1975Year Built
1Stories
RWBuilding Class
M1-1Zoning
291,454 sfGross Floor Area
2Units
LL97 Covered0 Open Violations
Condo, warehouse / factory / industrial · Owner of record: ALLOMATIC INDUSTRIES INC · 145,489 sf lot · 2 FAR built · Flood zone X
Locations of Work
MechanicalPlumbingFire Protection
Roof4p · 3 filings · 15 docs
Floor 12p · 2 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ASN1507/08/2026
BNS REAL ESTATE907/08/2026
BRADFORD SWETT MANAGEMENT LLC407/08/2026
BMS MANAGEMENT103/22/2026
DOLTON ASSOCIATES2303/21/2026
30-30 60 STREET403/21/2026
30-30 60TH STREET1203/21/2026
BRADFORD SWETT REALTY203/21/2026
ALLOMATIC INDUSTRIES403/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STRACAR ENGINEERING P C1203/21/2026
VINCENT J. LIOTTA P.E.203/21/2026
P.WOLFE CONSULTANTS, INC.103/21/2026
LOUIS STRIAR203/21/2026
VINCENT J. LIOTTA P. E.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ECONOMY P & H CO.,INCPlumbing207/08/2026
TOUGH STALLION LLCElectrical203/21/2026
BIRNBAUM, ALANElectrical203/21/2026
HKS CONSTRUCTION CORPGeneral Contractor107/08/2026
MOREAIR MECHANICAL SERVICGeneral Contractor107/08/2026
J.G.C PLBG & HTG INCPlumbing107/08/2026
SIGNSTAR NYCScaffold107/08/2026
SHUIR ELEC'L CONTR'S CORPElectrical103/22/2026
APPROVED FIRE PREV. CORPFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
VINCENT J. LIOTTA P. E.1974112/21/2020
STRACAR SPECIAL INSPECTIO229206/30/2020
Building Lifecycle
All (49)Filed (10)Permit Issued (7)Signed Off (7)Violation (6)Inspection (6)Objection (10)Special Inspection (3)
03/20/2023
Signed off — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661499-I1
03/20/2023
Signed off — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661483-I1
08/12/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/28/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/25/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
07/13/2022
Filed — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661499-P2
06/17/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/19/2022
Filed — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661499-P1
02/04/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/01/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/27/2022
Permit issued — Plumbing
Q00661483-I1-PL
01/25/2022
Permit issued — Plumbing
Q00661499-I1-PL
01/20/2022
Filed — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661499-I1
01/19/2022
Filed — Alteration
REPAIR GAS PIPING LEAKS AS PER PLAN
Q00661483-I1
09/16/2021
Signed off — Alteration
NON ILLUMINATED NON ADVERTISING ACCESSORY WALL SIGN - IN PROPERTY LINES - WHITE CAP.
Q00568571-I1
08/11/2021
Permit issued — Sign
Q00568571-I1-SG
08/09/2021
Filed — Alteration
NON ILLUMINATED NON ADVERTISING ACCESSORY WALL SIGN - IN PROPERTY LINES - WHITE CAP.
Q00568571-I1
08/09/2021
Special inspection requirement — Final
FRANK VILLANO
05/20/2021
Signed off — Alteration
SPRINKLER SYSTEM MODIFIED AS PER PLANS FILED TO SUPERSEDE APPLICATION #400561192
Q00210083-I1
03/03/2021
Signed off — Alteration
Q00447921-I1
03/02/2021
Signed off — Alteration
Q00443263-I1
02/22/2021
Permit issued — Plumbing
Q00447921-I1-PL
02/17/2021
Filed — Alteration
Q00447921-I1
12/30/2020
Permit issued — Mechanical Systems
Q00443263-I1-MS
12/21/2020
Filed — Alteration
Q00443263-I1
07/01/2020
Special inspection requirement — Sprinkler Systems
MIRO Stracar
06/30/2020
Filed — Alteration
SPRINKLER SYSTEM MODIFIED AS PER PLANS FILED TO SUPERSEDE APPLICATION #400561192
Q00210083-P1
06/30/2020
Special inspection requirement — Sprinkler Systems
MIRO Stracar
02/10/2020
Permit issued — Sprinklers
Q00210083-I1-EW-SP
10/08/2019
Filed — Alteration
SPRINKLER SYSTEM MODIFIED AS PER PLANS FILED TO SUPERSEDE APPLICATION #400561192
Q00210083-I1
09/09/2019
Signed off — Alteration
HEREWITH FILING A CURB-CUT. THIS APPLICATION IS FILED TO SUPERSEDE APPROVED APPLICATION # 420982253.
Q00030114-I1
09/18/2018
Permit issued — Curb Cut
Q00030114-I1-CC
05/30/2018
Objection raised — Other
05/30/2018
Objection resolved — Addressed
05/30/2018
Objection raised — Other
05/30/2018
Objection resolved — Addressed
05/25/2018
Filed — Alteration
HEREWITH FILING A CURB-CUT. THIS APPLICATION IS FILED TO SUPERSEDE APPROVED APPLICATION # 420982253.
