← Back
Two stories - detached, small or mid-size
305 RARITAN AVENUE
STATEN ISLAND · Grasmere-Arrochar-South Beach-Dongan Hills · BIN 5049216
💬 Discuss this project
1965Year Built
2Stories
A1Building Class
R3XZoning
2,748 sfGross Floor Area
1Units
0 Open Violations
Two stories - detached, small or mid-size · 5,000 sf lot · 0.55 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralFire Protection
Floor 11p · 1 filing · 15 docs
Cellar2p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ULTIMATE 1 CONSTRUCTION2807/08/2026
ULTIMATE 1 CONSTRUCTION 1103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
RYAN DESIGN ARCHITECTURE711/13/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
TOTAL EXPEDITING1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ULTIMATE 1 CONSTRUCTION IGeneral Contractor407/08/2026
DPH PLUMBING & HTG CORPPlumbing407/08/2026
SO PLUMBING & HEATING INCPlumbing107/08/2026
Building Lifecycle
All (46)Filed (7)Permit Issued (7)Signed Off (3)Violation (4)Inspection (5)Objection (8)Special Inspection (12)
06/12/2024
Signed off — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-I1
02/26/2024
Signed off — Alteration
S00323642-I1
02/23/2024
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/13/2024
Permit issued — Plumbing
S00411055-I1-PL
12/04/2023
Special inspection requirement — HVAC and service water heating system controls
Daniel Ryan
12/04/2023
Special inspection requirement — HVAC and service water heating equipment
Daniel Ryan
12/04/2023
Special inspection requirement — HVAC insulation and sealing
Daniel Ryan
11/15/2023
Permit issued — Curb Cut
S00323642-I1-CC
11/13/2023
Filed — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-P4
11/10/2023
Special inspection requirement — HVAC insulation and sealing
Daniel Ryan
11/10/2023
Special inspection requirement — HVAC and service water heating system controls
Daniel Ryan
11/10/2023
Special inspection requirement — HVAC and service water heating equipment
Daniel Ryan
11/01/2023
Signed off — Alteration
TEMPORARY FENCE
S00323677-I1
08/08/2023
Permit issued — Plumbing
S45963264-I1-PL
08/02/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
06/29/2023
Filed — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-P3
05/04/2023
Special inspection requirement — HVAC insulation and sealing
Daniel Ryan
05/04/2023
Special inspection requirement — HVAC and service water heating equipment
Daniel Ryan
05/04/2023
Special inspection requirement — HVAC and service water heating system controls
Daniel Ryan
04/06/2023
Objection resolved — Addressed
11/18/2022
Objection raised — Scope
11/09/2022
Filed — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-P2
10/31/2022
Special inspection requirement — HVAC and service water heating equipment
Daniel Ryan
10/31/2022
Special inspection requirement — HVAC and service water heating system controls
Daniel Ryan
10/31/2022
Special inspection requirement — HVAC insulation and sealing
Daniel Ryan
09/13/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/03/2022
Permit issued — Plumbing
S45963264-I1-PL
11/03/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/26/2021
Inspection — Certified Sprinkler (PL)-Sprinkler-Hydro
Certified
View inspection ↗
09/24/2021
Objection resolved — Addressed
09/15/2021
Objection raised — Scope
08/23/2021
Filed — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-P1
07/06/2021
Permit issued — Plumbing
S45963264-I1-PL
04/14/2021
Violation issued (ECB, closed)
Unknown
04/14/2021
Violation issued (ECB, closed)
Site Safety
03/29/2021
Violation issued (ECB, closed)
Unknown
03/29/2021
Violation issued (ECB, closed)
Unknown
03/03/2021
Permit issued — Plumbing
S00411055-I1-PL
12/07/2020
Permit issued — Construction Fence
S00323677-I1-FN
10/28/2020
Objection raised — Inspections
10/28/2020
Objection resolved — Addressed
10/28/2020
Objection raised — Other
10/28/2020
Objection resolved — Addressed
10/27/2020
Filed — Alteration
PLUMBING AND SPRINKLER FILED UNDER THIS APPLICATION
S00411055-I1
10/22/2020
Filed — Alteration
S00323642-I1
10/22/2020
Filed — Alteration
TEMPORARY FENCE
S00323677-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP02/13/2024
DOB NOWCurb CutSigned-offULTIMATE 1 CONSTRUCTION I11/15/2023
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP08/08/2023
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP08/03/2022
DOB NOWPlumbingSigned-offDPH PLUMBING & HTG CORP07/06/2021
DOB NOWPlumbingSigned-offNICHOLAS SUIDA03/03/2021
DOB NOWConstruction FenceSigned-offULTIMATE 1 CONSTRUCTION I12/07/2020
BIS—ISSUEDULTIMATE 1 CONSTRUCTION I12/17/2020
1 project · most recent 05/12/2022
General Wiring
FiledStatusContractorScope
05/12/2022CompleteBRANDL ELECTRIC INC.General Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
02/23/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
08/02/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
09/13/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/03/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/26/2021Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
12/04/2023HVAC and service water heating system controls Daniel Ryanenergy_progress
12/04/2023HVAC and service water heating equipment Daniel Ryanenergy_progress
12/04/2023HVAC insulation and sealing Daniel Ryanenergy_progress
11/10/2023HVAC insulation and sealing Daniel Ryanenergy_progress
11/10/2023HVAC and service water heating system controls Daniel Ryanenergy_progress
11/10/2023HVAC and service water heating equipment Daniel Ryanenergy_progress
