← Back
General warehouse
31-22 COLLEGE POINT BLVD
QUEENS · College Point · BIN 4605716
💬 Discuss this project
2011Year Built
2Stories
E1Building Class
M2-1Zoning
65,413 sfGross Floor Area
1Units
LL97 Covered0 Open ViolationsFDNY Report ↗
General warehouse · Owner of record: ARES GROUP LLC · 174,240 sf lot · 0.38 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneralOther
Roof17p · 1 filing · 20 docs
Floor 213p · 3 filings · 20 docs
Floor 133p · 5 filings · 20 docs
Mezzanine4p · 2 filings · 18 docs
Cellar1p · 1 filing · 5 docs
Site & exterior1p · 1 filing · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ARES GROUP6907/08/2026
ARES GROUP LLC 82031503/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A1 EXPEDITING SERVICE CORP.2803/21/2026
A1 EXPEDITING SERVICE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WESBUILT CONSTRUCTION MANGeneral Contractor1107/08/2026
REEM PLBG & HTG CORPPlumbing207/08/2026
MIGUEL VALCARCELElectrical103/21/2026
SIRINA FIRE PROT CORPFire Protection107/08/2026
PAR PLUMBING CO., INCPlumbing107/08/2026
ROY B PLUMBING & HEATINGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SPECIAL INSPECTION SERVIC12001407/20/2022
Building Lifecycle
All (131)Filed (16)Permit Issued (13)Signed Off (8)Violation (22)Inspection (10)Objection (32)Special Inspection (30)
09/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/03/2022
Signed off — Alteration
Exterior parking lot re-surfacing with cleaning of existing drain inlets, adding drain inlets/trench drains. No change to total impervious area, existing detention tank, or existing storm/sanitary sewer connections.
Q00386305-I1
10/03/2022
Signed off — Alteration
(Civil Filing) Removal and replacement of existing asphalt parking lot, including all site lighting fixtures, drainage inlets and piping, and stormwater treatment vault.
Q00477782-I1
09/27/2022
Signed off — Alteration
OCCUPANT PROTECTION PLAN FOR INTERIOR RENOVATION. INTERIOR RENOVATION FILED SEPARATELY UNDER APP # 420667674.
Q00682820-I1
09/21/2022
Signed off — Alteration
installation of temporary construction fence. no change in use, occupancy or egress.
Q00582006-I1
08/11/2022
Signed off — Alteration
Modification to Sprinkler/Plumbing systems as per plans filed herewith.
Q00369701-I1
07/26/2022
Special inspection requirement — Sprinkler Systems
Christopher Drutjons
07/20/2022
Filed — Alteration
Modification to Sprinkler/Plumbing systems as per plans filed herewith.
Q00369701-P3
06/29/2022
Signed off — Alteration
Modification to mechanical system as per plans filed herewith.
Q00369743-I1
06/14/2022
Signed off — Alteration
Q00709077-I1
05/24/2022
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
05/19/2022
Special inspection requirement — Final
Christopher Drutjons
05/19/2022
Special inspection requirement — Mechanical Systems
Christopher Drutjons
05/19/2022
Special inspection requirement — Post-installed Anchors
Christopher Drutjons
05/19/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Christopher Drutjons
05/19/2022
Special inspection requirement — Energy Code Compliance Inspections
Christopher Drutjons
05/19/2022
Special inspection requirement — Lighting controls
Christopher Drutjons
05/19/2022
Special inspection requirement — HVAC-R and service water heating equipment
Christopher Drutjons
05/19/2022
Special inspection requirement — Interior lighting power
Christopher Drutjons
05/19/2022
Special inspection requirement — HVAC-R and service water heating system controls
Christopher Drutjons
05/17/2022
Objection resolved — Addressed
05/13/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/12/2022
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
05/12/2022
Objection raised — Other
05/05/2022
Filed — Alteration
Modification to mechanical system as per plans filed herewith.
