← Back
One family attached or semi-detached
309 EAST 7 STREET
BROOKLYN · Kensington · BIN 3124769
💬 Discuss this project
1915Year Built
2Stories
A5Building Class
R5Zoning
1,520 sfGross Floor Area
1Units
One family attached or semi-detached · 3,254 sf lot · 0.47 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 15 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/22/2014$995K—Private party → Private party$655/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ETRECTE LLC203/05/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRIOT ENERGY SOLUTIONS CORP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PATRIOT ENERGY SOL COGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ETRECTE LLC8116203/05/2026
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
03/10/2026
Signed off — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
B01216178-I1
03/06/2026
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
03/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
03/06/2026
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
03/06/2026
Special inspection requirement — Final
VYACHESLAV NECHAYEV
03/05/2026
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
B01216178-P1
08/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
08/08/2025
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
08/08/2025
Special inspection requirement — Final
VYACHESLAV NECHAYEV
08/08/2025
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
05/06/2025
Permit issued — Solar
B01216178-I1-SL
05/02/2025
Filed — Alteration
ROOFTOP SOLAR PANEL INSTALLATION
B01216178-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offPATRIOT ENERGY SOL CO05/06/2025
1 project · most recent 04/29/2025
FiledStatusContractorScope
04/29/2025CompleteMAK ELECTRICAL CONTR CORP1 meters
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
03/06/2026Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
03/06/2026Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
03/06/2026Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
03/06/2026FinalVYACHESLAV NECHAYEVprogress
08/08/2025Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
08/08/2025Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
08/08/2025FinalVYACHESLAV NECHAYEVprogress
08/08/2025Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026B01216178-P1Request digital key ↗
08/18/2026B01216178-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026B01216178-P1Open ↗
09/01/2026B01216178-P1Open ↗
09/01/2026B01216178-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026B01216178-P1Open ↗
08/18/2026B01216178-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026B01216178-P1Open ↗
08/22/2026B01216178-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/18/2026B01216178-P1Open ↗
08/18/2026B01216178-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01216178-I1Open ↗