| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/02/2026 | Signed-off | ECOSYSTEM ENERGY SERVICES | Heating and Air Conditioning Systems, Heating Systems | |
| 03/27/2026 | — | — | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2026 | Permit Issued | G. C. PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Permit Issued | NEW YORK CITY ELECT SVCS | General Wiring |
| 03/14/2025 | Permit Issued | NEE ELECTRICAL, LLC | — |
| 06/25/2024 | Complete | SINCHRONY ELECTRIC INC | General Wiring |
| 06/21/2024 | Permit Issued | TOP SHELF ELECTRIC CORP | — |
| 07/19/2022 | Complete | TOP SHELF ELECTRIC CORP | — |
| 08/10/2021 | Complete | AGIR ELEC'L LTD. D/B/A | General Wiring |
| 10/29/2020 | Complete | AGIR ELEC'L LTD. D/B/A | — |
| 09/14/2020 | Permit Issued | ITKIN ELECTRIC CORP. | Boiler Controls |
| 03/25/2020 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 06/11/2019 | Complete | AGIR ELEC'L LTD. D/B/A | — |
| 05/21/2019 | Complete | TOP SHELF ELECTRIC CORP | — |
| 05/17/2019 | Permit Issued | ITKIN ELECTRIC CORP. | Boiler Controls |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2026 | — | — | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2019 | Permit Issued | J & G CONSTRUCTION SRVCS | Scaffold |
| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 4 | 07/08/2026 |
| LENDLEASE US CONSTRUCTION | 1 | 03/22/2026 |
| CONSIGLI ASSOCIATES | 6 | 03/22/2026 |
| CONSIGLIA & ASSOCIATES LL | 1 | 03/22/2026 |
| CONSILI ASSOCIATES LLC | 1 | 03/22/2026 |
| LENDLEASE DEVELOPMENT | 1 | 03/22/2026 |
| LIC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ELECSYS ENGINEERING GROUP | 2 | 04/02/2026 |
| LORING CONSULTING ENGINEERS, INC. | 8 | 03/27/2026 |
| SILMAN | 1 | 03/27/2026 |
| BEYER BLINDER BELLE | 1 | 03/26/2026 |
| ELIZABETH R. LEBER | 3 | 05/31/2024 |
| TOHFAZ UDDIN PE PC | 8 | 08/02/2022 |
| BAILEYS ENGINEERING PC | 1 | 10/03/2019 |
| SYED ENGINEERING, P.C. | 1 | 09/10/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 12 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| ARCHVISION DESIGN STUDIO | 1 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 10 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| AKS CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPRING SCAFFOLDING LLC | General Contractor | 24 | 07/08/2026 |
| KING ROSE OF NY, INC | General Contractor | 5 | 07/08/2026 |
| ECOSYSTEM ENERGY SERVICES | General Contractor | 3 | 03/21/2026 |
| ADRIANO TURBI GARCIA | Electrical | 2 | 03/21/2026 |
| AGIR ELEC'L LTD. D/B/A | Electrical | 2 | 03/22/2026 |
| NEE ELECTRICAL, LLC | Electrical | 1 | 03/22/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 1 | 07/08/2026 |
| JOSEPH SORTINO | Electrical | 1 | 03/21/2026 |
| JOSEPH BRAMAN | Electrical | 1 | 03/21/2026 |
| G. C. PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AHT ENGINEERING PLLC | 8836 | 2 | 04/02/2026 |
| FENAGH, INC | 6942 | 5 | 03/27/2026 |
| CATALPA SPECIAL INSPECTIO | 2004 | 2 | 05/28/2024 |
| ETI CONSULTANTS LLC | 7694 | 2 | 09/04/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | G. C. PLBG & HTG INC | 04/21/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 10/08/2025 |
| DOB NOW | Mechanical Systems | Signed-off | ECOSYSTEM ENERGY SERVICES | 10/03/2025 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 07/26/2024 |
| DOB NOW | Mechanical Systems | Signed-off | KING ROSE OF NY, INC | 08/30/2023 |
| DOB NOW | General Construction | Signed-off | KING ROSE OF NY, INC | 08/16/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 08/02/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 08/02/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 12/09/2020 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 10/20/2020 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 08/18/2020 |
