← Back
Elevator apt, fireproof without stores
Jackson (NYCHA)
3050 PARK AVENUE · BIN 2091223
💬 Discuss this project
1960Year Built
16Stories
D3Building Class
R8Zoning
748,000 sfGross Floor Area
868Units
LL97 Covered14 Open Violations 9 unresolved · 5 paperwork only ▸FISP: SAFE
Elevator apt, fireproof without stores · Owner of record: NYC HOUSING AUTHORITY · 343,403 sf lot · 2.18 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalCivilGeneralOther
Roof23p · 4 filings · 20 docs
Bulkhead6p · 1 filing · 17 docs
Cellar16p · 2 filings · 20 docs
1 job · most recent 04/30/2024
Storm
FiledStatusContractorScope
04/30/2024Signed-offMPC PLUMBING & HEATING INStorm
11 jobs · most recent 08/12/2026
General Wiring
FiledStatusContractorScope
08/12/2026CompleteARCADIA ELECT'L CO. INC.General Wiring
06/06/2025CompleteTRI-STATE ELECL & MECHL IGeneral Wiring
03/10/2025CompleteJEMCO ELECT. CONTRS INCGeneral Wiring
04/05/2024CompleteAMIN ELECTRICAL CORP—
08/30/2023CompleteLIT MODE ELECL CONTG INC—
01/24/2023Permit IssuedHYLAN DATACOM & ELECL LLC—
07/05/2022CompleteARCADIA ELECT'L CO. INC.—
03/02/2022CompleteEIA ELECTRIC, INC1 meters
05/05/2020Permit IssuedALL-STAR ELEC'L SERVICES—
05/14/2018CompleteLINTECH ELECTRIC, INC.—
05/14/2018CompleteLINTECH ELECTRIC, INC.—
2 jobs · most recent 04/30/2024
Steel Concrete Masonry
FiledStatusContractorScope
04/30/2024Signed-offMPC PLUMBING & HEATING INSteel, Concrete, Masonry
11/04/2022——1 scope_items
1 job · most recent 04/30/2024
Earthwork Tenant Protection Plan 72 Hour
FiledStatusContractorScope
04/30/2024Signed-offMPC PLUMBING & HEATING INEarthwork, Tenant Protection Plan 72 Hour
Building Lifecycle
All (182)Filed (33)Permit Issued (35)Signed Off (14)Facade (FISP) (23)Violation (30)Inspection (12)Objection (5)Special Inspection (30)
08/05/2026
Signed off — Alteration
X00656577-I1
07/29/2026
Permit issued — Construction Fence
X00656577-I1-FN
05/12/2026
Signed off — Alteration
plumbing connections for new geothermal hvac system. Jackson building 3
X00733796-I1
05/05/2026
Signed off — Alteration
Installation of equipment concrete pads. Jackson building 3
X00734700-I1
04/28/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
03/16/2026
Filed — Alteration
plumbing connections for new geothermal hvac system. Jackson building 3
X00733796-P3
03/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
01/28/2026
Special inspection requirement — Air barrier - visual inspection
01/28/2026
Special inspection requirement — Insulation placement and R values
01/28/2026
Special inspection requirement — Fenestration areas
01/28/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
01/28/2026
Special inspection requirement — Fenestration air leakage
12/10/2025
Permit issued — Construction Fence
X00656577-I1-FN
12/10/2025
Permit issued — Structural
X00734700-I1-ST
09/05/2025
Signed off — Alteration
NYCHA_BLDG#3_Roof replacement and roof bulkhead repair.
X00548322-I1
09/02/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/02/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/25/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/25/2025
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
04/22/2025
Signed off — Alteration
NYCHA Jackson Bldg 03, Exterior Faade repairs per the plans, including: Removal / Replacement /Repairs to masonry, concrete slab, shelf angle, slate sills, windows, and joint sealants. Pinning of existing brickwork with adhesive anchors. Expansion Joints.
