← Back
Utility company land and building
31-45 20 AVENUE
QUEENS · BIN 4624437
💬 Discuss this project
0Year Built
—Stories
U0Building Class
M3-1Zoning
0 sfGross Floor Area
0Units
0 Open Violations
Utility company land and building · Owner of record: CHPE LLC · 342,720 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Permit Issued — active, not yet Signed-off
Roof9p · 4 filings · 20 docs
Floor 2Under Construction131p · 2 filings · 20 docs
Floor 1Under Construction130p · 2 filings · 20 docs
MezzanineUnder Construction129p · 1 filing · 19 docs
1 job · most recent 02/21/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
02/21/2024Signed-offKIEWIT INFRASTRUCTURE COHeating and Air Conditioning Systems
Heat / Cool
Lg ARUM072BTE5 72,000 BTU · Vrf Outdoor ×2
LUU180HHV 18,000 BTU · Vrf Outdoor ×2
LUU240HHV 24,000 BTU · Condensing Unit ×2
LUU420HHV 42,000 BTU · Condensing Unit ×2
1 job · most recent 05/31/2024
Water/Sanitary
FiledStatusContractorScope
05/31/2024——Water/Sanitary
6 jobs · most recent 05/06/2026
General Wiring
FiledStatusContractorScope
05/06/2026Permit IssuedMASS ELEC. CONSTR. CO.General Wiring
01/09/2025CompleteMASS ELEC. CONSTR. CO.General Wiring
09/16/2024CompleteMASS ELEC. CONSTR. CO.General Wiring
09/14/2024CompleteMASS ELEC. CONSTR. CO.General Wiring
09/14/2024CompleteMASS ELEC. CONSTR. CO.General Wiring
06/24/2024CompleteMASS ELEC. CONSTR. CO.—
2 jobs · most recent 12/07/2022
Steel
FiledStatusContractorScope
12/07/2022——1 scope_items
———Steel
Building Lifecycle
All (187)Filed (36)Permit Issued (63)Signed Off (23)Violation (3)Inspection (8)Objection (24)Special Inspection (30)
07/29/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
05/27/2026
Signed off — Alteration
Proposed HVAC units within auxiliary enclosures with associate piping and duct work. No change of use, egress or occupancy.
Q01000770-I1
05/11/2026
Signed off — Alteration
Proposed mechanical units and related duct work within building, all as per plan. No change to use, occupancy or egress.
Q00836891-I1
04/16/2026
Signed off — Alteration
Proposed Plumbing fixtures and related piping for Service building, as per plan. No change to egress, occupancy or use.
Q00836779-I1
04/08/2026
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
JOHN MCMONAGLE
04/08/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
JOHN MCMONAGLE
04/06/2026
Filed — Alteration
Proposed Plumbing fixtures and related piping for Service building, as per plan. No change to egress, occupancy or use.
Q00836779-P1
03/18/2026
Permit issued — Mechanical Systems
Q00836891-I1-MS
03/18/2026
Permit issued — Mechanical Systems
Q01000770-I1-MS
03/18/2026
Permit issued — General Construction
Q00803878-I1-GC
03/04/2026
Signed off — Alteration
Installation of foundation and concrete ramp and slab for Backup Control Center, as per plan. No change to use, occupancy or egress.
Q01143219-I1
02/09/2026
Permit issued — Mechanical Systems
Q00836891-I1-MS
02/09/2026
Permit issued — Mechanical Systems
Q01000770-I1-MS
02/06/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/03/2026
Signed off — Alteration
INSTALLATION OF MICRO PILES, FOUNDATION AND CIVIL WORK FOR PULL PIT. No change to egress, occupancy or use.
Q01242348-I1
01/26/2026
Signed off — Alteration
Q08038772-I1
01/02/2026
Signed off — Alteration
Q08038915-I1
12/31/2025
Signed off — Alteration
Proposed sprinkler system and associated equipment and pumps for service building, storage and transformers enclosures, all as per plans. No change of use, occupancy or use.
Q00843487-I1
12/30/2025
Signed off — Alteration
PROPOSED INSTALLATION OF BACK UP CONTROL CENTER ENCLOSURE ON ITS FOUNDATION WHICH HAS BEEN FILED UNDER APPLICATION # Q01143219-I1, APPROVED AND PERMITTED. THE MECHANICAL SYSTEM (HVAC) HAS BEEN FILED UNDER APPLICATION # Q01000770-I1.