Q00030114-I1
05/25/2018
Objection raised — BC 2014, DOT 2010-CC BC Chapt
05/25/2018
Objection resolved — Addressed
05/25/2018
Objection raised — Other
05/25/2018
Objection resolved — Addressed
05/25/2018
Objection raised — AC 2014, DOT 2010-CC AC 28-104
05/25/2018
Objection resolved — Addressed
06/28/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/28/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/28/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/28/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/19/1990
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/07/1989
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offECONOMY P & H CO.,INC01/27/2022
DOB NOWPlumbingSigned-offECONOMY P & H CO.,INC01/25/2022
DOB NOWSignSigned-offSIGNSTAR NYC08/11/2021
DOB NOWPlumbingSigned-offJ.G.C PLBG & HTG INC02/22/2021
DOB NOWMechanical SystemsSigned-offMOREAIR MECHANICAL SERVIC12/30/2020
DOB NOWSprinklersSigned-offAPPROVED FIRE PREV. CORP02/10/2020
DOB NOWCurb CutSigned-offHKS CONSTRUCTION CORP09/18/2018
BISPLISSUEDECONOMY P & H CO.,INC05/01/2023
BISPLISSUEDECONOMY P & H CO.,INC05/01/2023
BISMHISSUEDCHELSEA DEVELOPMENT INC05/01/2023
BISPLISSUEDECONOMY P & H CO.,INC05/07/2020
BISPLISSUEDECONOMY P & H CO.,INC03/13/2019
BISMHISSUEDUNITED INDUSTRIAL INC02/07/2019
BISSPISSUEDCAPITOL FIRE SPKL CO,INC03/08/2018
BISSPISSUEDAPPROVED FIRE PREV. CORP03/06/2018
BISOTISSUEDHKS CONSTRUCTION CORP01/17/2018
BISOTISSUEDCHELSEA DEVELOPMENT INC10/19/2017
BISPLISSUEDECONOMY P & H CO.,INC09/01/2017
BISPLISSUEDECONOMY P & H CO.,INC03/31/2017
BISSPISSUEDCAPITOL FIRE SPKL CO,INC03/07/2017
BISSPISSUEDAPPROVED FIRE PREV. CORP12/12/2016
BISOTISSUEDCHELSEA DEVELOPMENT INC12/09/2016
BISSPISSUEDCAPITOL FIRE SPKL CO,INC10/26/2015
BISOTISSUEDCHELSEA DEVELOPMENT INC03/03/2015
BISMHISSUEDMOREAIR MECHANICAL SERVIC12/04/2014
BIS—ISSUEDACTIVE SIGNS INC12/01/2014
BIS—ISSUEDSIGNSTAR NYC10/23/2014
BIS—ISSUEDSIGNSTAR NYC10/23/2014
BISOTISSUEDCHELSEA DEVELOPMENT INC09/26/2014
BISEQISSUEDCHELSEA DEVELOPMENT INC09/26/2014
BISPLISSUEDECONOMY P & H CO.,INC07/05/2014
BISEQISSUEDB H & B CONSTRUCTION INC06/25/2014
BISOTISSUEDB H & B CONSTRUCTION INC06/25/2014
BISOTISSUEDONFORCE SOLAR, INC05/07/2013
BIS—ISSUEDINTERBORO SIGN & ELECL MA02/12/2013
BIS—ISSUEDINTERBORO SIGN & ELECL MA02/12/2013
BISOTISSUEDBETON BUILDERS INC02/03/2011
BIS—ISSUEDMAUCERI SIGN CO., INC12/23/2009
BISOTISSUEDECONOMY PLUMBING & HEATING CORP01/11/2005
BISPLISSUEDECONOMY P & H CO.,INC12/21/2004
+ 8 more permits on file
3 projects · most recent 11/17/2024
General Wiring
FiledStatusContractorScope
11/17/2024Permit IssuedZJ ELECTRICAL CORPGeneral Wiring
02/02/2022CompleteSHUIR ELEC'L CONTR'S CORP—
01/12/2018CompleteSHUIR ELEC'L CONTR'S CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
08/12/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/28/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/25/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/04/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
08/09/2021FinalFRANK VILLANOprogress
07/01/2020Sprinkler SystemsMIRO Stracarspecial
06/30/2020Sprinkler SystemsMIRO Stracarspecial
▾Documents — 453 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch6
08/27/2026Q00568571-I1Request digital key ↗
08/26/2026Q00661483-I1Request digital key ↗
08/26/2026Q00661499-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler2
08/28/2026Q00210083-I1Request digital key ↗
08/15/2026Q00210083-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/27/2026Q00443263-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/27/2026Q00447921-I1Request digital key ↗
▸Applications & Permits92
▸BISPLAN / WORK APPROVAL APPLICATION62
06/23/2023440151336Open ↗
06/03/2023440151336Open ↗
05/11/2023440151336Open ↗
Showing 3 of 62 on file for this type
▸BISWORK PERMIT APPLICATION29
08/16/2023440151336Open ↗
08/16/2023440151336Open ↗
03/14/2019421726494Open ↗
Showing 3 of 29 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
06/05/2018400477480Open ↗
▸Seals & Professional Certifications94
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION50
09/11/2019400477480Open ↗
09/11/2019400379292Open ↗
09/11/2019400379292Open ↗
Showing 3 of 50 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
12/06/2019440151336Open ↗
02/06/2019421726494Open ↗
12/28/2017420998219Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/28/2026Q00210083-P1Open ↗
08/28/2026Q00210083-I1Open ↗
08/27/2026Q00443263-I1Open ↗
Showing 3 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT9
02/06/2019421726494Open ↗
12/28/2017420998219Open ↗
08/29/2017440430730Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