X00989356-I1
04/22/2025
Permit issued — Plumbing
X00733796-I1-PL
04/16/2025
Special inspection requirement — Energy Code Compliance Inspections
CHRISTOPHER BEHLE
04/16/2025
Special inspection requirement — Post-installed Anchors
CHRISTOPHER BEHLE
04/16/2025
Special inspection requirement — Preliminary
CHRISTOPHER BEHLE
04/16/2025
Special inspection requirement — Insulation placement and R values
CHRISTOPHER BEHLE
04/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHRISTOPHER BEHLE
04/16/2025
Special inspection requirement — Fire-Resistance Rated Construction
CHRISTOPHER BEHLE
04/10/2025
Filed — Alteration
NYCHA_BLDG#3_Roof replacement and roof bulkhead repair.
X00548322-P3
04/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
CHRISTOPHER BEHLE
04/09/2025
Special inspection requirement — Post-installed Anchors
CHRISTOPHER BEHLE
04/09/2025
Special inspection requirement — Preliminary
CHRISTOPHER BEHLE
04/09/2025
Special inspection requirement — Insulation placement and R values
CHRISTOPHER BEHLE
04/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
CHRISTOPHER BEHLE
04/09/2025
Special inspection requirement — Energy Code Compliance Inspections
CHRISTOPHER BEHLE
03/26/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
03/20/2025
Signed off — Alteration
INSTALLATION OF MATERIAL HOIST SYSTEM FOR NYCHA BUILDING # 3 AT 785 COURTLANDT AVENUE, BRONX, NY 10451.
X00996560-I1
03/12/2025
Permit issued — Suspended Scaffold
X00996560-I1-SC
02/21/2025
Permit issued — General Construction
X00753964-I1-GC
12/04/2024
Signed off — Alteration
INSTALLATION OF SUSPENDED SCAFFOLD AND MATERIAL HOIST FOR EXTERIOR FACADE REPAIRS. SUSPENDED SCAFFOLD AND MATERIAL HOIST SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00985648-I1
11/26/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 785 COURTLANDT AVENUE, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
X08032932-I1
11/26/2024
Signed off — Alteration
INSTALLATION OF NEW SIDEWALK SHED AT 785 COURTLANDT AVENUE, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
X08032902-I1
11/25/2024
Violation issued (ECB, closed)
Construction
10/31/2024
Cycle 9 facade report submitted
10/29/2024
Cycle 9 facade inspection completed
10/29/2024
Cycle 9 facade report signed — SAFE
10/17/2024
Special inspection requirement — Final
IBRAHIM MOURAD
10/17/2024
Special inspection requirement — Concrete - Cast-In-Place
IBRAHIM MOURAD
10/17/2024
Special inspection requirement — Post-installed Anchors
IBRAHIM MOURAD
10/16/2024
Filed — Alteration
Installation of equipment concrete pads. Jackson building 3
X00734700-P1
10/03/2024
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLD AT 785 COURTLANDT AVENUE, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
X00807771-I1
09/03/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — Heating Systems
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — Mechanical Systems
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — HVAC-R and service water heating system controls
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — HVAC-R and service water heating equipment
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — Final
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
IBRAHIM MOURAD
09/03/2024
Special inspection requirement — Maintenance information
IBRAHIM MOURAD