Q00369743-P2
05/02/2022
Signed off — Alteration
Provide structural support to frame around floor openings @2nd- and Mezzanine Level and provide structural steel dunnage for roof equipment.
Q00371861-I1
04/19/2022
Filed — Alteration
Modification to Sprinkler/Plumbing systems as per plans filed herewith.
Q00369701-P2
04/12/2022
Special inspection requirement — Sprinkler Systems
Christopher Drutjons
04/08/2022
Permit issued — Boiler Equipment
Q00709077-I1-BE
04/05/2022
Filed — Alteration
Q00709077-I1
03/24/2022
Permit issued — General Construction
Q00682820-I1-GC
03/21/2022
Objection resolved — Addressed
03/19/2022
Objection raised — Other
03/18/2022
Permit issued — Construction Fence
Q00582006-I1-FN
03/16/2022
Permit issued — Structural
Q00371861-I1-ST
03/16/2022
Permit issued — Mechanical Systems
Q00369743-I1-MS
03/16/2022
Permit issued — General Construction
Q00477782-I1-GC
03/16/2022
Special inspection requirement — Final
Christopher Drutjons
03/16/2022
Special inspection requirement — Structural Steel - Welding
Christopher Drutjons
03/16/2022
Special inspection requirement — Structural Steel - High Strength Bolting
Christopher Drutjons
03/16/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Christopher Drutjons
03/16/2022
Special inspection requirement — Structural Steel - Details
Christopher Drutjons
03/16/2022
Special inspection requirement — Sprayed fire-resistant materials
Christopher Drutjons
03/14/2022
Filed — Alteration
Modification to mechanical system as per plans filed herewith.
Q00369743-P1
03/14/2022
Objection resolved — Addressed
03/14/2022
Special inspection requirement — Interior lighting power
Christopher Drutjons
03/14/2022
Special inspection requirement — Lighting controls
Christopher Drutjons
03/14/2022
Special inspection requirement — Energy Code Compliance Inspections
Christopher Drutjons
03/14/2022
Special inspection requirement — HVAC-R and service water heating system controls
Christopher Drutjons
03/14/2022
Special inspection requirement — HVAC-R and service water heating equipment
Christopher Drutjons
03/11/2022
Objection raised — Other
03/10/2022
Filed — Alteration
Exterior parking lot re-surfacing with cleaning of existing drain inlets, adding drain inlets/trench drains. No change to total impervious area, existing detention tank, or existing storm/sanitary sewer connections.
Q00386305-P1
03/10/2022
Objection resolved — Addressed
03/10/2022
Special inspection requirement — Concrete - Cast-In-Place
Christopher Drutjons
03/10/2022
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
EN-HUEI JOE
03/10/2022
Special inspection requirement — Subgrade Inspections
Christopher Drutjons
03/10/2022
Special inspection requirement — Final
Christopher Drutjons
03/08/2022
Filed — Alteration
Modification to Sprinkler/Plumbing systems as per plans filed herewith.
Q00369701-P1
03/08/2022
Objection raised — Admin
03/07/2022
Filed — Alteration
Provide structural support to frame around floor openings @2nd- and Mezzanine Level and provide structural steel dunnage for roof equipment.
