| Owner | Filings | Most Recent |
|---|---|---|
| 307 5th Avenue | 49 | 03/22/2026 |
| 307 Fifth Ave Realty | 2 | 03/21/2026 |
| Shulsky Properties | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Joel Phagoo P.E | 1 | 05/22/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Skyline Access | 1 | 03/21/2026 |
| A1 Expediting Service | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Crew Contracting of NJ | Scaffold | 3 | 07/08/2026 |
| Green Power Electric | Electrical | 1 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | Skyline Restoration | 01/22/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Crew Contracting of NJ | 02/08/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Crew Contracting of NJ | 01/11/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Crew Contracting of NJ | 05/23/2018 |
| BIS | OT | ISSUED | DPC New York | 07/13/2018 |
| BIS | OT | ISSUED | DPC New York | 06/14/2018 |
| BIS | FP | ISSUED | Master Fire Systems | 07/10/2017 |
| BIS | — | ISSUED | CDS Design and Consulting | 06/30/2017 |
| BIS | PL | ISSUED | Power Plumbing & Heating | 05/17/2017 |
| BIS | — | ISSUED | CDS Design and Consulting | 05/08/2017 |
| BIS | EQ | ISSUED | CDS Design and Consulting | 05/08/2017 |
| BIS | OT | ISSUED | Skyland Development | 03/16/2016 |
| BIS | — | ISSUED | Skyland Development | 04/24/2015 |
| BIS | — | ISSUED | Unitech Design | 04/16/2015 |
| BIS | FP | ISSUED | William Hird & Co | 04/08/2015 |
| BIS | — | ISSUED | Unitech Design | 03/20/2015 |
| BIS | OT | ISSUED | Skyland Development | 03/12/2015 |
| BIS | MH | ISSUED | Skyland Development | 02/17/2015 |
| BIS | PL | ISSUED | Plumbing & Heating Doctor | 01/22/2015 |
| BIS | SP | ISSUED | Plumbing & Heating Doctor | 01/22/2015 |
| BIS | MH | ISSUED | Skyland Development | 01/15/2015 |
| BIS | OT | ISSUED | Skyland Development | 01/15/2015 |
| BIS | FS | ISSUED | C C Controlled Combustion | 08/04/2014 |
| BIS | EQ | ISSUED | ZDG | 12/20/2012 |
| BIS | OT | ISSUED | ZDG | 12/20/2012 |
| BIS | EQ | ISSUED | Universal Builders Supply | 09/19/2012 |
| BIS | MH | ISSUED | Right Temp Mechanical | 07/16/2012 |
| BIS | EQ | ISSUED | Fine Finishes Construction | 06/22/2012 |
| BIS | OT | ISSUED | Fine Finishes Construction | 06/22/2012 |
| BIS | EQ | ISSUED | Universal Builders Supply | 05/08/2012 |
| BIS | MH | ISSUED | Right Temp Mechanical | 06/02/2011 |
| BIS | OT | ISSUED | Fine Finishes Construction | 05/20/2011 |
| BIS | OT | ISSUED | Cisco General Construction | 04/04/2011 |
| BIS | EQ | ISSUED | S Singh Construction Co | 03/21/2011 |
| BIS | OT | ISSUED | Navillus Tile | 01/28/2009 |
| BIS | — | ISSUED | New York Sign Contractor Incc | 09/29/2008 |
| BIS | FP | ISSUED | New York Business Fire System | 06/16/2008 |
| BIS | PL | ISSUED | C.R.U. Mechan & Heating | 04/10/2008 |
| BIS | OT | ISSUED | Ein Contracting | 04/09/2008 |
| BIS | OT | ISSUED | Satkartar Group Development | 04/02/2008 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2018 | Complete | Green Power Electric | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/18/2018 | Final | JOEL PHAGOO | progress |