05/04/2023HVAC insulation and sealing Daniel Ryanenergy_progress
05/04/2023HVAC and service water heating equipment Daniel Ryanenergy_progress
05/04/2023HVAC and service water heating system controls Daniel Ryanenergy_progress
10/31/2022HVAC and service water heating equipment Daniel Ryanenergy_progress
10/31/2022HVAC and service water heating system controls Daniel Ryanenergy_progress
10/31/2022HVAC insulation and sealing Daniel Ryanenergy_progress
▾Documents — 103 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch - Curb Cut1
08/25/2026S00323642-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/15/2026S00323677-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION13
01/07/2025540181952Open ↗
11/14/2024540181952Open ↗
10/25/2024540181952Open ↗
Showing 3 of 13 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
07/28/2023540181952Open ↗
▸BISWORK PERMIT APPLICATION1
12/17/2020540181952Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
03/06/2020520399060Open ↗
▸Zoning, Tax Lot & Property Records4
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
10/21/2020540181952Open ↗
▸BISVERIFY TAX LOT1
12/04/2023540181952Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
12/04/2023540181952Open ↗
▸BISZONING DIAGRAM1
12/15/2020540181952Open ↗
▸Seals & Professional Certifications16
▸DOB NOWProgress Inspector Seal & Signature12
09/02/2026S00411055-I1Open ↗
09/02/2026S00411055-I1Open ↗
09/02/2026S00411055-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/25/2026S00323677-I1Open ↗
08/13/2026S00323642-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/09/2020540181952Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/09/2020540181952Open ↗
▸Trade Schedules & Equipment7
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)2
01/30/2024540181952Open ↗
10/08/2020540181952Open ↗
▸BISHEATING SYSTEMS1
01/11/2024540181952Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
01/11/2024540181952Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
01/11/2024540181952Open ↗
▸BISDEP STORMWATER SEWER CERTIFICATION (HCP/SCP)1
10/08/2020540181952Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
01/31/2024540181952Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST2
12/15/2020540181952Open ↗
10/08/2020540181952Open ↗
▸BISTenant Protection Plan and Notes1
10/08/2020540181952Open ↗
▸BISSTREET TREES SITE PLAN1
11/22/2023540181952Open ↗
▸BISSTREET TREE SIGNOFF1
11/22/2023540181952Open ↗
▸Energy Compliance9
▸BISELECTRICAL ENERGY CONSUMPTION1
01/11/2024540181952Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
01/11/2024540181952Open ↗
▸BISINTERIOR LIGHTING POWER1
01/11/2024540181952Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
01/11/2024540181952Open ↗
▸BISFENESTRATION AREAS1
01/11/2024540181952Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
12/17/2020540181952Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
01/11/2024540181952Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
01/11/2024540181952Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
01/11/2024540181952Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/13/2024540181952Open ↗
12/17/2020540181952Open ↗
09/09/2020540181952Open ↗
▸BISFRAME (2008)/STRUCTURAL WOOD FRAME (2014) INSPECTION1
01/11/2024540181952Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
01/11/2024540181952Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
01/11/2024540181952Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
01/11/2024540181952Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
03/06/2020520399060Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
01/11/2024540181952Open ↗
▸BISSOIL REPORT1
09/09/2020540181952Open ↗
▸BISSOIL PERC. TEST-PVT ON-SITE STORM WATER DRAINAGE DISPOSAL SYS & DET. FACL.1
01/11/2024540181952Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
09/09/2020540181952Open ↗
▸Approvals, Objections & Sign-offs8
▸BISLETTERS - SUPPORTING DOCUMENTATION3
12/15/2020540181952Open ↗
10/21/2020540181952Open ↗
03/06/2020520399060Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE3
11/14/2024540181952Open ↗
10/25/2024540181952Open ↗
10/14/2020540181952Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
03/06/2020520399060Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/12/2020520399060Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
12/15/2020540181952Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
02/26/2024540181952Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION4
11/25/2024540181952Open ↗
08/14/2024540181952Open ↗
02/06/2024540181952Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
02/12/2020520399060Open ↗
▸Other Documents14
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form2
03/06/2020520399060Open ↗
03/05/2020520399060Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
09/09/2020540181952Open ↗
▸BISLOWEST FLOOR ELEVATION1
01/11/2024540181952Open ↗
▸BISEXTERIOR INSULATION AND FINISH SYSTEMS (EIFS) (2014)1
01/11/2024540181952Open ↗
▸BISMAINTENANCE INFORMATION1
01/11/2024540181952Open ↗
▸BISHVAC & SERVICE WATER PIPING DESIGN AND INSULATION1
01/11/2024540181952Open ↗
▸BISPERMANENT CERTIFICATE1
01/11/2024540181952Open ↗
▸BISFIREPLACES1
01/11/2024540181952Open ↗
▸BISTCO - Supporting Documents1
12/17/2024540181952Open ↗
▸BISBPP: FILING REQUIRED1
09/09/2020540181952Open ↗
▸BISDUCT DESIGN, INSULATION AND LEAKAGE TESTING1
01/11/2024540181952Open ↗
▸BISPLOT DIAGRAM1
09/08/2020540181952Open ↗
▸BISPVT ON-SITE STORM WATER DISPOSAL SYSTEMS & DETENTION FACL., INSTALLATION1
01/30/2024540181952Open ↗