| DOB NOW | Boiler Equipment | Permit Issued | RICHARD MORTMAN | 08/04/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 04/23/2020 |
| DOB NOW | Construction Fence | Signed-off | SPRING SCAFFOLDING LLC | 04/21/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 02/03/2020 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 12/10/2019 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 10/17/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | SPRING SCAFFOLDING LLC | 10/03/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | J & G CONSTRUCTION SVCS | 09/11/2019 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 09/09/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 05/23/2019 |
| DOB NOW | Construction Fence | Signed-off | SPRING SCAFFOLDING LLC | 05/21/2019 |
| BIS | SP | ISSUED | MAGIC MECHANICAL INC | 07/13/2021 |
| BIS | PL | ISSUED | MAGIC MECHANICAL INC | 07/13/2021 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 08/26/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 08/26/2020 |
| BIS | SD | ISSUED | MAGIC MECHANICAL INC | 06/25/2020 |
| BIS | BL | ISSUED | RICHARD MORTMAN | 06/24/2020 |
| BIS | PL | ISSUED | MAGIC MECHANICAL INC | 06/18/2020 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 05/22/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 03/12/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 03/12/2020 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 02/28/2020 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 02/28/2020 |
| BIS | EQ | ISSUED | PRATT CONSTRUCTION & REST | 01/30/2020 |
| BIS | EQ | ISSUED | SPRING SCAFFOLDING LLC | 01/17/2020 |
| BIS | EQ | ISSUED | PRATT CONSTRUCTION & REST | 01/14/2020 |
| BIS | BL | ISSUED | RICHARD MORTMAN | 01/13/2020 |
| BIS | OT | ISSUED | CONSIGLI & ASSOCIATES LLC | 12/31/2019 |
| BIS | OT | ISSUED | SKYLINE RESTORATION INC | 10/15/2019 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/07/2026 | Mechanical Systems | ABRAHAM TAWIL | special |
| 04/07/2026 | Final | ABRAHAM TAWIL | progress |
| 04/07/2026 | Fire-Resistance Rated Construction | ABRAHAM TAWIL | progress |
| 04/07/2026 | Fire-Resistant Penetrations and Joints | ABRAHAM TAWIL | special |
| 04/07/2026 | Tenant Protection Plan Compliance | ABRAHAM TAWIL | special |
| 03/24/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Fire-Resistance Rated Construction | AILANTO DANIEL MINAWI | progress |
| 03/20/2026 | Structural Steel - High Strength Bolting | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Structural Steel - Details | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Final | Carmen Menocal | progress |
| 03/20/2026 | Structural Steel - Welding | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Post-installed Anchors | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Structural Stability – Alterations of existing buildings | AILANTO DANIEL MINAWI | special |
| 03/20/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 03/16/2026 | Final | AILANTO DANIEL MINAWI | progress |
| 03/10/2026 | Final | AILANTO DANIEL MINAWI | progress |
| 03/10/2026 | Mechanical Systems | AILANTO DANIEL MINAWI | special |
| 03/10/2026 | Sprinkler Systems | AILANTO DANIEL MINAWI | special |
| 02/05/2026 | Final | ABRAHAM TAWIL | progress |
| 02/05/2026 | Fire-Resistant Penetrations and Joints | ABRAHAM TAWIL | special |
| 02/05/2026 | Mechanical Systems | ABRAHAM TAWIL | special |
| 02/05/2026 | Tenant Protection Plan Compliance | — | special |
| 02/05/2026 | Fire-Resistance Rated Construction | ABRAHAM TAWIL | progress |
| 06/05/2024 | Final | Elizabeth Leber | progress |