Q00371861-P1
Latest 60 of 131 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offPAR PLUMBING CO., INC04/08/2022
DOB NOWGeneral ConstructionSigned-offWESBUILT CONSTRUCTION MAN03/24/2022
DOB NOWConstruction FenceSigned-offWESBUILT CONSTRUCTION MAN03/18/2022
DOB NOWStructuralSigned-offWESBUILT CONSTRUCTION MAN03/16/2022
DOB NOWMechanical SystemsSigned-offWESBUILT CONSTRUCTION MAN03/16/2022
DOB NOWGeneral ConstructionSigned-offWESBUILT CONSTRUCTION MAN03/16/2022
DOB NOWPlumbingSigned-offROY B PLUMBING & HEATING09/16/2021
DOB NOWConstruction FenceSigned-offWESBUILT CONSTRUCTION MAN08/26/2021
DOB NOWSprinklersSigned-offREEM PLBG & HTG CORP08/13/2021
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP08/09/2021
DOB NOWGeneral ConstructionSigned-offWESBUILT CONSTRUCTION MAN08/09/2021
DOB NOWMechanical SystemsSigned-offWESBUILT CONSTRUCTION MAN08/04/2021
DOB NOWStructuralSigned-offWESBUILT CONSTRUCTION MAN08/04/2021
BIS—ISSUEDWESBUILT CONSTRUCTION MAN03/15/2023
BIS—ISSUEDWESBUILT CONSTRUCTION MAN03/16/2022
BIS—ISSUEDWESBUILT CONSTRUCTION MAN03/16/2022
BIS—ISSUEDWESBUILT CONSTRUCTION MAN09/23/2021
BIS—ISSUEDWESBUILT CONSTRUCTION MAN09/23/2021
BISOTISSUEDORION DEVELOPMENT INC04/21/2011
BISMHISSUEDORION DEVELOPMENT INC04/21/2011
BISPLISSUEDPASQUALE QUARATINO INC06/22/2010
BISSPISSUEDHEADS UP FIRE SPRINKLER06/17/2010
BISCCISSUEDORION DEVELOPMENT INC06/15/2010
BISEQISSUEDORION DEVELOPMENT INC08/14/2009
BIS—ISSUEDORION DEVELOPMENT INC08/14/2009
BISEQISSUEDORION DEVELOPMENT INC10/15/2008
BIS—ISSUEDORION DEVELOPMENT INC12/20/2007
BISEQISSUEDORION DEVELOPMENT INC12/20/2007
1 project · most recent 08/22/2022
General Wiring
FiledStatusContractorScope
08/22/2022CompleteCORZO ELECTL SYS CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
05/24/2022Pass-Final Boiler Equipment InspectionPassView ↗
05/13/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/12/2022Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
02/17/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/17/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/19/2021Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/14/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
10/14/2021Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/08/2021Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/08/2021Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
07/26/2022Sprinkler SystemsChristopher Drutjonsspecial
05/19/2022FinalChristopher Drutjonsprogress
05/19/2022Mechanical SystemsChristopher Drutjonsspecial
05/19/2022Post-installed AnchorsChristopher Drutjonsspecial
05/19/2022Fire-Resistant Penetrations and JointsChristopher Drutjonsspecial
05/19/2022Energy Code Compliance InspectionsChristopher Drutjonsprogress
05/19/2022Lighting controlsChristopher Drutjonsenergy_progress
05/19/2022HVAC-R and service water heating equipmentChristopher Drutjonsenergy_progress
05/19/2022Interior lighting powerChristopher Drutjonsenergy_progress
05/19/2022HVAC-R and service water heating system controlsChristopher Drutjonsenergy_progress
04/12/2022Sprinkler SystemsChristopher Drutjonsspecial
03/16/2022FinalChristopher Drutjonsprogress
03/16/2022Structural Steel - WeldingChristopher Drutjonsspecial
03/16/2022Structural Steel - High Strength BoltingChristopher Drutjonsspecial
03/16/2022Structural Stability – Alterations of existing buildingsChristopher Drutjonsspecial
03/16/2022Structural Steel - DetailsChristopher Drutjonsspecial
03/16/2022Sprayed fire-resistant materialsChristopher Drutjonsspecial
03/14/2022Interior lighting powerChristopher Drutjonsenergy_progress
03/14/2022Lighting controlsChristopher Drutjonsenergy_progress
03/14/2022Energy Code Compliance InspectionsChristopher Drutjonsprogress
03/14/2022HVAC-R and service water heating system controlsChristopher Drutjonsenergy_progress
03/14/2022HVAC-R and service water heating equipmentChristopher Drutjonsenergy_progress
03/10/2022Concrete - Cast-In-PlaceChristopher Drutjonsspecial
03/10/2022Subsurface Investigations (Borings/Test Pits)EN-HUEI JOEspecial
03/10/2022Subgrade InspectionsChristopher Drutjonsspecial
Latest 25 of 43.