Q01187601-I1
12/29/2025
Signed off — Alteration
proposed architectural package for auxiliary enclosures, all as per plan. no change of egress, occupancy or use.
Q08038688-I1
12/08/2025
Signed off — Alteration
Installation of Valve cooling system for power plant, all as per plan. No change to use, occupancy or egress.
Q00892758-I1
12/03/2025
Permit issued — General Construction
Q00803878-I1-GC
11/21/2025
Signed off — Alteration
Proposed civil work for site utility, all as per plan. No change of use, occupancy or use.
Q00889641-I1
11/21/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/05/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/30/2025
Signed off — Alteration
Proposed site drainage management and erosion and sediment control work, all as per plans. No change to use, occupancy or use.
Q00858043-I1
10/15/2025
Permit issued — Mechanical Systems
Q00836891-I1-MS
10/14/2025
Permit issued — Foundation
Q08038688-I1-FO
09/29/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/26/2025
Signed off — Alteration
Propose to install Valve Hangers, all as per plans. No changes to occupancy or egress or use.
Q01022332-I1
09/08/2025
Permit issued — General Construction
Q08038772-I1-GC-CX
09/04/2025
Permit issued — Plumbing
Q00836779-I1-PL
08/28/2025
Permit issued — Sprinklers
Q00843487-I1-EW-SP
08/25/2025
Signed off — Alteration
Proposed equipment and storage enclosures, all as per plan. No change to use, egress or occupancy.
Q00849578-I1
08/15/2025
Special inspection requirement — Structural Steel - Welding
08/15/2025
Special inspection requirement — Structural Cold-Formed Steel
08/15/2025
Special inspection requirement — Structural Steel - High Strength Bolting
08/15/2025
Special inspection requirement — Open-web Steel Joists and Joist Girders
08/08/2025
Permit issued — General Construction
Q01242348-I1-GC-CX
07/31/2025
Signed off — Alteration
Proposed Site structural support members, all as per plan. No change of use, egress or occupancy.
Q00849397-I1
07/31/2025
Special inspection requirement — Final
07/31/2025
Special inspection requirement — Structural Steel - Details
07/22/2025
Filed — Alteration
INSTALLATION OF MICRO PILES, FOUNDATION AND CIVIL WORK FOR PULL PIT. No change to egress, occupancy or use.
Q01242348-I1
07/15/2025
Signed off — Alteration
proposed architectural package for auxiliary enclosures, all as per plan. no change of egress, occupancy or use.
Q08038688-S1
07/14/2025
Signed off — Alteration
installation of construction fence to protect site during full demolition of tanks, and administrative building.
Q08051317-I1
06/23/2025
Permit issued — General Construction
Q00889641-I1-GC
06/20/2025
Permit issued — General Construction
Q00858043-I1-GC
06/18/2025
Special inspection requirement — Concrete - Precast
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Concrete - Cast-In-Place
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Dharmil Patel
06/18/2025
Special inspection requirement — Structural Steel - Welding
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Concrete – Prestressed
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Post-installed Anchors
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Structural Steel - High Strength Bolting
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Subgrade Inspections
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Structural Steel - Details
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Structural Cold-Formed Steel
JOHN MCMONAGLE
06/18/2025
Special inspection requirement — Deep Foundation Elements
Gregory Moormann
06/17/2025
Special inspection requirement — Final
JOHN MCMONAGLE
06/17/2025
Special inspection requirement — Footing and Foundation
JOHN MCMONAGLE
Latest 60 of 187 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TRANSMISSION DEVELOPERS3909/13/2026
CHPE9407/08/2026
KIEWIT INFRASTRUCTURE CO203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/14/2022$67.1M—ASTORIA GENERATING COMPANY, L.P. → ASTORIA AGGREGATOR CO. LLC— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
WALTER T GORMAN PE5903/21/2026
RPO403/21/2026
PATUXENT ENGINEERING603/21/2026
EXPEDITE DEM403/21/2026
WALTER T GORMAN P E P C103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KIEWIT INFRASTRUCTURE COGeneral Contractor6807/08/2026
SERVICE SCAFFOLD CO INCGeneral Contractor603/21/2026
SIRINA FIRE PROT CORPFire Protection307/08/2026
EVERGREEN MECHANICAL CORPPlumbing307/08/2026
MASS ELEC. CONSTR. CO.Electrical103/22/2026
INTERNATIONAL ASB. REMOVGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOMANI INSPECTION SERVICE8432804/06/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO03/18/2026
