← Back
BuildNYC
Miscellaneous educational facility
P.S. 168
3050 WEBSTER AVENUE · BIN 2086851
💬 Discuss this project
1991Year Built
4Stories
W9Building Class
R7DZoning
119,945 sfGross Floor Area
1Units
LL97 Covered28 Active Violations 0 unresolved · 28 paperwork only 2 likely answered ▸
Miscellaneous educational facility · Owner of record: NYC Department of Education · 110,900 sf lot · 1.08 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofP.S. 20 Port Richmond, Public School20 +18p · 3 filings · 18 docs
Floor 5P.S. 1681 filing · 20 docs
Floor 4Public School20, P.S. 1682 filings · 18 docs
Floor 3P.S. 20 Port Richmond, Public School20 +17p · 3 filings · 18 docs
Floor 2P.S. 20 (X168), P.S. 20 Port Richmond +2Under Construction23p · 4 filings · 18 docs
Floor 1P.S. 20 Port Richmond, P.S. 1687p · 2 filings · 20 docs
MezzanineP.S. 1681 filing · 20 docs
CellarP.S. 20 Port Richmond, Public School20 +17p · 4 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority6207/08/2026
Nycsha603/21/2026
NYC Department of Education203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYC School Construction Authority401/23/2026
Salam & Giacalone Architects112/29/2025
HRM Engineering Services112/29/2025
Bladykas Engineering511/15/2024
DI Domenico + Partners103/31/2023
AKRF203/28/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC School Construction Authority603/21/2026
Bladykas Engineering1203/21/2026
Precision 3Sixty NYC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Prince ElectricElectrical203/21/2026
Selectric Electrical Cont Co IElectrical203/21/2026
DVM Electrical ServicesElectrical103/22/2026
Slope ElectricElectrical103/21/2026
Forsythe Plumbing & HeatingPlumbing106/27/2026
ABC Construction ContGeneral Contractor107/08/2026
Smart Heating & Coolingspecialty_contractor107/08/2026
Charan Electrical Enterp'sElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Tectonic Engineering Cons106312/29/2025
Twin Peaks317101/31/2023
Building Lifecycle
All (126)Filed (14)Permit Issued (3)Violation (60)Inspection (1)Objection (18)Special Inspection (30)
09/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/26/2026
Violation issued (ECB, open)
Construction
06/25/2026
Permit issued — Plumbing
X01327856-S2-PL
05/18/2026
Permit issued — General Construction
X01327856-I1-GC
03/27/2026
Objection resolved — Addressed
03/27/2026
Objection resolved — Addressed
03/17/2026
Special inspection requirement — Post-installed Anchors
GEORGE GHEBRYAL
03/17/2026
Special inspection requirement — Maintenance information
JAMES WILSON
03/06/2026
Objection resolved — Addressed
03/04/2026
Objection resolved — Addressed
03/04/2026
Special inspection requirement — Interior lighting power
JAMES WILSON
03/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/04/2026
Special inspection requirement — Lighting controls
JAMES WILSON
03/03/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
JAMES WILSON
03/03/2026
Special inspection requirement — Energy Code Compliance Inspections
JAMES WILSON
02/05/2026
Objection raised — Other
02/05/2026
Objection raised — Other
01/27/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
01/23/2026
Filed — Alteration
X020 : Remove, Replace, relocate 52 Roof Drains; Reflash, relocate 1 Vent Stacks, reflashing of 17 Vent Stacks and Power Wash 28 Roof Leaders. No Change in Use, Egress or Occupancy.
X01285939-I1
01/23/2026
Filed — Alteration
X020 : Remove, Replace, relocate 52 Roof Drains; Reflash, relocate 1 Vent Stacks, reflashing of 17 Vent Stacks and Power Wash 28 Roof Leaders. No Change in Use, Egress or Occupancy.
X01285939-S1
01/23/2026
Special inspection requirement — Post-installed Anchors
01/23/2026
Special inspection requirement — Energy Code Compliance Inspections
01/23/2026
Special inspection requirement — Masonry
01/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
01/23/2026
Special inspection requirement — Post-installed Anchors
01/23/2026
Special inspection requirement — Insulation placement and R values
01/23/2026
Special inspection requirement — Fire-Resistance Rated Construction
01/12/2026
Objection raised — Other
01/12/2026
Objection raised — Other
12/29/2025
Filed — Alteration
REMOVE AND REPLACE PARTITIONS, CASEWORK, CABINETS, WINDOW SHADES, FURNITURE AND EQUIPMENT, FLOORING, AND FINISHES. PLASTER PATCH AND PAINT WALLS AND CEILINGS, INTERIOR LIGHTING.
