Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE PURSUANT TO SECTION AC 28-111 AND BUILDINGS BULLETIN 2010-002 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 1 drawing sheet
INSTALLATION OF PIPE SCAFFOLDING, NEEDLE BEAMS, OVERHEAD PROTECTION AND ROOF OF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 3 drawing sheets
TEMPORARY SUSPENDED SCAFFOLD AS PER DRAWINGS. SUSPENDED SCAFFOLD SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 101 filing
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
TEMPORARY SUSPENDED SCAFFOLD AS PER DRAWINGS. SUSPENDED SCAFFOLD SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 9
Floor 8
Floor 71p · 1 filing
ArchitectureFire ProtectionMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR A SALES OFFICE PURSUANT TO SECTION AC 28-111 AND BUILDINGS BULLETIN 2010-002 AS SHOWN ON DRAWINGS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 1 drawing sheet
Floor 6
Floor 5
Floor 4
Floor 3
Floor 21p · 1 filing
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe
INSTALLATION OF PIPE SCAFFOLDING, NEEDLE BEAMS, OVERHEAD PROTECTION AND ROOF OF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 1 drawing sheet
Floor 11p · 1 filing
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers · Standpipe
INSTALLATION OF PIPE SCAFFOLDING, NEEDLE BEAMS, OVERHEAD PROTECTION AND ROOF OF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 1 drawing sheet
Site & exterior3 filings · 20 docs
ArchitectureCivilElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold
Installation of a construction fence and Sidewalk Shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
On file for this project
4 documents · 12 drawing sheets
INSTALLATION OF PIPE SCAFFOLDING, NEEDLE BEAMS, OVERHEAD PROTECTION AND ROOF OF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
10 documents · 12 drawing sheets
INSTALLATION OF AN EMERGENCY HEAVY DUTY SIDEWALK SHED AS PER DRAWINGS (SEE COMMENTS SECTION). SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
9 documents · 4 drawing sheets
Filed — no permit issued2 filings · 9 docs
ArchitectureDMGeneralPlumbingStructural
Application is being filed for Plumbing work type for CEL, BAS, 001 through 10 & Roof to supersede all open PL applications (123455803, 123025715, 120534136 & 110240490) at the subject premises. No change in use, egress or occupancy.
On file for this project
6 documents · 12 drawing sheets
Structural Work for CEL, BAS, 001 - 010 & ROF as per plans submitted herewith. This application is to supersede all open Structural applications at the subject premises. There is no change to use, egress or occupancy.