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO03/18/2026
DOB NOWGeneral ConstructionPermit IssuedKIEWIT INFRASTRUCTURE CO03/18/2026
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO02/09/2026
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO02/09/2026
DOB NOWGeneral ConstructionPermit IssuedKIEWIT INFRASTRUCTURE CO12/03/2025
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO10/15/2025
DOB NOWFoundationSigned-offKIEWIT INFRASTRUCTURE CO10/14/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO09/08/2025
DOB NOWPlumbingSigned-offEVERGREEN MECHANICAL CORP09/04/2025
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP08/28/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO08/08/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO06/23/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO06/20/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO05/14/2025
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO04/23/2025
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO03/10/2025
DOB NOWStructuralSigned-offKIEWIT INFRASTRUCTURE CO03/10/2025
DOB NOWGeneral ConstructionPermit IssuedKIEWIT INFRASTRUCTURE CO02/10/2025
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO02/10/2025
DOB NOWFoundationSigned-offKIEWIT INFRASTRUCTURE CO01/15/2025
DOB NOWStructuralSigned-offKIEWIT INFRASTRUCTURE CO10/30/2024
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO10/30/2024
DOB NOWSupported ScaffoldSigned-offSERVICE SCAFFOLD CO INC10/01/2024
DOB NOWStructuralSigned-offKIEWIT INFRASTRUCTURE CO09/30/2024
DOB NOWStructuralSigned-offKIEWIT INFRASTRUCTURE CO09/30/2024
DOB NOWGeneral ConstructionPermit IssuedKIEWIT INFRASTRUCTURE CO09/12/2024
DOB NOWSprinklersSigned-offSIRINA FIRE PROT CORP09/06/2024
DOB NOWPlumbingSigned-offEVERGREEN MECHANICAL CORP08/29/2024
DOB NOWFoundationSigned-offKIEWIT INFRASTRUCTURE CO08/06/2024
DOB NOWFoundationSigned-offKIEWIT INFRASTRUCTURE CO08/06/2024
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO07/15/2024
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO07/10/2024
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO07/08/2024
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO07/08/2024
DOB NOWFoundationSigned-offKIEWIT INFRASTRUCTURE CO06/17/2024
DOB NOWGeneral ConstructionSigned-offKIEWIT INFRASTRUCTURE CO06/17/2024
DOB NOWMechanical SystemsSigned-offKIEWIT INFRASTRUCTURE CO05/13/2024
DOB NOWStructuralSigned-offKIEWIT INFRASTRUCTURE CO05/13/2024
DOB NOWSupported ScaffoldSigned-offSERVICE SCAFFOLD CO INC05/10/2024
+ 15 more permits on file
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
07/29/2026Fail-Final CND-Occupancy InspectionFailView ↗
02/06/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/21/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/05/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/29/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/11/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/24/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/21/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
04/08/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)JOHN MCMONAGLEspecial
04/08/2026Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical ComponentsJOHN MCMONAGLEspecial
08/15/2025Structural Steel - Welding—special
08/15/2025Structural Steel - High Strength Bolting—special
08/15/2025Open-web Steel Joists and Joist Girders—special
08/15/2025Structural Cold-Formed Steel—special
07/31/2025Final—progress
07/31/2025Structural Steel - Details—special
06/18/2025Structural Cold-Formed SteelJOHN MCMONAGLEspecial
06/18/2025Concrete - Cast-In-PlaceJOHN MCMONAGLEspecial
06/18/2025Subsurface Investigations (Borings/Test Pits)Dharmil Patelspecial
06/18/2025Post-installed AnchorsJOHN MCMONAGLEspecial
06/18/2025Concrete – PrestressedJOHN MCMONAGLEspecial
06/18/2025Concrete - PrecastJOHN MCMONAGLEspecial
06/18/2025Deep Foundation ElementsGregory Moormannspecial
06/18/2025Subgrade InspectionsJOHN MCMONAGLEspecial
06/18/2025Structural Steel - High Strength BoltingJOHN MCMONAGLEspecial
06/18/2025Structural Steel - WeldingJOHN MCMONAGLEspecial
06/18/2025Structural Steel - DetailsJOHN MCMONAGLEspecial
06/17/2025FinalJOHN MCMONAGLEprogress
06/17/2025Footing and FoundationJOHN MCMONAGLEprogress
04/15/2025Footing and FoundationJOHN MCMONAGLEprogress
04/15/2025Structural Steel - WeldingJOHN MCMONAGLEspecial
04/15/2025Post-installed AnchorsJOHN MCMONAGLEspecial
04/15/2025Structural Steel - DetailsJOHN MCMONAGLEspecial
Latest 25 of 150.
