Elevator apt, semi-fireproof without stores
303 EAST 71 STREET
💬 Discuss this project
1948Year Built
6Stories
D1Building Class
R8BZoning
43,288 sfGross Floor Area
49Units
LL97 CoveredRent Stabilized2 Open Violations 1 unresolved · 1 paperwork only ▸FISP: SWARMP
Elevator apt, semi-fireproof without stores · 10,216 sf lot · 4.24 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction13p · 2 filings · 20 docs
Floor 6Under Construction1p · 1 filing · 20 docs
Floor 5Under Construction1p · 1 filing · 20 docs
Floor 4Under Construction1p · 1 filing · 20 docs
Floor 3Under Construction1p · 1 filing · 20 docs
Floor 2Under Construction1p · 1 filing · 20 docs
Floor 1Under Construction1p · 1 filing · 20 docs
CellarUnder Construction8p · 1 filing · 20 docs
Site & exterior19p · 4 filings · 19 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MSKCC706/28/2026
PLATINUM SERVICES NY503/22/2026
S K I REALTY203/21/2026
MEMORIAL HOSPITAL FOR CANCER AND ALLIED DISEASES203/21/2026
MEMORIALSLOANKETTERING103/21/2026
MEMORIAL HOSPITAL FOR CANCER103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SATO CONSTRUCTION603/21/2026
P WOLFE CONSULTANTS403/21/2026
NEW YORK ENGINEERING ASSOCIATES P603/21/2026
SYNERGY BUILDING CONSULTANTS103/21/2026
AE DESIGN SOLUTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EVEREST SCAFFOLDING INCGeneral Contractor403/21/2026
PLATINUM SERVICES NY LLCGeneral Contractor303/21/2026
SATO CONSTRUCTION CO.INCGeneral Contractor204/09/2026
THE METRO GROUP PLBG LLCPlumbing206/28/2026
ARSENAL SCAFFOLD INCGeneral Contractor104/09/2026
RADOS MILOJKOVICElectrical103/21/2026
THE METRO GROUP, INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NEW YORK ENGINEERING ASSO851306/20/2025
ALAN MARGOLIN & ASSOC423212/05/2024
CANY ARCHITECTURE & ENGIN1125212/05/2024
Building Lifecycle
All (122)Filed (11)Permit Issued (13)Signed Off (4)Facade (FISP) (24)Violation (41)Inspection (6)Objection (4)Special Inspection (19)
04/30/2026
Signed off — Alteration
Installation of temporary adjacent overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01260378-I1
04/09/2026
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
02/17/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
12/01/2025
Cycle 10 facade report signed — SAFE
10/24/2025
Cycle 10 facade report submitted
10/22/2025
Signed off — Alteration
FILING FOR FACADE RESTORATION WORK - FISP CYCLE 9A REPAIRS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01019731-I1
10/13/2025
Signed off — Alteration
Submitting an Amendment CD5.
M01027136-I1
10/01/2025
Cycle 10 facade inspection completed
09/05/2025
Filed — Alteration
Installation of temporary adjacent overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01260378-I1
09/05/2025
Permit issued — Protection and Mechanical Methods
M01260378-I1-PMM
08/22/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/08/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/30/2025
Permit issued — Boiler Equipment
M01228265-I1-BE
06/30/2025
Permit issued — General Construction
M01228265-S2-GC
06/27/2025
Permit issued — Plumbing
M01228265-S1-PL
06/20/2025
Filed — Alteration
INSTALL NEW GAS SERVICE, METER AND PIPING AND CONNECT TO REPLACEMENT GAS BURNER.
M01228265-S2
06/20/2025
Filed — Alteration
INSTALL NEW GAS SERVICE, METER AND PIPING AND CONNECT TO REPLACEMENT GAS BURNER.
M01228265-I1
06/20/2025
Filed — Alteration
INSTALL NEW GAS SERVICE, METER AND PIPING AND CONNECT TO REPLACEMENT GAS BURNER.