Latest 60 of 182 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYCHA7907/30/2026
P K CONTRACTING203/22/2026
NYC NYCHA103/22/2026
NEW YORK CITY HOUSING AUTHORITY1003/22/2026
SKYWORX CONTRACTING303/22/2026
METROPOLITAN ENTERPRISES203/22/2026
NYCHA 99503/22/2026
NYCHA 996103/22/2026
NYC HOUSING AUTHORITY503/22/2026
NYCHA OFFICE OF DESIGN 12103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STV603/21/2026
GREEN LIGHT EXPEDITING LLC803/21/2026
JOEL PHAGOO P.E. PLLC403/21/2026
JAM CONSULTANTS, INC.703/21/2026
AK CONSULTING SERVICES1203/21/2026
GAMILL ENGINEERING, PC203/21/2026
DSENY ENGINEERING SERVICES203/21/2026
SUPERSTRUCTURES ENG + ARCH103/21/2026
JMV CONSULTING ENGINEERING, P.C103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RAVEN CONSTRUCTION SERVICGeneral Contractor1607/30/2026
ROMA SCAFFOLDING INCGeneral Contractor1607/08/2026
SKYWORX CONTRACTING INCGeneral Contractor607/08/2026
JRCRUZ CORPGeneral Contractor603/21/2026
SKYLINE P & H INCPlumbing203/22/2026
FRANK, SEYMOURElectrical203/21/2026
KORDUN CONSTRUCTION CORPPlumbing207/08/2026
NEELAM CONSTRUCTION CORPGeneral Contractor207/08/2026
P & K CONTRACTING INCGeneral Contractor107/08/2026
JCC CONSTRUCTION CORPPlumbing107/08/2026
MPC PLUMBING & HEATING INCPlumbing107/08/2026
KORDUN CONSTRUCTION CORPGeneral Contractor107/08/2026
EIA ELECTRIC, INCElectrical103/22/2026
FORD, GUYElectrical103/21/2026
GUY FORDElectrical103/21/2026
JAMES MAGRIPLESElectrical103/21/2026
JOSEPH MENDEZElectrical103/21/2026
LIOTINE, VITOElectrical103/21/2026
BUNAY, CLEVERElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUREAU VERITAS NA6902703/16/2026
MT GROUP798304/10/2025
AK CONSULTING SERVICES, I6198101/26/2024
DISTINCT ENGINEERING SOLU2641101/22/2024
JOEL PHAGOO ,PE, PLLC2416101/08/2024
BIG APPLE GROUP NY A RMA9168409/01/2023
BITOPI CONSULTANTS LLC7036101/05/2023
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC07/29/2026
DOB NOWConstruction FencePermit IssuedRAVEN CONSTRUCTION SERVIC12/10/2025
DOB NOWStructuralSigned-offRAVEN CONSTRUCTION SERVIC12/10/2025
DOB NOWPlumbingSigned-offKORDUN CONSTRUCTION CORP04/22/2025
DOB NOWSuspended ScaffoldSigned-offD&N CONST & CONSULTNG INC03/12/2025
DOB NOWGeneral ConstructionSigned-offRAVEN CONSTRUCTION SERVIC02/21/2025
DOB NOWGeneral ConstructionSigned-offP & K CONTRACTING INC05/08/2024
DOB NOWGeneral ConstructionSigned-offROMA SCAFFOLDING INC01/31/2024
DOB NOWSuspended ScaffoldSigned-offD&N CONST & CONSULTNG INC01/30/2024
DOB NOWSuspended ScaffoldSigned-offD&N CONST & CONSULTNG INC01/30/2024
DOB NOWSuspended ScaffoldSigned-offZORIA HOUSING LLC01/19/2024
DOB NOWSupported ScaffoldSigned-offROMA SCAFFOLDING INC01/03/2024
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC01/02/2024
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC01/02/2024
DOB NOWPlumbingSigned-offMPC PLUMBING & HEATING IN11/08/2023
DOB NOWEarth WorkPermit IssuedJRCRUZ CORP11/06/2023
DOB NOWGeneral ConstructionPermit IssuedJRCRUZ CORP11/06/2023
DOB NOWGeneral ConstructionSigned-offJRCRUZ CORP11/03/2023
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC08/09/2023
DOB NOWMechanical SystemsSigned-offKORDUN CONSTRUCTION CORP02/22/2023
DOB NOWPlumbingSigned-offKORDUN CONSTRUCTION CORP02/22/2023
DOB NOWGeneral ConstructionSigned-offRAVEN CONSTRUCTION SERVIC02/16/2023
DOB NOWStructuralSigned-offRAVEN CONSTRUCTION SERVIC02/16/2023
