💬 Discuss this project
1955Year Built
1Stories
E1Building Class
M1-1Zoning
16,250 sfGross Floor Area
1Units
0 Open Violations
General warehouse · Owner of record: UTLEY'S, INC. · 14,842 sf lot · 1.09 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire Protection
Roof3p · 2 filings · 20 docs
Floor 16p · 2 filings · 19 docs
3 jobs · most recent 04/28/2026
Others Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
04/28/2026——Others
Other
Global Finish Solutions AMU-RAM-25-OHD-SP 15,000 CFM · Makeup Air ×1
05/06/2025——Air Conditioning Systems, Heating Systems
Cooling
Rheem RPNL-060CAZ Classic Series 5 Ton 260 LBS 60,000 BTU · Rooftop Unit ×2
Heating
Rgi RGI E521511 13,940 CFM ×2
04/02/2024Signed-offAUTOMOTIVE FACILITY SVCSVentilation Systems
Ventilation
Rgi RGI Spray Booth 19,290 CFM · Ductwork ×2
1 job · most recent 04/02/2024
Sprinkler System
FiledStatusContractorScope
04/02/2024Signed-offGO PRO FIRE PROTECTION CSprinkler System
2 jobs · most recent 04/28/2026
Gas
FiledStatusContractorScope
04/28/2026——Gas
04/02/2024Permit IssuedKCM PLUMBING & HEATING COGas
3 jobs · most recent 07/25/2024
General Wiring
FiledStatusContractorScope
07/25/2024CompleteELMAC ELECTRIC INC.General Wiring
04/22/2019Permit IssuedRICHARD NEU—
09/25/2018Permit IssuedA & A ELEC'L CONTR'G CORP1 meters, 1 new_meters
1 job · most recent 04/23/2019
Sidewalk Shed
FiledStatusContractorScope
04/23/2019Permit IssuedKAJ NY CONSTRUCTION INCSidewalk Shed
Building Lifecycle
All (48)Filed (11)Permit Issued (5)Signed Off (2)Violation (2)Inspection (5)Objection (8)Special Inspection (15)
07/04/2026
Objection resolved — Resolved
07/04/2026
Objection resolved — Resolved
07/04/2026
Objection resolved — Resolved
07/04/2026
Objection resolved — Resolved
05/15/2026
Objection raised — Scope
05/15/2026
Objection raised — Inspections
05/15/2026
Objection raised — Other
05/15/2026
Objection raised — Energy
04/28/2026
Filed — Alteration
Plumbing New Gas Piping for RTU and Make Up Air Heating Unit as per Plans, No change in use occupancy or egress.
Q01374404-I1
02/25/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/28/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/04/2025
Permit issued — Plumbing
Q00993457-S2-PL
05/20/2025
Special inspection requirement — Final
05/20/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
05/20/2025
Special inspection requirement — Mechanical Systems
Ashish Patel
05/06/2025
Filed — Alteration
RTU Unit for Air Conditioning of Work Area. Air Maker Unit for the Heating of the Open Face Spray Booths.
Q01138163-P2
05/06/2025
Filed — Alteration
RTU Unit for Air Conditioning of Work Area. Air Maker Unit for the Heating of the Open Face Spray Booths.
Q01138163-P3
05/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
04/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
04/23/2025
Special inspection requirement — Mechanical Systems
Ashish Patel
04/23/2025
Special inspection requirement — Final
04/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
03/22/2025
Filed — Alteration
RTU Unit for Air Conditioning of Work Area. Air Maker Unit for the Heating of the Open Face Spray Booths.
Q01138163-P1
03/18/2025
Special inspection requirement — Final
03/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
03/18/2025
Special inspection requirement — Mechanical Systems
Ashish Patel
01/08/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/11/2024
Filed — Alteration
RTU Unit for Air Conditioning of Work Area. Air Maker Unit for the Heating of the Open Face Spray Booths.
Q01138163-S1
11/08/2024
Filed — Alteration
RTU Unit for Air Conditioning of Work Area. Air Maker Unit for the Heating of the Open Face Spray Booths.
Q01138163-I1
10/31/2024
Violation issued (ECB, closed)
Construction
10/02/2024
Signed off — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-I1
09/30/2024
Signed off — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-S1
09/13/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/21/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/18/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/02/2024
Filed — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-P1
03/11/2024
Permit issued — Sprinklers
Q00993457-S1-EW-SP
02/27/2024
Permit issued — Plumbing
Q00993457-S2-PL
02/05/2024
Permit issued — General Construction
Q00993457-I1-GC-CX
01/30/2024
Filed — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-S2
01/29/2024
Special inspection requirement — Post-installed Anchors
Ashish Patel
01/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
01/26/2024
Filed — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-S1
01/22/2024
Filed — Alteration
Alteration Work for the Installation of Mini Open Face Paint Spray Booths and Associated Mechanical Exhaust System.
Q00993457-I1
01/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ashish Patel
01/21/2024
Special inspection requirement — Sprinkler Systems
Ashish Patel
04/24/2019
Permit issued — Sidewalk Shed
Q00157825-I1-SH
04/23/2019
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE.