M01228265-S1
05/19/2025
Special inspection requirement — Final
LOUIS ARENA
05/19/2025
Special inspection requirement — Maintenance information
LOUIS ARENA
05/19/2025
Special inspection requirement — HVAC-R and service water heating system controls
LOUIS ARENA
05/19/2025
Special inspection requirement — HVAC-R and service water heating equipment
LOUIS ARENA
05/19/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
LOUIS ARENA
05/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
LOUIS ARENA
05/19/2025
Special inspection requirement — Tenant Protection Plan Compliance
LOUIS ARENA
05/19/2025
Special inspection requirement — Chimneys and vents
LOUIS ARENA
05/19/2025
Special inspection requirement — Tenant Protection Plan Compliance
LOUIS ARENA
05/19/2025
Special inspection requirement — Heating Systems
LOUIS ARENA
05/19/2025
Special inspection requirement — Tenant Protection Plan Compliance
LOUIS ARENA
03/20/2025
Permit issued — Suspended Scaffold
M01027136-I1-SC
03/14/2025
Permit issued — Structural
M01019731-I1-GC-CX
01/29/2025
Violation issued (ECB, open)
Construction
12/05/2024
Filed — Alteration
FILING FOR FACADE RESTORATION WORK - FISP CYCLE 9A REPAIRS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01019731-P1
12/05/2024
Special inspection requirement — Masonry
VINCENT ORTIZ
12/05/2024
Special inspection requirement — Post-installed Anchors
Young Suh
12/05/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Young Suh
12/05/2024
Special inspection requirement — Tenant Protection Plan Compliance
Young Suh
12/05/2024
Special inspection requirement — Final
Ivan Zurkiwskyj
11/15/2024
Cycle 9 facade report submitted
11/14/2024
Cycle 9 facade report signed — SWARMP
11/07/2024
Cycle 9 facade inspection completed
07/26/2024
Permit issued — Suspended Scaffold
M01027136-P2-SC
07/26/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
07/23/2024
Filed — Alteration
Submitting an Amendment CD5.
M01027136-P2
07/23/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
JAMES NAPOLI
07/03/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/02/2024
Permit issued — Suspended Scaffold
M01027136-P1-SC
06/28/2024
Objection resolved — Addressed
06/27/2024
Objection raised — Other
06/18/2024
Filed — Alteration
Submitting an Amendment CD5.
M01027136-P1
05/14/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/19/2024
Permit issued — Suspended Scaffold
M01027136-I1-SC
04/16/2024
Objection raised — Other
04/16/2024
Objection resolved — Addressed
04/11/2024
Permit issued — General Construction
M01019731-I1-GC-CX
04/03/2024
Permit issued — Sidewalk Shed
M01026110-I1-SH
04/02/2024
Filed — Alteration
INSTALLATION OF 300PSF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE 2022. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01026110-I1
03/28/2024
Filed — Alteration
Submitting an Amendment CD5.
M01027136-I1
03/14/2024
Filed — Alteration
FILING FOR FACADE RESTORATION WORK - FISP CYCLE 9A REPAIRS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01019731-I1
11/01/2023
Cycle 9 facade report submitted
Latest 60 of 122 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsSigned-offARSENAL SCAFFOLD INC09/05/2025
DOB NOWBoiler EquipmentPermit IssuedTHE METRO GROUP PLBG LLC06/30/2025
DOB NOWGeneral ConstructionPermit IssuedTHE METRO GROUP, INC06/30/2025
DOB NOWPlumbingPermit IssuedTHE METRO GROUP PLBG LLC06/27/2025
DOB NOWSuspended ScaffoldSigned-offSATO CONSTRUCTION CO. INC03/20/2025
DOB NOWStructuralSigned-offSATO CONSTRUCTION CO.INC03/14/2025
DOB NOWSuspended ScaffoldPermit IssuedSATO CONSTRUCTION CO. INC07/26/2024
DOB NOWSuspended ScaffoldPermit IssuedSATO CONSTRUCTION CO. INC07/02/2024
DOB NOWSuspended ScaffoldSigned-offSATO CONSTRUCTION CO. INC04/19/2024
DOB NOWGeneral ConstructionSigned-offSATO CONSTRUCTION CO.INC04/11/2024
DOB NOWSidewalk ShedPermit IssuedPLATINUM SERVICES NY LLC04/03/2024
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC03/21/2018
DOB NOWSidewalk ShedSigned-offEVEREST SCAFFOLDING INC11/09/2017
BISOTISSUEDJ. GIARNELLA & SONS II, I06/29/2018
BISOTISSUEDJ. GIARNELLA & SONS II, I10/05/2017
BISEQISSUEDROCKLEDGE SCAFFOLD CORP08/21/2015
BISOTISSUEDDEERPATH CONSTRUCTION06/04/2007
BISEQISSUEDCLARK & WILKINS INDUSTRIES, INC.11/21/2005
BISEQISSUEDATLANTIC HEYDT SCAFFOLD CORP04/05/2000
BISOTISSUEDJ. GIARNELLA AND SON03/24/2000
BISEQISSUEDJ. GIARNELLA AND SON02/23/2000
BISOTISSUEDJ. GIARNELLA AND SON11/04/1999
BISEQISSUEDJ. GIARNELLA AND SON11/04/1999
BISEQISSUEDATLANTIC HEYDT SCAFFOLD CORP09/28/1999
BISFSISSUEDUNFLAT PEROTTO ASSOCIATES08/04/1997
BISPLISSUEDBMC PLUMBING CORP.06/30/1993
BIS—ISSUEDN.Y.C. BUILDERS GROUP05/26/1993