▾Documents — 330 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch - Plumbing6
08/26/2026Q00369701-P3Request digital key ↗
08/26/2026Q00369701-P2Request digital key ↗
08/26/2026Q00386305-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch5
08/27/2026Q00477782-I1Request digital key ↗
08/27/2026Q00477782-P1Request digital key ↗
08/27/2026Q00582006-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler4
08/26/2026Q00369701-P2Request digital key ↗
08/26/2026Q00369701-P3Request digital key ↗
08/15/2026Q00369701-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/15/2026Q00369743-P1Request digital key ↗
08/15/2026Q00369743-P2Request digital key ↗
08/14/2026Q00369743-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
08/15/2026Q00371861-P1Request digital key ↗
08/14/2026Q00371861-I1Request digital key ↗
▸Applications & Permits55
▸BISPLAN / WORK APPROVAL APPLICATION41
09/01/2023420667674Open ↗
08/24/2022440644386Open ↗
04/20/2022420667674Open ↗
Showing 3 of 41 on file for this type
▸BISWORK PERMIT APPLICATION9
10/01/2021420667674Open ↗
10/01/2021420667674Open ↗
10/01/2021420667674Open ↗
Showing 3 of 9 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
10/07/2011420187210Open ↗
10/07/2011420187201Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
11/18/2021440679053Open ↗
11/09/2021440679053Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
04/26/2022420667674Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISVERIFY TAX LOT1
10/03/2022420667674Open ↗
▸BISTAX LOT- FINAL LOT NUMBER ISSUED1
10/25/2011420187210Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
10/27/2023420667674Open ↗
▸Seals & Professional Certifications70
▸DOB NOWSpecial Inspector Seal & Signature25
09/23/2026Q00369701-I1Open ↗
09/02/2026Q00371861-P1Open ↗
09/02/2026Q00371861-P1Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/28/2026Q00369743-I1Open ↗
08/28/2026Q00369743-P2Open ↗
08/28/2026Q00369743-P1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWProgress Inspector Seal & Signature14
09/02/2026Q00371861-P1Open ↗
08/28/2026Q00369743-P1Open ↗
08/28/2026Q00369743-P1Open ↗
Showing 3 of 14 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
10/01/2021420667674Open ↗
10/01/2021420667674Open ↗
11/05/2020420667674Open ↗
Showing 3 of 12 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
06/21/2021440679053Open ↗
01/29/2021440644386Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/21/2021440679053Open ↗
▸Trade Schedules & Equipment56
▸BISSELF-CERT PLUMBING NOTICE18
06/15/2011420116430Open ↗
06/15/2011420116430Open ↗
06/09/2011420116430Open ↗
Showing 3 of 18 on file for this type
▸BISWATER METER PERMIT : DEP-METER10
04/18/2011420116430Open ↗
04/13/2011420116430Open ↗
04/13/2011420116430Open ↗
Showing 3 of 10 on file for this type
▸BISRPZ/DDCV TEST REPORT : GEN215B5
04/13/2011420116430Open ↗
04/12/2011420116430Open ↗
04/12/2011420116430Open ↗
Showing 3 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT5
07/14/2011420116430Open ↗
01/21/2011420116430Open ↗
01/21/2011420116430Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING4
01/21/2011420116430Open ↗
Showing 1 of 4 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION4
04/05/2011420116430Open ↗
Showing 1 of 4 on file for this type
▸BISEQUIPMENT USE PERMITS4
07/14/2011420116430Open ↗
07/14/2011420116430Open ↗
07/14/2011420116430Open ↗
Showing 3 of 4 on file for this type
▸BISSPRINKLER INSP REPORT : FP-851
04/18/2011420116430Open ↗
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA1
04/25/2011420114860Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
06/28/2022420667674Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
