| Owner | Filings | Most Recent |
|---|---|---|
| Church of Sacred Heart | 7 | 08/29/2026 |
| Sacred Heart School | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Ikra Consulting | 1 | 07/28/2026 |
| Rodriguez + Gambino Architectural | 2 | 06/18/2026 |
| Sohail Humayun P E | 1 | 08/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Sagacity Building Services | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Avalon Construction | General Contractor | 1 | 07/14/2026 |
| Yarks NYC | Scaffold | 1 | 07/29/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | Yarks NYC | 07/28/2026 |
| DOB NOW | General Construction | Permit Issued | Avalon Construction | 07/13/2026 |
| BIS | BL | ISSUED | R&A Heating & Contracting Co.i | 10/13/2017 |
| BIS | PL | ISSUED | R&A Heating & Contracting Co.i | 10/13/2017 |
| BIS | OT | ISSUED | Four Suns Fuel Oil Co | 10/12/2017 |
| BIS | OT | ISSUED | Arthur Vincent Company | 09/06/2011 |
| BIS | FP | ISSUED | Lund Fire Products Co | 05/21/2007 |
| BIS | PL | ISSUED | Girasan Plumbing & Heating | 09/16/1994 |
| BIS | FP | ISSUED | Lund Fire Products Co | 04/12/1994 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/26/2025 | — | — | Ventilation Systems | Ventilation — 56JN92 3,996 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | Richard Neu | — |
| 10/24/2022 | Permit Issued | Catello Electrical Cont | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | Yarks NYC | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/11/2026 | Final | STEVEN GAMBINO | progress |
| 05/04/2026 | Final | STEVEN GAMBINO | progress |
| 09/14/2025 | Ventilation and air distribution system | — | energy_progress |
| 09/14/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 09/14/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 07/23/2025 | Fire-Resistance Rated Construction | — | progress |
| 07/23/2025 | Mechanical Systems | — | special |
| 07/23/2025 | Maintenance information | — | energy_progress |
| 07/23/2025 | Final | — | progress |
| 07/23/2025 | Energy Code Compliance Inspections | — | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Sacred Heart School | Education | Entire building | Project S01437188 Project S01396823 Project S01397423 Project S01260717 |