08/29/2017440430730Open ↗
Showing 1 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION4
08/29/2017440430730Open ↗
Showing 1 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026Q00210083-P1Open ↗
08/25/2026Q00210083-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/23/2026Q00568571-I1Open ↗
▸Trade Schedules & Equipment34
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE15
11/07/2019440151336Open ↗
10/29/2019440151336Open ↗
05/13/2019400379292Open ↗
Showing 3 of 15 on file for this type
▸BISSCHEDULE B - PLUMBING8
05/11/2023440151336Open ↗
07/21/2020421726494Open ↗
06/30/2020421726494Open ↗
Showing 3 of 8 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
04/14/2021421726494Open ↗
02/06/2019421726494Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
04/16/2018440180572Open ↗
▸BISHEATING SYSTEMS1
06/17/2024440151336Open ↗
▸BISEQUIPMENT USE PERMITS1
05/06/2021421726494Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
08/03/2023421407640Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
06/17/2024440151336Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
06/17/2024440151336Open ↗
▸BISPLUMBING (PL) SIGNOFF1
06/17/2024440151336Open ↗
▸Environmental & Asbestos25
▸BISASBESTOS: CERTIFICATION (DEP ACP5)13
02/06/2019421726494Open ↗
12/28/2017420998219Open ↗
08/29/2017440430730Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/28/2026Q00210083-P1Open ↗
08/28/2026Q00210083-I1Open ↗
08/26/2026Q00661499-I1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTHIS IS NOT AN ASBESTOS PROJECT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance37
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS14
09/11/2019400379292Open ↗
09/11/2019400379292Open ↗
05/15/2019400379292Open ↗
Showing 3 of 14 on file for this type
▸BISTR8: Energy Code Progress Inspections4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
04/10/2018420998219Open ↗
12/13/2017440430730Open ↗
Showing 2 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
04/06/2021421726494Open ↗
08/29/2017440430730Open ↗
Showing 2 of 3 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
06/17/2024440151336Open ↗
04/01/2021421726494Open ↗
▸BISNYCECC ANALYSIS2
08/29/2017440430730Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
08/29/2017440430730Open ↗
Showing 1 of 2 on file for this type
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
06/17/2024440151336Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00447921-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026Q00443263-I1Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY3
06/17/2024440151336Open ↗
Showing 1 of 3 on file for this type
▸BISMECHANICAL SYSTEMS2
06/17/2024440151336Open ↗
04/01/2021421726494Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISHYDRO FLOW TEST LETTER2
04/16/2018440180572Open ↗
Showing 1 of 2 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
12/03/2018400477480Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
04/01/2021421726494Open ↗
▸Approvals, Objections & Sign-offs52
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST20
08/23/2023421407640Open ↗
04/14/2021421726494Open ↗
05/15/2019440367265Open ↗
Showing 3 of 20 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE11
05/13/2019400379292Open ↗
01/09/2019400379292Open ↗
01/05/2019400477480Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
08/16/2023440151336Open ↗
06/07/2018420982244Open ↗
10/03/2017440367265Open ↗
Showing 3 of 5 on file for this type
▸BISFINAL2
06/17/2024440151336Open ↗
04/06/2021421726494Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISMECHANICAL (MH) SIGNOFF1
06/17/2024440151336Open ↗
▸BISSUPERSEDING LETTER1
01/24/2023420605937Open ↗
▸DOB NOWOther Documents - Prior to Approval1
08/13/2026Q00030114-I1Open ↗
▸Cost, Insurance & Ownership44
▸BISCOST AFFIDAVIT43
04/01/2021421726494Open ↗
02/06/2019421726494Open ↗
12/01/2018440367265Open ↗
Showing 3 of 43 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
08/18/2023421407640Open ↗
▸Filing & Intake Forms52
▸BISADDITIONAL INFORMATION17
01/28/2021440151336Open ↗
07/21/2020421726494Open ↗
05/15/2019400379292Open ↗
Showing 3 of 17 on file for this type
▸BISEFILING COVER SHEET16
02/06/2019421726494Open ↗
12/28/2017420998219Open ↗
Showing 2 of 16 on file for this type
▸BISBOROUGH INTAKE FORM14
03/23/2019440367265Open ↗
01/29/2019440367265Open ↗
12/01/2018440367265Open ↗
Showing 3 of 14 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET5
08/29/2017440430730Open ↗
Showing 1 of 5 on file for this type
▸Other Documents2
▸BISTax Abatement Miscellaneous2
On file, but not among the 200 most recently loaded documents for this source.