Q00157825-I1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KAJ NY CONSTRUCTION407/08/2026
UTLEYS2407/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MAR ARCHITECTURE & ENGINEERING P.C.104/28/2026
ASHOK ARCHITECTURE DESIGN, PL/905/06/2025
GREEN DESIGN104/23/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ATLANTIC BUILDING SUPPLY INC.203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AUTOMOTIVE FACILITY SVCSGeneral Contractor203/21/2026
KCM PLUMBING & HEATING COPlumbing207/08/2026
GO PRO FIRE PROTECTION CFire Protection107/08/2026
KAJ NY CONSTRUCTION INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ASHOK ARCHITECTURE DESIGN6027905/06/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedKCM PLUMBING & HEATING CO08/04/2025
DOB NOWSprinklersSigned-offGO PRO FIRE PROTECTION C03/11/2024
DOB NOWPlumbingPermit IssuedKCM PLUMBING & HEATING CO02/27/2024
DOB NOWGeneral ConstructionSigned-offAUTOMOTIVE FACILITY SVCS02/05/2024
DOB NOWSidewalk ShedPermit IssuedKAJ NY CONSTRUCTION INC04/24/2019
BISMHISSUEDDYNAIRE LLC06/13/2019
BISPLISSUEDK.G. MECHANICAL INC06/13/2019
BISOTISSUEDNATIONAL GRID ENERGY MANA09/22/2015
BISSPISSUEDAUTOMATIC FIRE SPRINKLER INSTALL04/12/2005
BISMHISSUEDZETA MGT. CORP.10/14/2004
BISMHISSUEDDYNAIRE LLC01/29/2003
BISPLISSUEDSCHMELZ BROTHERS INC01/26/1999
BISOTISSUEDWINDSOR CONSTRUCTION CORP.12/22/1998
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
02/25/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/28/2026Pass-Final CND-Occupancy InspectionPassView ↗
09/13/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/21/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/18/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
05/20/2025Final—progress
05/20/2025Fire-Resistant Penetrations and JointsAshish Patelspecial
05/20/2025Mechanical SystemsAshish Patelspecial
05/06/2025Fire-Resistant Penetrations and JointsAshish Patelspecial
04/23/2025Fire-Resistant Penetrations and JointsAshish Patelspecial
04/23/2025Mechanical SystemsAshish Patelspecial
04/23/2025Final—progress
04/23/2025Fire-Resistant Penetrations and JointsAshish Patelspecial
03/18/2025Final—progress
03/18/2025Fire-Resistant Penetrations and JointsAshish Patelspecial
03/18/2025Mechanical SystemsAshish Patelspecial
01/29/2024Post-installed AnchorsAshish Patelspecial
01/29/2024Fire-Resistant Penetrations and JointsAshish Patelspecial
01/21/2024Fire-Resistant Penetrations and JointsAshish Patelspecial
01/21/2024Sprinkler SystemsAshish Patelspecial
▾Documents — 94 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch11
08/23/2026Q00993457-P1Request digital key ↗
08/23/2026Q00993457-S2Request digital key ↗
08/23/2026Q00993457-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
08/28/2026Q00157825-I1Request digital key ↗
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION5
06/12/2019440551975Open ↗
08/03/2018421639720Open ↗
06/14/2018421639720Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION4
06/12/2019440551975Open ↗
06/12/2019440551975Open ↗
06/12/2019440551975Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications22
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/23/2026Q00993457-P1Open ↗
08/23/2026Q00993457-S2Open ↗
08/23/2026Q00993457-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/02/2026Q01138163-P3Open ↗
08/29/2026Q01138163-S1Open ↗
08/29/2026Q00993457-S1Open ↗
Showing 3 of 6 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/12/2019440551975Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/12/2019440551975Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/01/2015440215839Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/12/2019440551975Open ↗
▸Trade Schedules & Equipment6
▸BISEQUIPMENT USE APPLICATION/PERMIT3
03/02/2021440551975Open ↗
03/02/2021440551975Open ↗
01/13/2021440551975Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
10/20/2021421639720Open ↗
▸BISSCHEDULE B - PLUMBING1
06/12/2019440551975Open ↗
▸BISEQUIPMENT USE PERMITS1
03/02/2021440551975Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/23/2026Q00993457-P1Open ↗
08/23/2026Q00993457-S2Open ↗
08/23/2026Q00993457-I1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
06/14/2018421639720Open ↗
09/18/2015440215839Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
06/12/2019440551975Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
12/31/2020440551975Open ↗
10/23/2020440551975Open ↗
06/12/2019440551975Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
12/31/2020440551975Open ↗
10/23/2020440551975Open ↗
02/18/2016440215839Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
02/25/2016440215839Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
09/18/2015440215839Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/12/2019440551975Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY5
12/31/2020440551975Open ↗
10/23/2020440551975Open ↗
06/12/2019440551975Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
03/02/2021440551975Open ↗
02/18/2016440215839Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/18/2016440215839Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
01/06/2021440551975Open ↗
10/23/2020440551975Open ↗
06/12/2019440551975Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms5
▸BISEFILING JOB APPLICATION COVER SHEET2
06/12/2019440551975Open ↗
07/01/2015440215839Open ↗
▸BISADDITIONAL INFORMATION2
11/19/2015440215839Open ↗
09/18/2015440215839Open ↗
▸BISEFILING COVER SHEET1
06/14/2018421639720Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
02/18/2016440215839Open ↗