| Owner | Filings | Most Recent |
|---|---|---|
| CHUNGLY DEVELOPMENT | 19 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ZHENG & ASSOCIATES LLC | 4 | 05/19/2025 |
| CX CONSULTING CORP | 1 | 10/18/2023 |
| GREYSTONE ENGINEERING CONSULTING,PC | 2 | 03/29/2022 |
| MW PROFESSIONAL ENGINEERING, P.C. | 1 | 12/31/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| STUDIO HUASHI | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRESTIGE TEAM WORK INC | General Contractor | 3 | 03/21/2026 |
| LAILE INC | General Contractor | 2 | 03/21/2026 |
| STANDARD CONSTRUCTION COR | General Contractor | 2 | 03/21/2026 |
| FALCONET MANAGEMENT INC | General Contractor | 1 | 07/08/2026 |
| ZAQ CONSTRUCTION INC | General Contractor | 1 | 04/09/2026 |
| HP SERVICES INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ZHENG & ASSOCIATES LLC | 7330 | 4 | 05/19/2025 |
| GREYSTONE ENGINEERING CON | 2973 | 2 | 03/29/2022 |
| MW PROFESSIONAL ENGINEERI | 570 | 1 | 12/31/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HP SERVICES INC | 08/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | ZAQ CONSTRUCTION INC | 08/20/2024 |
| DOB NOW | General Construction | Signed-off | PRESTIGE TEAM WORK INC | 10/24/2023 |
| DOB NOW | General Construction | Signed-off | FALCONET MANAGEMENT INC | 04/29/2022 |
| DOB NOW | General Construction | Signed-off | STANDARD CONSTRUCTION COR | 01/07/2022 |
| DOB NOW | General Construction | Signed-off | LAILE INC | 02/03/2021 |
| BIS | PL | ISSUED | B.H. PLUMBING & HEATING CORP | 07/12/2006 |
| BIS | MH | ISSUED | JNL CONSTRUCTION INC | 07/10/2006 |
| BIS | PL | ISSUED | FLYTIGER P & H LTD | 05/08/2000 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/16/2025 | Permit Issued | HP SERVICES INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2020 | Complete | ALL WAYS ELECTRIC CORP.W | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/15/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/16/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/29/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/06/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/20/2025 | Electrical motors and elevators | Jinfar Liu | energy_progress |
| 05/20/2025 | Interior lighting power | Jinfar Liu | energy_progress |
| 05/20/2025 | Metering | Jinfar Liu | energy_progress |
| 05/20/2025 | Lighting controls | Jinfar Liu | energy_progress |
| 05/20/2025 | Final | Jinfar Liu | progress |
| 05/20/2025 | Mechanical Systems | Jinfar Liu | special |
| 05/20/2025 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 05/15/2025 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 05/15/2025 | Mechanical Systems | Jinfar Liu | special |
| 05/15/2025 | Final | Jinfar Liu | progress |
| 05/15/2025 | Lighting controls | Jinfar Liu | energy_progress |
| 05/15/2025 | Electrical motors and elevators | Jinfar Liu | energy_progress |
| 05/15/2025 | Metering | Jinfar Liu | energy_progress |
| 05/15/2025 | Interior lighting power | Jinfar Liu | energy_progress |
| 01/16/2025 | Fire-Resistant Penetrations and Joints | Jinfar Liu | special |
| 01/16/2025 | Electrical motors and elevators | Jinfar Liu | energy_progress |
| 01/16/2025 | Metering | Jinfar Liu | energy_progress |
| 01/16/2025 | Energy Code Compliance Inspections | Jinfar Liu | progress |
| 03/30/2022 | Air barrier - visual inspection | TIMOTHY TWEEDY | energy_progress |
| 03/30/2022 | Structural Stability – Alterations of existing buildings | TIMOTHY TWEEDY | special |
| 03/30/2022 | Masonry | TIMOTHY TWEEDY | special |
| 03/30/2022 | Fire-Resistant Penetrations and Joints | TIMOTHY TWEEDY | special |
| 03/30/2022 | Final | TIMOTHY TWEEDY | progress |
| 03/30/2022 | Energy Code Compliance | TIMOTHY TWEEDY | progress |
| 03/30/2022 | Insulation placement and R values | TIMOTHY TWEEDY | energy_progress |