DOB NOWGeneral ConstructionSigned-offROMA SCAFFOLDING INC01/30/2023
DOB NOWSupported ScaffoldSigned-offROMA SCAFFOLDING INC01/06/2023
DOB NOWConstruction FenceSigned-offROMA SCAFFOLDING INC12/30/2022
DOB NOWSidewalk ShedSigned-offROMA SCAFFOLDING INC12/30/2022
DOB NOWConstruction FenceSigned-offRAVEN CONSTRUCTION SERVIC08/05/2022
DOB NOWPlumbingSigned-offJCC CONSTRUCTION CORP05/12/2022
DOB NOWSidewalk ShedSigned-offSKYWORX CONTRACTING INC08/02/2018
DOB NOWSupported ScaffoldSigned-offSKYWORX CONTRACTING INC08/02/2018
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP07/31/2018
DOB NOWSupported ScaffoldSigned-offSKYWORX CONTRACTING INC06/22/2018
DOB NOWSidewalk ShedSigned-offSKYWORX CONTRACTING INC06/09/2018
DOB NOWConstruction FenceSigned-offNEELAM CONSTRUCTION CORP06/09/2018
BISPLISSUEDRICHARDS P AND H CO, INC03/11/2022
BISOTISSUEDRICHARDS PLUM & HTG CO,IN07/02/2021
BISPLISSUEDRICHARDS P AND H CO, INC03/12/2021
BISOTISSUEDRICHARDS PLUM & HTG CO,IN07/01/2020
BISOTISSUEDRICHARDS PLUM & HTG CO,IN04/01/2020
+ 23 more permits on file
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/28/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/02/2025Pass-Final General Construction Non-Directive 14PassView ↗
06/02/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/25/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/25/2025Certified Sprinkler - SP - RoughingCertifiedView ↗
03/26/2025Fail-Final General Construction Non-Directive 14FailView ↗
07/17/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
07/16/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/28/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/21/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/15/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 77
DateRequirementInspectorRole
03/17/2026Fire-Resistant Penetrations and JointsIBRAHIM MOURADspecial
03/13/2026Fire-Resistant Penetrations and JointsIBRAHIM MOURADspecial
01/28/2026Air barrier - visual inspection—energy_progress
01/28/2026Insulation placement and R values—energy_progress
01/28/2026Fenestration air leakage—energy_progress
01/28/2026Fenestration areas—energy_progress
01/28/2026Fenestration and door U-factor and product ratings—energy_progress
04/16/2025Post-installed AnchorsCHRISTOPHER BEHLEspecial
04/16/2025Fire-Resistant Penetrations and JointsCHRISTOPHER BEHLEspecial
04/16/2025Fire-Resistance Rated ConstructionCHRISTOPHER BEHLEprogress
04/16/2025PreliminaryCHRISTOPHER BEHLEprogress
04/16/2025Energy Code Compliance InspectionsCHRISTOPHER BEHLEprogress
04/16/2025Insulation placement and R valuesCHRISTOPHER BEHLEenergy_progress
04/09/2025Fire-Resistant Penetrations and JointsCHRISTOPHER BEHLEspecial
04/09/2025Insulation placement and R valuesCHRISTOPHER BEHLEenergy_progress
04/09/2025PreliminaryCHRISTOPHER BEHLEprogress
04/09/2025Fire-Resistance Rated ConstructionCHRISTOPHER BEHLEprogress
04/09/2025Energy Code Compliance InspectionsCHRISTOPHER BEHLEprogress
04/09/2025Post-installed AnchorsCHRISTOPHER BEHLEspecial
10/17/2024FinalIBRAHIM MOURADprogress
10/17/2024Concrete - Cast-In-PlaceIBRAHIM MOURADspecial
10/17/2024Post-installed AnchorsIBRAHIM MOURADspecial
09/03/2024HVAC-R and service water heating system controlsIBRAHIM MOURADenergy_progress
09/03/2024Mechanical SystemsIBRAHIM MOURADspecial
09/03/2024Heating SystemsIBRAHIM MOURADspecial
Latest 25 of 77.
