| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/15/2016 | $395K | — | 203 ROBINSON AVENUE REALTY CORP → Private party | $346/sf building |
| 08/31/2015 | $240K | — | Private party → 203 ROBINSON AVENUE REALTY CORP. | $210/sf building |
| 02/09/2015 | $463K | — | — → — | $407/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| C2B ARCHITECTS PC | 5 | 08/04/2026 |
| JM CONSULTING ENGINEERS, LLC | 2 | 05/01/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZEFI & CO. LLC | General Contractor | 2 | 09/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Permit Issued | ZEFI & CO. LLC | 09/23/2026 |
| DOB NOW | Construction Fence | Permit Issued | ZEFI & CO. LLC | 08/14/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | ZEFI & CO. LLC | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | ZEFI & CO. LLC | Steel, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | ZEFI & CO. LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2026 | Demolition | — | special |
| 07/15/2026 | Air barrier — testing | — | energy_progress |
| 05/01/2026 | Energy Code Compliance Inspections | — | progress |
| 05/01/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 05/01/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 05/01/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 05/01/2026 | Maintenance information | — | energy_progress |
| 05/01/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 04/30/2026 | Insulation placement and R values | — | energy_progress |
| 04/30/2026 | Exterior lighting power | — | energy_progress |
| 04/30/2026 | Fenestration areas | — | energy_progress |
| 04/30/2026 | Fenestration air leakage | — | energy_progress |
| 04/30/2026 | Lighting controls | — | energy_progress |
| 04/30/2026 | Air barrier - visual inspection | — | energy_progress |
| 04/30/2026 | Interior lighting power | — | energy_progress |
| 04/30/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 04/30/2026 | Air barrier continuity plan testing | — | energy_progress |
| 04/30/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 04/30/2026 | Maintenance information | — | energy_progress |
| 04/30/2026 | Metering | — | energy_progress |
| 04/30/2026 | Concrete - Cast-In-Place | — | special |
| 04/30/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/30/2026 | Concrete - Cast-In-Place | — | special |
| 04/30/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 04/30/2026 | Masonry | — | special |