| Owner | Filings | Most Recent |
|---|---|---|
| WEST SIDE MANAGEMENT | 6 | 07/08/2026 |
| 303 WEST 76TH STREET, LLC | 3 | 03/22/2026 |
| 303 WEST 76 STREET | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/23/2014 | $7.0M | — | 303 GS LLC → 303 WEST 76TH STREET, LLC | $1,218/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BAILEYS ENGINEERING PC | 2 | 03/28/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EVEREST SCAFFOLDING INC | General Contractor | 3 | 07/08/2026 |
| SEABRAVE ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | EVEREST SCAFFOLDING INC | 03/28/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | EVEREST SCAFFOLDING INC | 03/22/2019 |
| BIS | OT | ISSUED | BRUSCO CONTRACTING CORP | 04/10/2020 |
| BIS | PL | ISSUED | COPPER PLUMBING INC | 04/03/2019 |
| BIS | OT | ISSUED | BRUSCO CONTRACTING CORP | 03/25/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/09/2019 | Complete | SEABRAVE ELECTRIC CORP | — |
| 07/08/2019 | Complete | SEABRAVE ELECTRIC CORP | General Wiring |
| 05/17/2019 | Complete | ACP ELECTRICAL CONTRACTIN | General Wiring |
| 04/24/2019 | Complete | ACP ELECTRICAL CONTRACTIN | General Wiring |
| 03/28/2019 | Complete | ACP ELECTRICAL CONTRACTIN | General Wiring |
| 03/21/2019 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 03/01/2019 | Complete | ACP ELECTRICAL CONTRACTIN | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/20/2019 | Final | PAUL BAILEY | progress |