X01327856-I1
12/29/2025
Filed — Alteration
REMOVE AND REPLACE PARTITIONS, CASEWORK, CABINETS, WINDOW SHADES, FURNITURE AND EQUIPMENT, FLOORING, AND FINISHES. PLASTER PATCH AND PAINT WALLS AND CEILINGS, INTERIOR LIGHTING.
X01327856-S2
12/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
GEORGE GHEBRYAL
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
07/28/2025
Violation issued (ECB, open)
Construction
07/28/2025
Violation issued (ECB, closed)
Construction
11/26/2024
Special inspection requirement — Shutoff dampers
11/26/2024
Special inspection requirement — Energy Code Compliance Inspections
11/26/2024
Special inspection requirement — Final
11/26/2024
Special inspection requirement — Post-installed Anchors
11/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/26/2024
Special inspection requirement — Duct leakage testing, insulation and design
11/26/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
11/26/2024
Special inspection requirement — HVAC-R and service water heating system controls
11/26/2024
Special inspection requirement — Mechanical Systems
11/26/2024
Special inspection requirement — Maintenance information
11/26/2024
Special inspection requirement — Electrical motors and elevators
11/26/2024
Special inspection requirement — HVAC-R and service water heating equipment
11/15/2024
Filed — Alteration
PS 20X - REPLACE EXISTING SPLIT UNITS WITH NEW SPLIT HEAT PUMP CHILLERs AND AIR HANDLING UNITS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00850692-S6
Latest 60 of 126 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedForsythe Plumbing & Heating06/25/2026
DOB NOWGeneral ConstructionPermit IssuedABC Construction Cont05/18/2026
DOB NOWMechanical SystemsPermit IssuedSmart Heating & Cooling02/10/2023
BISPLISSUEDWill-Do Plumbing02/09/2021
BISPLISSUEDWill-Do Plumbing10/22/2019
BISPLISSUEDWill-Do Plumbing07/17/2018
BISPLISSUEDVarsity Plumbing and Heating03/08/2016
BISOTISSUED2 Saab Construction01/07/2016
BISOTISSUED2 Saab Construction11/04/2015
BISEQISSUEDAdvanced Construction Equipment03/19/2015
BISOTISSUED2 Saab Construction03/17/2015
BISPLISSUEDVarsity Plumbing and Heating03/17/2015
BISEQISSUED2 Saab Construction03/06/2015
BISEQISSUEDAdvanced Construction Equipment03/06/2015
BISEQISSUEDKoko Contracting12/22/2011
BISPLISSUEDEagle 1 Mechanical06/29/2011
BISMHISSUEDACS System Associates06/29/2011
BISOTISSUEDKoko Contracting06/29/2011
BISEQISSUEDKoko Contracting06/21/2011
BISEQISSUEDKoko Contracting06/10/2011
BISOTISSUEDPMY Construction10/22/2010
BISPLISSUEDAbsolute Mechanical Co03/09/2010
BISPLISSUEDAbsolute Mechanical Co01/14/2009
BISOTISSUEDPMY Construction01/14/2009
BISPLISSUEDGino's Plumbing and Heating08/06/2002
BIS—ISSUEDD&L Associates05/22/2001
BISPLISSUEDFranco Belli Plumbing & Heating & Son02/15/2001
BISOTISSUEDNY School Construction Authority02/01/2000
BISFBISSUEDTemperature Systems08/31/1999
BISOTISSUEDNab Construction02/08/1999
BIS—ISSUEDNab Construction05/28/1998
BISPLISSUEDFranco Belli Plumbing and05/28/1998
BISEQISSUEDNab Construction05/19/1998
BIS—ISSUEDMorrison-Knudsen Company01/16/1998
BIS—ISSUEDMorrison-Knudsen Company01/22/1997
BISEQISSUEDMorrison-Knudsen Company01/04/1996
BISSDISSUEDM & J Plumbing & Mechanical Co12/12/1995
BISFPRE-ISSUEDM & J Plumbing and Mechanical Co05/10/1995
BISPLISSUEDM & J Plumbing Mechanical Co01/09/1995
BIS—ISSUEDMorrison-Knudsen Company01/06/1995
+ 13 more permits on file
2 projects · most recent 11/15/2024
Heating and Air Conditioning Systems Ventilation Systems Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
11/15/2024——Heating and Air Conditioning Systems, Ventilation Systems—
01/31/2023Permit IssuedSmart Heating & CoolingAir Conditioning Systems
3 projects · most recent 01/23/2026
Storm Water/Sanitary
FiledStatusContractorScope
01/23/2026——Storm
12/29/2025Permit IssuedForsythe Plumbing & HeatingWater/Sanitary
11/15/2024——Storm, Water/Sanitary
8 projects · most recent 05/20/2026