BISEQISSUEDSWIG STAGING INCORPORATED04/12/1991
1 project · most recent 06/20/2025
Gas
FiledStatusContractorScope
06/20/2025Permit IssuedTHE METRO GROUP PLBG LLCGas
2 projects · most recent 03/27/2024
General Wiring
FiledStatusContractorScope
03/27/2024Permit IssuedILLUMINOUS ELECTRIC CORP.—
08/14/2023Permit IssuedTRI-POWER ELECTRICAL LLCGeneral Wiring
1 project · most recent 04/02/2024
Sidewalk Shed
FiledStatusContractorScope
04/02/2024Permit IssuedPLATINUM SERVICES NY LLCSidewalk Shed
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
04/09/2026Fail-Final Boiler Equipment InspectionFailView ↗
02/17/2026Pass-Final PL - UndergroundPassView ↗
08/22/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/08/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/03/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/14/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
05/19/2025FinalLOUIS ARENAprogress
05/19/2025Maintenance informationLOUIS ARENAenergy_progress
05/19/2025HVAC-R and service water heating system controlsLOUIS ARENAenergy_progress
05/19/2025HVAC-R and service water heating equipmentLOUIS ARENAenergy_progress
05/19/2025HVAC-R and service water piping design and insulationLOUIS ARENAenergy_progress
05/19/2025Fire-Resistant Penetrations and JointsLOUIS ARENAspecial
05/19/2025Tenant Protection Plan ComplianceLOUIS ARENAspecial
05/19/2025Chimneys and ventsLOUIS ARENAspecial
05/19/2025Tenant Protection Plan ComplianceLOUIS ARENAspecial
05/19/2025Heating SystemsLOUIS ARENAspecial
05/19/2025Tenant Protection Plan ComplianceLOUIS ARENAspecial
12/05/2024MasonryVINCENT ORTIZspecial
12/05/2024Post-installed AnchorsYoung Suhspecial
12/05/2024Structural Stability – Alterations of existing buildingsYoung Suhspecial
12/05/2024Tenant Protection Plan ComplianceYoung Suhspecial
12/05/2024FinalIvan Zurkiwskyjprogress
07/26/2024Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
07/23/2024Alternative Materials - OTCR Buildings Bulletin NumberJAMES NAPOLIspecial
10/26/2017FinalPAUL BAILEYprogress
▾Documents — 83 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
09/06/2026M00001266-I1Request digital key ↗
08/27/2026M01019731-P1Request digital key ↗
08/27/2026M01019731-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits5
▸BISWORK PERMIT APPLICATION3
07/09/2018123188148Open ↗
10/06/2017123188148Open ↗
09/01/2015122501514Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
10/05/2017123188148Open ↗
09/01/2015122501514Open ↗
▸Seals & Professional Certifications34
▸DOB NOWSpecial Inspector Seal & Signature10
09/23/2026M01228265-I1Open ↗
09/23/2026M01228265-I1Open ↗
09/02/2026M01027136-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/06/2026M00001266-I1Open ↗
08/27/2026M01019731-I1Open ↗
08/27/2026M01026110-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/23/2026M01228265-I1Open ↗
09/23/2026M01228265-I1Open ↗
09/23/2026M01228265-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
03/01/2019123188148Open ↗
10/05/2017123188148Open ↗
01/09/2016122501514Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
10/05/2017123188148Open ↗
09/01/2015122501514Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
10/05/2017123188148Open ↗
09/01/2015122501514Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/13/2026M01228265-S1Open ↗
08/13/2026M01228265-S2Open ↗
08/13/2026M01228265-I1Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/27/2026M01019731-I1Open ↗
08/13/2026M01019731-P1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/05/2017123188148Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
10/05/2017123188148Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
03/01/2019123188148Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter9
08/27/2026M01019731-I1Open ↗
08/13/2026M01027136-I1Open ↗
08/13/2026M01027136-P2Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
03/01/2019123188148Open ↗
01/09/2016122501514Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/02/2015122501514Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/01/2019123188148Open ↗
10/05/2017123188148Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
10/05/2017123188148Open ↗
09/01/2015122501514Open ↗
▸BISBOROUGH INTAKE FORM1
03/01/2019123188148Open ↗
▸Other Documents8
▸DOB NOWManufacturer's Specifications3
08/13/2026M01027136-I1Open ↗
08/13/2026M01027136-P2Open ↗
08/13/2026M01027136-P1Open ↗
▸DOB NOWCalculations3
08/13/2026M01027136-I1Open ↗
08/13/2026M01027136-P1Open ↗
08/13/2026M01027136-P2Open ↗
▸BISSupporting Document: Fee Exempt1
01/09/2016122501514Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
10/05/2017123188148Open ↗