← Back
Miscellaneous religious facility
3080 WHITE PLAINS ROAD
BRONX · BIN 2055556
💬 Discuss this project
1931Year Built
1Stories
M9Building Class
R6Zoning
7,690 sfGross Floor Area
2Units
1 Open Violation ▸
Miscellaneous religious facility · Owner of record: MOUNT CARMEL PENTECOSTAL CHURCH INC · 10,000 sf lot · 0.77 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalGeneral
Roof3p · 2 filings · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 13p · 2 filings · 20 docs
Cellar7p · 2 filings · 20 docs
1 job · most recent 05/26/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScope
05/26/2025——Heating and Air Conditioning Systems, Ventilation Systems
1 job · most recent 05/26/2025
Sprinkler System
FiledStatusContractorScope
05/26/2025——Sprinkler System
1 job · most recent 05/26/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/26/2025——Gas, Storm, Water/Sanitary
1 job · most recent 05/26/2025
Steel Concrete Masonry
FiledStatusContractorScope
05/26/2025——Steel, Concrete, Masonry
1 job · most recent 05/26/2025
FiledStatusContractorScope
05/26/2025——5 kw
1 job · most recent 05/26/2025
Fence
FiledStatusContractorScope
05/26/2025——Fence
Building Lifecycle
All (112)Filed (11)Violation (23)Objection (55)Special Inspection (23)
04/10/2026
Objection resolved — Addressed
03/11/2026
Objection resolved — Addressed
03/05/2026
Objection resolved — Addressed
10/08/2025
Objection raised — Zoning
10/07/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
09/21/2025
Objection resolved — Addressed
09/20/2025
Objection resolved — Addressed
09/16/2025
Objection raised — Scope
09/11/2025
Objection resolved — Addressed
08/29/2025
Objection resolved — Addressed
07/23/2025
Special inspection requirement — Shutoff dampers
07/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
07/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
07/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
07/23/2025
Special inspection requirement — Maintenance information
07/01/2025
Objection resolved — Addressed
06/13/2025
Objection resolved — Addressed
06/03/2025
Objection raised — Admin
05/26/2025
Filed — Alteration CO
Renovation work for a 1-story church & horizontal and vertical addition at rear of building.
X01059401-S8
05/17/2025
Objection resolved — Addressed
05/17/2025
Objection resolved — Addressed
05/16/2025
Objection resolved — Addressed
05/15/2025
Objection raised — Admin
05/15/2025
Objection raised — Cost
05/15/2025
Objection raised — Scope
05/15/2025
Objection raised — Scope
05/15/2025
Objection raised — Scope
05/04/2025
Filed — Alteration
RENOVATION OF CELLAR, 1ST FLOOR AND ROOF. ALTERATION CO FILED UNDER APPLICATION X01059401-I1.
X01209271-I1
04/21/2025
Objection raised — Admin
04/21/2025
Objection raised — Admin
04/21/2025
Objection raised — Structural
04/10/2025
Objection raised — Other
04/09/2025
Objection raised — Admin
04/09/2025
Objection raised — Admin
04/09/2025
Objection resolved — Addressed
04/08/2025
Filed — Alteration CO
Renovation work for a 1-story church & horizontal and vertical addition at rear of building.
X01059401-S7
04/08/2025
Objection raised — Admin
04/07/2025
Filed — Alteration CO
Renovation work for a 1-story church & horizontal and vertical addition at rear of building.