▾Documents — 276 on file (BIS + DOB NOW)
▸Plans & Drawings30
▸DOB NOWPlans/Sketch30
08/26/2026X00051109-I1Request digital key ↗
08/26/2026X00051122-I1Request digital key ↗
08/26/2026X00054967-I1Request digital key ↗
Showing 3 of 30 on file for this type
▸Applications & Permits29
▸BISPLAN / WORK APPROVAL APPLICATION17
01/04/2019240242466Open ↗
11/13/2018240242466Open ↗
10/15/2018240230727Open ↗
Showing 3 of 17 on file for this type
▸BISWORK PERMIT APPLICATION12
03/11/2020240242466Open ↗
03/11/2020240242466Open ↗
07/10/2018240225788Open ↗
Showing 3 of 12 on file for this type
▸Seals & Professional Certifications95
▸DOB NOWDPL-1: Design Professional Seal & Signature28
08/26/2026X00051122-I1Open ↗
08/25/2026X00548322-P3Open ↗
08/25/2026X00548322-I1Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/01/2026X00054967-I1Open ↗
09/01/2026X00753964-P1Open ↗
09/01/2026X00753964-P1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/29/2026X00985648-I1Open ↗
09/23/2026X00733796-I1Open ↗
08/27/2026X00548322-P3Open ↗
Showing 3 of 15 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION11
03/12/2020240242466Open ↗
05/15/2019240225788Open ↗
03/15/2017240124897Open ↗
Showing 3 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT7
06/28/2018240227296Open ↗
06/14/2018240225788Open ↗
03/15/2017240124897Open ↗
Showing 3 of 7 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION6
06/28/2018240227296Open ↗
06/14/2018240225788Open ↗
12/03/2015240124897Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY6
06/28/2018240227296Open ↗
06/14/2018240225788Open ↗
12/03/2015240124897Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
03/15/2017240124897Open ↗
12/20/2013220035496Open ↗
11/06/2009220035496Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
11/13/2018240242466Open ↗
10/01/2018240230727Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
11/06/2009220035496Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING2
11/13/2018240242466Open ↗
10/01/2018240230727Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION2
11/13/2018240242466Open ↗
11/13/2018240242466Open ↗
▸Safety & Tenant Protection4
▸BISTENANT PROTECTION PLAN AND NOTES4
06/28/2018240227296Open ↗
06/14/2018240225788Open ↗
11/13/2018240242466Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form6
08/25/2026X00548322-I1Open ↗
08/21/2026X00989356-I1Open ↗
08/21/2026X00753964-I1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
04/11/2019240242466Open ↗
01/21/2013240016317Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)2
05/15/2019240225788Open ↗
06/14/2018240225788Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026X00733285-I1Open ↗
08/13/2026X00054967-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
11/06/2009220035496Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
03/11/2020240242466Open ↗
01/08/2019240242466Open ↗
06/14/2018240225788Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026X00733212-I1Open ↗
08/13/2026X00548322-I1Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/15/2019240225788Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
05/15/2019240225788Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/14/2018240225788Open ↗
▸BISNYCECC ANALYSIS1
06/14/2018240225788Open ↗
▸Inspections & Test Reports9
▸BISTECHNICAL REPORT: RESPONSIBILITY8
03/11/2020240242466Open ↗
11/13/2018240242466Open ↗
10/01/2018240230727Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSOIL REPORT1
08/13/2026X00919018-S4Open ↗
▸Approvals, Objections & Sign-offs55
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter30
08/25/2026X00548322-P3Open ↗
08/25/2026X00548322-I1Open ↗
08/25/2026X00548322-P2Open ↗
Showing 3 of 30 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION10
11/13/2018240242466Open ↗
07/10/2018240225788Open ↗
01/08/2014220035496Open ↗
Showing 3 of 10 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
05/15/2019240225788Open ↗
03/15/2017240124897Open ↗
01/08/2014220035496Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDEP Variance (V5) letter5
08/17/2026X00733796-I1Open ↗
08/13/2026X00753964-I1Open ↗
08/13/2026X00734700-I1Open ↗
Showing 3 of 5 on file for this type
▸BISSHED LETTER3
12/23/2016240124897Open ↗
05/14/2013220035496Open ↗
06/14/2010220035496Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
11/06/2009220035496Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
05/15/2019240225788Open ↗
01/08/2019240242466Open ↗
10/01/2018240230727Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms16
▸BISEFILING JOB APPLICATION COVER SHEET8
11/13/2018240242466Open ↗
10/01/2018240230727Open ↗
06/28/2018240227296Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION6
01/08/2019240242466Open ↗
11/13/2018240242466Open ↗
03/15/2017240124897Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET1
11/06/2009220035496Open ↗
▸BISBOROUGH INTAKE FORM1
05/15/2019240225788Open ↗
▸Other Documents5
▸DOB NOWCalculations2
08/13/2026X00996560-I1Open ↗
08/13/2026X00985648-I1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026X00985648-I1Open ↗
08/13/2026X00996560-I1Open ↗
▸BISFEE EXEMPTION DOCUMENTATION1
06/14/2018240225788Open ↗