06/28/2022420667674Open ↗
▸BISSTANDPIPE INSP REPORT : FP-841
04/05/2011420116430Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST4
08/25/2023420667674Open ↗
08/11/2023440679053Open ↗
11/18/2021440679053Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREE SIGNOFF1
08/28/2023420667674Open ↗
▸BISSTREET TREES SITE PLAN1
08/28/2023420667674Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
04/22/2022420667674Open ↗
08/09/2021420667674Open ↗
01/29/2021440644386Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
10/01/2021420667674Open ↗
08/10/2020420667674Open ↗
08/10/2020420667674Open ↗
Showing 3 of 4 on file for this type
▸BISLIGHTING CONTROLS1
06/28/2022420667674Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
06/28/2022420667674Open ↗
▸BISINTERIOR LIGHTING POWER1
06/28/2022420667674Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
04/22/2022420667674Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00369743-I1Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY11
04/22/2022420667674Open ↗
08/09/2021420667674Open ↗
08/09/2021420667674Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSOIL REPORT2
08/13/2026Q00477782-I1Open ↗
08/13/2026Q00477782-P1Open ↗
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISSTRUCTURAL STABILITY - EXISTING BUILDINGS1
06/28/2022420667674Open ↗
▸BISSUBSURFACE / SOILS-FILL PLACEMENT IN-PLACE DENSITY1
06/28/2022420667674Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
06/28/2022420667674Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
06/28/2022420667674Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026Q00477782-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00477782-I1Open ↗
▸Approvals, Objections & Sign-offs29
▸BISSCHEDULE A - OCCUPANCY / USE9
04/20/2022420667674Open ↗
04/13/2022420667674Open ↗
04/12/2022420667674Open ↗
Showing 3 of 9 on file for this type
▸BISTAP LETTER - DOM SVC : DEP-DOM6
10/25/2011420187201Open ↗
04/18/2011420116430Open ↗
04/13/2011420116430Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
11/01/2011420119339Open ↗
10/07/2011420187210Open ↗
10/07/2011420187201Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
04/13/2011420116430Open ↗
04/13/2011420116430Open ↗
04/13/2011420116430Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT8
09/14/2021420667674Open ↗
05/20/2021420667674Open ↗
05/20/2021420667674Open ↗
Showing 3 of 8 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE1
10/01/2021420667674Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
10/03/2022420667674Open ↗
▸Filing & Intake Forms30
▸BISEFILING COVER SHEET14
11/05/2020420667674Open ↗
08/10/2020420667674Open ↗
08/10/2020420667674Open ↗
Showing 3 of 14 on file for this type
▸BISADDITIONAL INFORMATION11
04/21/2022420667674Open ↗
04/13/2022420667674Open ↗
04/12/2022420667674Open ↗
Showing 3 of 11 on file for this type
▸BISBOROUGH INTAKE FORM3
10/01/2021420667674Open ↗
08/10/2020420667674Open ↗
08/10/2020420667674Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
06/21/2021440679053Open ↗
01/29/2021440644386Open ↗
▸Other Documents9
▸BISPLOT DIAGRAM2
10/27/2023420667674Open ↗
09/22/2020420667674Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
10/27/2023420667674Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
09/23/2021440679053Open ↗
▸BISBPP: GRADE STUDY1
11/09/2021440679053Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
11/09/2021440679053Open ↗
▸BISBPP: CATCH BASIN/MANHOLE REQUIRED1
11/09/2021440679053Open ↗
▸BISBPP: INFRASTRUCTURE AND SITE SKETCH1
11/09/2021440679053Open ↗
▸BISFA SELF CERT DEFECT : FD-FASC1
06/30/2022420667674Open ↗