General Wiring Lighting
FiledStatusContractorScope
05/20/2026Permit IssuedJames F. Volpe ElectricalGeneral Wiring
07/09/2024CompleteDVM Electrical ServicesLighting
03/12/2023CompleteEverest Electric—
12/02/2022CompleteSlope ElectricGeneral Wiring
09/07/2022CompleteCharan Electrical Enterp's—
04/15/2019CompleteCharan Electrical Enterp's—
11/21/2018CompleteCharan Electrical Enterp's—
01/05/2018CompleteCharan Electrical Enterp's—
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
09/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 55
DateRequirementInspectorRole
03/17/2026Post-installed AnchorsGEORGE GHEBRYALspecial
03/17/2026Maintenance informationJAMES WILSONenergy_progress
03/04/2026Interior lighting powerJAMES WILSONenergy_progress
03/04/2026Structural Stability – Alterations of existing buildings—special
03/04/2026Lighting controlsJAMES WILSONenergy_progress
03/03/2026HVAC-R and service water piping design and insulationJAMES WILSONenergy_progress
03/03/2026Energy Code Compliance InspectionsJAMES WILSONprogress
01/27/2026Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
01/23/2026Post-installed Anchors—special
01/23/2026Energy Code Compliance Inspections—progress
01/23/2026Masonry—special
01/23/2026Fire-Resistant Penetrations and Joints—special
01/23/2026Post-installed Anchors—special
01/23/2026Insulation placement and R values—energy_progress
01/23/2026Fire-Resistance Rated Construction—progress
12/03/2025Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
11/26/2024Shutoff dampers—energy_progress
11/26/2024Energy Code Compliance Inspections—progress
11/26/2024Final—progress
11/26/2024Post-installed Anchors—special
11/26/2024Fire-Resistant Penetrations and Joints—special
11/26/2024Duct leakage testing, insulation and design—energy_progress
11/26/2024HVAC-R and service water piping design and insulation—energy_progress
11/26/2024HVAC-R and service water heating system controls—energy_progress
11/26/2024Mechanical Systems—special
Latest 25 of 55.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Public School20EducationCellar, Floors 2–4, Roof
Project X01285939 Alteration · Approved · 01/23/2026
P.S. 20 (X168)EducationFloor 2
Project X01327856 Alteration · Permit Entire · 12/29/2025
P.S. 168EducationCellar, Floors 1–5, Mezzanine, Roof
Project X00850692 Alteration · Approved · 03/31/2023
Project X00693608 Alteration · Approved · 03/15/2022
P.S. 20 Port RichmondEducationCellar, Floors 1–3, Roof
Project X00662503 Alteration · Permit Entire · 01/21/2022
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 95 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/24/2026X00662503-P1Request digital key ↗
08/24/2026X00693608-S1Request digital key ↗
08/23/2026X00850692-P1Request digital key ↗
Showing 3 of 16 on file for this type
▸Seals & Professional Certifications26
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/24/2026X00662503-P1Open ↗
08/24/2026X00662503-I1Open ↗
08/24/2026X00693608-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/12/2026X01327856-S2Open ↗
09/12/2026X01327856-S2Open ↗
08/29/2026X00662503-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/12/2026X01327856-S2Open ↗
08/29/2026X00662503-I1Open ↗
08/29/2026X00662503-I1Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs34
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter16
08/24/2026X00693608-S1Open ↗
08/15/2026X01327856-S2Open ↗
08/15/2026X01327856-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)16
08/14/2026X00693608-I1Open ↗
08/13/2026X00850692-S5Open ↗
08/13/2026X00850692-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/13/2026X01285939-I1Open ↗
08/13/2026X01285939-S1Open ↗
▸Other Documents19
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal17
08/15/2026X01327856-I1Open ↗
08/14/2026X00693608-I1Open ↗
08/13/2026X00850692-S2Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProof of Historic Building2
08/13/2026X00662503-I1Open ↗
08/13/2026X00662503-P1Open ↗