| Owner | Filings | Most Recent |
|---|---|---|
| ROYAL EXPEDITING | 6 | 07/08/2026 |
| 494 JACKSON | 39 | 07/08/2026 |
| 860 INVESTORS | 14 | 07/08/2026 |
| ROYAL BUILDERS GROUP | 9 | 07/08/2026 |
| 3082 VILLA REALTY LP | 3 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/29/2018 | $575K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| P GEORGOPOULOS ARCHITECT PC | 17 | 01/30/2024 |
| FL&M ENGINEERING DESIGN &INSPECTION | 3 | 10/16/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITING 4 U | 16 | 03/21/2026 |
| THE GREEN STUDIO | 3 | 03/21/2026 |
| KD DESIGNS | 1 | 03/21/2026 |
| MILLENNIUM DESIGNS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TARGET CONSTRUCTION LLC | General Contractor | 9 | 07/08/2026 |
| ENDRE BANYA | Electrical | 4 | 03/21/2026 |
| MC SUPERSTRUCTURE INC | General Contractor | 4 | 03/21/2026 |
| TFK ELECTRIC CORP 004849 | General Contractor | 4 | 03/22/2026 |
| ROYAL BUILDERS GROUP INC | General Contractor | 3 | 07/08/2026 |
| P GEORGOPOULOS ARCHITECT | General Contractor | 3 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| A. M. PLUMBING COMPANY | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 8 | 01/30/2024 |
| VICTOR SUBEN | 6672 | 5 | 06/20/2023 |
| ENTHINK ENGINEERS LLC | 6247 | 1 | 05/31/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | TARGET CONSTRUCTION LLC | 12/15/2023 |
| DOB NOW | Supported Scaffold | Signed-off | MC SUPERSTRUCTURE INC | 10/17/2023 |
| DOB NOW | General Construction | Permit Issued | TARGET CONSTRUCTION LLC | 09/11/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MC SUPERSTRUCTURE INC | 08/23/2023 |
| DOB NOW | Structural | Signed-off | TARGET CONSTRUCTION LLC | 08/09/2023 |
| DOB NOW | Plumbing | Signed-off | A. M. PLUMBING COMPANY | 08/08/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 08/08/2023 |
| DOB NOW | Earth Work | Signed-off | TARGET CONSTRUCTION LLC | 07/29/2023 |
| DOB NOW | Support of Excavation | Signed-off | TARGET CONSTRUCTION LLC | 07/27/2023 |
| DOB NOW | Construction Fence | Signed-off | TARGET CONSTRUCTION LLC | 04/27/2023 |
| DOB NOW | Construction Fence | Signed-off | ROYAL BUILDERS GROUP INC | 02/22/2023 |
| DOB NOW | Foundation | Signed-off | ROYAL BUILDERS GROUP INC | 06/02/2022 |
| BIS | EQ | ISSUED | ROYAL BUILDERS GROUP INC | 02/17/2023 |
| BIS | — | ISSUED | ROYAL BUILDERS GROUP INC | 02/17/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 01/30/2024 | Signed-off | TARGET CONSTRUCTION LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Heating |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/30/2024 | Signed-off | A. M. PLUMBING COMPANY | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/12/2023 | Complete | POWER DIRECT ELECTRIC INC | — |
| 09/07/2023 | Complete | TFK ELECTRIC CORP | 60 meters, 60 new_meters |
| 08/30/2023 | Complete | TFK ELECTRIC CORP | General Wiring |
| 08/04/2023 | Complete | TFK ELECTRIC CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/12/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/29/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/18/2024 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 01/17/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/11/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/06/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 08/24/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/24/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/17/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/13/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/13/2024 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 02/13/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 02/13/2024 | Air barrier continuity plan testing | FAHAD FATEH | energy_progress |
| 02/13/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 02/13/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 02/13/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 02/13/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 02/13/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 02/13/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 02/13/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 02/13/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 02/13/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 02/13/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 02/13/2024 | Metering | FAHAD FATEH | energy_progress |
| 02/13/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 02/13/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/13/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 02/09/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/09/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 02/09/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 02/09/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 02/09/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 02/09/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 02/09/2024 | Sprinkler Systems | FAHAD FATEH | special |