REMOVE & INSTALL NEW WINDOWS, EXTERIOR DOOR & STOREFRONT, DOORS FOR ADA BATHRROMS & CLOSETS. REPAIR & REBUILD AREAS OF CRACKED BRICK MASONRY PARAPETS, INSTALL HANDRAILS AT PERIMETER OF STAIRWELL BULKHEADS & PARAPETS AND SITEWORK AS PER PLANS FILED
REMOVE & INSTALL NEW WINDOWS, EXTERIOR DOOR & STOREFRONT, DOORS FOR ADA BATHRROMS & CLOSETS. REPAIR & REBUILD AREAS OF CRACKED BRICK MASONRY PARAPETS, INSTALL HANDRAILS AT PERIMETER OF STAIRWELL BULKHEADS & PARAPETS AND SITEWORK AS PER PLANS FILED
INSTALLATION OF MECHANICAL SYSTEM AND ASSOCIATED DUCT & PIPING SYSTEM FOR PARTIAL FIRST FLOOR COMMUNITY ROOMS, REPLACEMENT OF A/C SLEEVES ON ALL FLOORS AS PER PLANS FILED
REPLACE EXG. FUEL OIL TANK WITH NEW 4,500 GAL. FUEL OIL TANK. NEW TANK ROOM TO BE ERECTED UNDER SEPARATE APPLICATION. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
18 documents · 1 drawing sheet
Nothing on file for this building.
Building Lifecycle
All (3)Inspection (3)
09/13/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing