-offBARUCH BUILDERS CORP06/01/2023
DOB NOWStructuralSigned-offBARUCH BUILDERS CORP05/25/2023
DOB NOWSupport of ExcavationSigned-offBARUCH BUILDERS CORP05/24/2023
DOB NOWGeneral ConstructionPermit IssuedBARUCH BUILDERS CORP05/09/2023
DOB NOWConstruction FenceSigned-offBARUCH BUILDERS CORP02/16/2023
1 project · most recent 04/24/2026
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
04/24/2026Signed-offBARUCH BUILDERS CORPAir Conditioning Systems, Heating Systems
Cooling
Carrier 24ABB330A330 1,600 CFM · Condensing Unit ×3
24ABB360A520 1,200 CFM · Condensing Unit ×1
Heating
Weil-Mclain CGi-7 PIN 11 CFM · Boiler ×1
1 project · most recent 04/24/2026
Gas Water/Sanitary
FiledStatusContractorScope
04/24/2026Signed-offNOPHIER PLUMBING & HTG INGas, Water/Sanitary
1 project · most recent 12/28/2023
General Wiring
FiledStatusContractorScope
12/28/2023CompleteSTAT ELECTRIC & MAINTENANGeneral Wiring
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
06/05/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/30/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
02/04/2025Pass-Final CND-Occupancy InspectionPassView ↗
02/03/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/04/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/31/2024Pass-Final CND-Occupancy InspectionPassView ↗
10/30/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/22/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
10/21/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/27/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
04/27/2026Sprayed fire-resistant materialsHESHAM ELSHAMYspecial
04/27/2026Structural Stability – Alterations of existing buildingsHESHAM ELSHAMYspecial
04/27/2026Fire-Resistant Penetrations and JointsHESHAM ELSHAMYspecial
04/27/2026Energy Code Compliance InspectionsHESHAM ELSHAMYprogress
04/27/2026Fire-Resistance Rated ConstructionHESHAM ELSHAMYprogress
04/27/2026MasonryHESHAM ELSHAMYspecial
04/27/2026Exterior Insulation and Finish Systems (EIFS)HESHAM ELSHAMYspecial
04/23/2026Energy Code Compliance InspectionsHESHAM ELSHAMYprogress
04/23/2026Structural Stability – Alterations of existing buildingsHESHAM ELSHAMYspecial
04/23/2026Sprayed fire-resistant materialsHESHAM ELSHAMYspecial
04/23/2026MasonryHESHAM ELSHAMYspecial
04/23/2026Fire-Resistant Penetrations and JointsHESHAM ELSHAMYspecial
04/23/2026Exterior Insulation and Finish Systems (EIFS)HESHAM ELSHAMYspecial
04/23/2026Fire-Resistance Rated ConstructionHESHAM ELSHAMYprogress
02/11/2026Structural Stability – Alterations of existing buildingsHESHAM ELSHAMYspecial
02/11/2026Energy Code Compliance InspectionsHESHAM ELSHAMYprogress
02/11/2026Fire-Resistance Rated ConstructionHESHAM ELSHAMYprogress
02/11/2026Exterior Insulation and Finish Systems (EIFS)HESHAM ELSHAMYspecial
02/11/2026Fire-Resistant Penetrations and JointsHESHAM ELSHAMYspecial
02/11/2026MasonryHESHAM ELSHAMYspecial
02/11/2026Sprayed fire-resistant materialsHESHAM ELSHAMYspecial
01/30/2025Post-installed AnchorsHESHAM ELSHAMYspecial
01/30/2025Fire-Resistant Penetrations and JointsHESHAM ELSHAMYspecial
01/30/2025HVAC-R and service water heating equipmentHESHAM ELSHAMYenergy_progress
01/30/2025HVAC-R and service water piping design and insulationHESHAM ELSHAMYenergy_progress
Latest 25 of 77.
▾Documents — 138 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/28/2026B00805555-I1Request digital key ↗
08/18/2026B07994195-P1Request digital key ↗
08/18/2026B07994195-P6Request digital key ↗
Showing 3 of 16 on file for this type
▸Zoning, Tax Lot & Property Records17
▸DOB NOWRestrictive Declaration/Easement 16
08/13/2026B07994195-P2Open ↗
08/13/2026B07994195-P1Open ↗
08/13/2026B07994195-S5Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram5
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-P9Open ↗
08/13/2026B07994195-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-I1Open ↗
08/13/2026B07994195-P9Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B07994195-I1Open ↗
▸Seals & Professional Certifications55
▸DOB NOWSpecial Inspector Seal & Signature21
09/01/2026B07994195-P1Open ↗
09/01/2026B07994195-P1Open ↗
08/31/2026B07994195-P6Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWProgress Inspector Seal & Signature18
09/01/2026B07994195-P1Open ↗
08/31/2026B07994195-P6Open ↗
08/31/2026B07994195-P6Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/28/2026B00805537-I1Open ↗
08/18/2026B07994195-P9Open ↗
08/18/2026B07994195-P6Open ↗
Showing 3 of 16 on file for this type
▸Safety & Tenant Protection9
▸DOB NOWStreet Tree Checklist5
08/18/2026B07994195-I1Open ↗
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-P9Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan2
08/18/2026B07994195-I1Open ↗
08/13/2026B07994195-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/18/2026B07994195-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/18/2026B07994195-I1Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
08/18/2026B07994195-P9Open ↗
08/18/2026B07994195-P6Open ↗
08/18/2026B07994195-P3Open ↗
Showing 3 of 14 on file for this type
▸Inspections & Test Reports2
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026B07994195-S2Open ↗
08/13/2026B07994195-S1Open ↗
▸Other Documents25
▸DOB NOWPlot Diagram7
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-S1Open ↗
08/13/2026B07994195-P9Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-I1Open ↗
08/13/2026B07994195-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/18/2026B07994195-P9Open ↗
08/18/2026B07994195-P1Open ↗
08/18/2026B07994195-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial5
08/18/2026B07994195-A1Open ↗
08/13/2026B07994195-I1Open ↗
08/13/2026B07994195-P9Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026B07994195-S1Open ↗
08/13/2026B07994195-S2Open ↗
▸DOB NOWFinal Survey1
08/13/2026B07994195-I1Open ↗