X01059401-S6
03/31/2025
Objection raised — Energy
03/29/2025
Objection resolved — Addressed
03/29/2025
Objection resolved — Addressed
03/29/2025
Objection resolved — Addressed
03/29/2025
Objection resolved — Addressed
03/29/2025
Objection resolved — Addressed
03/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
03/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
03/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
03/06/2025
Special inspection requirement — Post-installed Anchors
03/06/2025
Special inspection requirement — Subgrade Inspections
03/06/2025
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
03/06/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
03/06/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
03/06/2025
Special inspection requirement — Concrete - Cast-In-Place
03/06/2025
Special inspection requirement — Post-installed Anchors
03/05/2025
Special inspection requirement — Footing and Foundation
03/05/2025
Special inspection requirement — Final
02/24/2025
Objection resolved — Addressed
02/24/2025
Objection resolved — Addressed
Latest 60 of 112 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MOUNT CARMEL PENTECOSTAL CHURCH IN2303/22/2026
MT CARMEL PENTECOSTAL CHURCH1303/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FIGURATIVE SPACE ARCHITECTURE, PLLC505/26/2025
CITYSCAPE ENGINEERING, PLLC304/08/2025
A&M CONSULTING310/05/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MAMC CONSULTING REPS1203/21/2026
FIGURATIVE SPACE ARCHITECTURE403/21/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISMHISSUEDRIVERSEA CONTRACTING INC.07/17/2006
BIS—ISSUEDOAK DRIVE DRIVE01/13/2006
BISEQISSUEDMASTROCOLA CONTR. CORP.02/14/1997
BISOTISSUEDMASTROCOLA CONTR. CORP.02/14/1997
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
07/23/2025Shutoff dampers—energy_progress
07/23/2025HVAC-R and service water heating system controls—energy_progress
07/23/2025HVAC-R and service water piping design and insulation—energy_progress
07/23/2025HVAC-R and service water heating equipment—energy_progress
07/23/2025Maintenance information—energy_progress
03/29/2025HVAC-R and service water piping design and insulation—energy_progress
03/29/2025HVAC-R and service water heating equipment—energy_progress
03/29/2025HVAC-R and service water heating system controls—energy_progress
03/06/2025Post-installed Anchors—special
03/06/2025Subgrade Inspections—special
03/06/2025Subsurface Conditions – Fill Placement & In-Place Density—special
03/06/2025Excavations - Sheeting, Shoring, and Bracing—special
03/06/2025Subsurface Investigations (Borings/Test Pits)—special
03/06/2025Concrete - Cast-In-Place—special
03/06/2025Post-installed Anchors—special
03/05/2025Footing and Foundation—progress
03/05/2025Final—progress
11/10/2024Public Assembly Emergency LightingOLULADE ADEMOKUNprogress
11/10/2024Public Assembly Emergency LightingOLULADE ADEMOKUNprogress
09/09/2024Sprinkler Systems—special
09/09/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
07/23/2024Final—progress
07/23/2024Mechanical Systems—special
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch9
08/19/2026X01209271-I1Request digital key ↗
08/15/2026X01059401-S7Request digital key ↗
08/15/2026X01059401-S1Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
08/20/2026X01140114-I1Request digital key ↗
08/20/2026X01140121-I1Request digital key ↗
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
06/13/2017220456619Open ↗
07/07/2015220456619Open ↗
▸BISPLACE OF ASSEMBLY1
03/08/2016220518857Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026X01059401-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X01059401-I1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/21/2026X01059401-S7Open ↗
08/21/2026X01059401-S6Open ↗
08/21/2026X01059401-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026X01140121-I1Open ↗
08/26/2026X01140114-I1Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/13/2017220456619Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST1
07/07/2015220456619Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01059401-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/13/2026X01059401-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/19/2026X01209271-I1Open ↗
08/15/2026X01059401-S7Open ↗
08/15/2026X01059401-S1Open ↗
Showing 3 of 6 on file for this type
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT2
08/13/2026X01059401-I1Open ↗
08/13/2026X01059401-S6Open ↗
▸Approvals, Objections & Sign-offs12
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/13/2026X01059401-I1Open ↗
08/13/2026X01059401-S1Open ↗
08/13/2026X01059401-S4Open ↗
Showing 3 of 11 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE1
07/07/2015220456619Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
07/07/2015220456619Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
06/13/2017220456619Open ↗
07/07/2015220456619Open ↗
▸Other Documents6
▸DOB NOWPlot Diagram3
08/13/2026X01059401-I1Open ↗
08/13/2026X01059401-S6Open ↗
08/13/2026X01059401-S7Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026X01059401-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026X01059401-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026X01059401-I1Open ↗