Miscellaneous educational facility
Little Flower Preparatory School
305 REMSEN AVENUE · Name © OpenStreetMap contributors · BIN 3101024
💬 Discuss this project
1970Year Built
1Stories
W9Building Class
R6Zoning
9,800 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Miscellaneous educational facility · Owner of record: 305 Remsen Realty · 10,000 sf lot · 0.98 FAR built · Flood zone X
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Roof2 filings
Floor 12 filings
Cellar2 filings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
180 East 18th St Realty2307/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/09/2023$6.0M—REMSEN ASSOCIATES COMPANY LLC → 305 REMSEN REALTY LLC$612/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Pinner311/17/2025
The Downtown508/14/2025
New York & Company207/09/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Pinner1003/21/2026
New York & Company403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
P.H. WorksPlumbing310/04/2026
Pragmatic DevelopersGeneral Contractor207/08/2026
P H WorksGeneral Contractor104/09/2026
Bruche Mechanical NYFire Protection107/08/2026
Plumbing P & HPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MB Inspections8703208/14/2025
New York Engineers3868208/14/2025
New York Engineering Associates851207/09/2025
Downtown Engineers9711305/19/2025
Building Lifecycle
All (74)Filed (10)Permit Issued (6)Signed Off (4)Violation (4)Inspection (10)Objection (10)Special Inspection (28)
09/22/2026
Signed off — Alteration
INSTALL TWO GAS BOILERS.
B01230125-I1
07/23/2026
Permit expired, never signed off — General Construction
The city's record still shows this permit as issued, with no sign-off on its filing
B01107603-I1-GC
07/13/2026
Permit renewed — Plumbing
Renewed without changes
B01230125-S1-PL
12/26/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/26/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/03/2025
Special inspection requirement — Interior lighting power
Lawrence pinner
12/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Lawrence pinner
12/03/2025
Special inspection requirement — Lighting controls
Lawrence pinner
12/01/2025
Objection resolved — Addressed
11/24/2025
Objection raised — Scope
11/17/2025
Filed — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-P4
11/11/2025
Special inspection requirement — Interior lighting power
Lawrence pinner
11/11/2025
Special inspection requirement — Lighting controls
Lawrence pinner
11/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Lawrence pinner
09/16/2025
FA-05-01: Failed to install fire alarm system conforming with the Fire Department-approved plans meeting all applicable requirements of the New…
FDNY_ORDER violation · closed
09/15/2025
Signed off — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-S5
09/15/2025
Signed off — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-S3
09/10/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/05/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/04/2025
Signed off — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-S4
09/03/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/28/2025
Special inspection requirement — Sprinkler Systems
Raimundo Ramos
08/28/2025
Special inspection requirement — Post-installed Anchors
Raimundo Ramos
08/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Raimundo Ramos
08/26/2025
Filed — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-P3
08/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Lawrence pinner
08/22/2025
Special inspection requirement — Lighting controls
Lawrence pinner
08/22/2025
Special inspection requirement — Interior lighting power
Lawrence pinner
08/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/18/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Raimundo Ramos
08/18/2025
Special inspection requirement — HVAC-R and service water heating equipment
Raimundo Ramos
08/18/2025
Special inspection requirement — Energy Code Compliance Inspections
Raimundo Ramos
08/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Raimundo Ramos
08/18/2025
Special inspection requirement — Post-installed Anchors
Raimundo Ramos
08/18/2025
Special inspection requirement — Maintenance information
Raimundo Ramos
08/18/2025
Special inspection requirement — HVAC-R and service water heating system controls
Raimundo Ramos
08/14/2025
Filed — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-P1
08/14/2025
Filed — Alteration CO
INTERIOR RENOVATION OF FIRST FLOOR AND INSTALLATION OF EXTERIOR RAMP
B01107603-P2
07/31/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/31/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Michael Tobias
07/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Michael Tobias
07/31/2025
Special inspection requirement — Post-installed Anchors
BORIS BALKHIYEV
07/31/2025
Special inspection requirement — Sprinkler Systems
Michael Tobias
07/31/2025
Special inspection requirement — Energy Code Compliance Inspections
Michael Tobias
07/31/2025
Special inspection requirement — HVAC-R and service water heating equipment
Michael Tobias
07/31/2025
Special inspection requirement — Maintenance information
Michael Tobias
07/31/2025
Special inspection requirement — HVAC-R and service water heating system controls
Michael Tobias
07/23/2025
Permit issued — General Construction
B01107603-I1-GC
07/21/2025
Objection resolved — Addressed
07/14/2025
Permit issued — Boiler Equipment
B01230125-I1-BE
07/14/2025
Permit issued — Plumbing
B01230125-S1-PL
07/10/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/09/2025
Filed — Alteration
INSTALL TWO GAS BOILERS.
B01230125-I1
07/09/2025
Filed — Alteration
INSTALL TWO GAS BOILERS.
B01230125-S1
07/09/2025
Objection resolved — Addressed
06/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/11/2025
Permit issued — Mechanical Systems
B01107603-S4-MS
06/05/2025
Permit issued — Plumbing
B01107603-S3-PL
06/05/2025
Permit issued — Sprinklers
B01107603-S5-EW-SP
Latest 60 of 74 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOW—P.H. Works—
DOB NOW—Pragmatic Developers—
DOB NOW—P.H. Works—
DOB NOW—P.H. Works—
DOB NOW—Pragmatic Developers—
DOB NOW—Plumbing P & H—
DOB NOW—Bruche Mechanical NY—
BIS—Alaska Cooling—
BIS—Norhtstar Construction Man—
Nothing on file for this building.
Nothing on file for this building.
▾Documents — 73 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/21/2026B01107603-P4Request the plans ↗
08/21/2026B01107603-P3Request the plans ↗
08/21/2026B01107603-P2Request the plans ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications37
▸DOB NOWProgress Inspector Seal & Signature18
09/23/2026B01230125-I1Open ↗
09/22/2026B01107603-S3Open ↗
09/22/2026B01107603-S3Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature10
08/21/2026B01107603-I1Open ↗
08/21/2026B01107603-P4Open ↗
08/21/2026B01107603-P3Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
10/05/2026B01107603-S5Open ↗
09/30/2026B01107603-P1Open ↗
09/30/2026B01107603-P1Open ↗
Showing 3 of 9 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/13/2026B01107603-P4Open ↗
08/13/2026B01107603-I1Open ↗
08/13/2026B01107603-P3Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/21/2026B01107603-P4Open ↗
08/21/2026B01107603-P3Open ↗
08/21/2026B01107603-P2Open ↗
Showing 3 of 10 on file for this type
▸Approvals, Objections & Sign-offs10
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter10
08/13/2026B01107603-S5Open ↗
08/13/2026B01107603-I1Open ↗
08/13/2026B01107603-P2Open ↗
Showing 3 of 10 on file for this type
▸Other Documents3
▸DOB NOWProperty Ownership Certification3
08/21/2026B01107603-P4Open ↗
08/21/2026B01107603-P3Open ↗
08/21/2026B01107603-I1Open ↗