| Owner | Filings | Most Recent |
|---|---|---|
| NYCHA | 26 | 07/08/2026 |
| NYCHA 99 | 1 | 03/22/2026 |
| NYC HOUSING AUTHORITY | 5 | 03/21/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 1 | 03/21/2026 |
| HPD | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GANNETT FLEMING ENGINEERS & ARCHITE | 2 | 10/30/2025 |
| CSA GROUP NY ARCHITECTS AND ENGINEE | 2 | 10/30/2025 |
| CSA GROUP | 2 | 10/30/2025 |
| JOEL PHAGOO P.E. PLLC | 1 | 06/30/2023 |
| AK CONSULTING SERVICES, INC | 1 | 12/09/2022 |
| BITOPI CONSULTANTS LLC | 1 | 12/09/2022 |
| SUPERSTRUCTURES ENG. + ARCH. | 1 | 04/12/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUPERSTRUCTURES ENG + ARCH | 1 | 03/21/2026 |
| NERIS | 12 | 03/21/2026 |
| AK CONSULTING SERVICES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J & N CONSTRUCTION GROUP | General Contractor | 15 | 07/08/2026 |
| SLSCO,LTD | General Contractor | 4 | 04/09/2026 |
| HALPERN, S | Electrical | 2 | 03/21/2026 |
| ORTEGA-CEDENO, DAVID | Electrical | 2 | 03/21/2026 |
| ALVARADO, JUAN | Electrical | 2 | 03/21/2026 |
| CHRYSSIADIS, NICOLAS | Electrical | 2 | 03/21/2026 |
| SEGRETI JOSEPH | Electrical | 1 | 03/21/2026 |
| JOSEPH SEGRETI | Electrical | 1 | 03/21/2026 |
| ANZELM KRYSA | Electrical | 1 | 03/21/2026 |
| METROCITY GROUP,INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PROJECT TACTICAL SOLUTION | 5859 | 6 | 10/30/2025 |
| JOEL PHAGOO ,PE, PLLC | 2416 | 1 | 06/30/2023 |
| TECTONIC ENGINEERING CONS | 106 | 1 | 04/12/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | SLSCO,LTD | 12/19/2025 |
| DOB NOW | Plumbing | Signed-off | METROCITY GROUP,INC | 12/17/2025 |
| DOB NOW | General Construction | Signed-off | SLSCO,LTD | 12/16/2025 |
| DOB NOW | Construction Fence | Signed-off | J & N CONSTRUCTION GROUP | 12/11/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | J & N CONSTRUCTION GROUP | 12/05/2023 |
| DOB NOW | General Construction | Signed-off | J & N CONSTRUCTION GROUP | 11/28/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | J & N CONSTRUCTION GROUP | 07/01/2023 |
| DOB NOW | General Construction | Signed-off | J & N CONSTRUCTION GROUP | 03/23/2023 |
| DOB NOW | Construction Fence | Signed-off | J & N CONSTRUCTION GROUP | 12/14/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | J & N CONSTRUCTION GROUP | 12/09/2022 |
| BIS | PL | ISSUED | DYNAMIC CONTRACTING CORP | 03/11/2011 |
| BIS | PL | ISSUED | FIVE STAR P AND H CO, INC | 02/18/2010 |
| BIS | PL | ISSUED | DYNAMIC CONTRACTING CORP | 09/09/2009 |
| BIS | OT | ISSUED | ZAFFUTO CONST CO INC | 06/18/2003 |
| BIS | OT | ISSUED | 4A GENERAL CONTRACTING CORP. | 06/08/2001 |
| BIS | PL | ISSUED | DNA PLUMBING CONTR. INC | 03/23/2001 |
| BIS | OT | ISSUED | CRANE MECHANICAL CORP | 02/28/2001 |
| BIS | OT | ISSUED | LITHOS CONST | 02/03/2000 |
| BIS | PL | ISSUED | FIVE STAR P AND H CO, INC | 09/07/1999 |
| BIS | OT | ISSUED | LITHOS CONST | 08/30/1999 |
| BIS | OT | ISSUED | CRANE MECHANICAL CORP | 07/02/1999 |
| BIS | PL | ISSUED | DNA PLUMBING CONTR. INC | 07/02/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Complete | EMPIRE STATE ELECTL CORP | General Wiring |
| 08/12/2025 | Complete | TRI-STATE ELECL & MECHL I | General Wiring |
| 08/08/2025 | Complete | TRI-STATE ELECL & MECHL I | General Wiring |
| 11/22/2022 | Complete | LIT MODE ELECL CONTG INC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/05/2025 | HVAC-R and service water heating equipment | Max Lee | energy_progress |
| 11/05/2025 | Mechanical Systems | Max Lee | special |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 11/05/2025 | Tenant Protection Plan Compliance | Max Lee | special |
| 11/05/2025 | Final | Max Lee | progress |
| 11/05/2025 | Energy Code Compliance Inspections | Max Lee | progress |
| 11/05/2025 | Maintenance information | Max Lee | energy_progress |
| 11/05/2025 | HVAC-R and service water heating system controls | Max Lee | energy_progress |
| 11/05/2025 | HVAC-R and service water piping design and insulation | Max Lee | energy_progress |
| 11/05/2025 | Duct leakage testing, insulation and design | Max Lee | energy_progress |
| 10/31/2025 | Tenant Protection Plan Compliance | Max Lee | special |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 10/22/2025 | Tenant Protection Plan Compliance | Max Lee | special |
| 10/22/2025 | Final | Max Lee | progress |
| 10/22/2025 | Fire-Resistance Rated Construction | Max Lee | progress |
| 10/22/2025 | Fenestration air leakage | Max Lee | energy_progress |
| 10/22/2025 | Fenestration and door U-factor and product ratings | Max Lee | energy_progress |
| 10/22/2025 | Fenestration areas | Max Lee | energy_progress |
| 10/22/2025 | Interior lighting power | Max Lee | energy_progress |
| 10/22/2025 | Lighting in dwelling units | Max Lee | energy_progress |
| 10/22/2025 | Final | Max Lee | progress |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | Max Lee | special |
| 10/22/2025 | Mechanical Systems | Max Lee | special |
| 10/22/2025 | Tenant Protection Plan Compliance | Max Lee | special |
| 10/22/2025 | Energy Code Compliance Inspections | Max Lee | progress |