▾Documents — 268 on file (BIS + DOB NOW)
▸Plans & Drawings37
▸DOB NOWPlans/Sketch37
08/25/2026Q08038688-S1Request digital key ↗
08/25/2026Q08038688-I1Request digital key ↗
08/25/2026Q08038772-I1Request digital key ↗
Showing 3 of 37 on file for this type
▸Applications & Permits7
▸BISWORK PERMIT APPLICATION5
09/28/2023421811668Open ↗
09/28/2023421811668Open ↗
04/11/2023421811677Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
12/29/2022421811668Open ↗
11/21/2022421811677Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/22/2026Q00803878-I1Open ↗
08/13/2026Q00803878-P1Open ↗
▸Seals & Professional Certifications117
▸DOB NOWSpecial Inspector Seal & Signature47
09/23/2026Q00889641-I1Open ↗
09/02/2026Q01022332-I1Open ↗
09/02/2026Q00836779-I1Open ↗
Showing 3 of 47 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature37
08/25/2026Q08038688-I1Open ↗
08/25/2026Q08038688-S1Open ↗
08/25/2026Q08038688-P1Open ↗
Showing 3 of 37 on file for this type
▸DOB NOWProgress Inspector Seal & Signature29
09/23/2026Q00889641-I1Open ↗
09/02/2026Q01022332-I1Open ↗
09/02/2026Q00836891-I1Open ↗
Showing 3 of 29 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
09/28/2023421811668Open ↗
09/28/2023421811668Open ↗
03/21/2023421811677Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment4
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
09/28/2023421811668Open ↗
▸BISWATER CUT-OFF1
09/28/2023421811668Open ↗
▸BISELECTRIC CUT-OFF1
09/28/2023421811668Open ↗
▸DOB NOWStandpipe Alarms Drawings1
08/22/2026Q00803878-I1—
▸Safety & Tenant Protection11
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
09/29/2023421811668Open ↗
04/11/2023421811677Open ↗
03/21/2023421811677Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST3
09/28/2023421811668Open ↗
04/11/2023421811677Open ↗
03/22/2023421811677Open ↗
▸DOB NOWStreet Tree Checklist3
08/22/2026Q00803878-I1Open ↗
08/13/2026Q00803878-P1Open ↗
08/13/2026Q01256698-I1Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
09/28/2023421811668Open ↗
03/21/2023421811677Open ↗
▸Environmental & Asbestos29
▸DOB NOWDEP ACP-5: Asbestos Assessment Report29
08/25/2026Q08038688-I1Open ↗
08/25/2026Q08038688-S1Open ↗
08/25/2026Q08039169-P1Open ↗
Showing 3 of 29 on file for this type
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/23/2026Q00836891-I1Open ↗
▸Inspections & Test Reports12
▸DOB NOWSOIL REPORT5
08/13/2026Q08038688-P1Open ↗
08/13/2026Q08038688-I1Open ↗
08/13/2026Q01242348-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram4
08/13/2026Q01242348-I1Open ↗
08/13/2026Q08038688-I1Open ↗
Showing 2 of 4 on file for this type
▸DOB NOWTR5 Test Report3
08/13/2026Q01242348-I1Open ↗
08/13/2026Q08038772-I1Open ↗
08/13/2026Q08038188-I1Open ↗
▸Approvals, Objections & Sign-offs17
▸BISLETTERS - SUPPORTING DOCUMENTATION16
09/29/2023421811668Open ↗
09/29/2023421811668Open ↗
09/29/2023421811668Open ↗
Showing 3 of 16 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION1
03/21/2023421811677Open ↗
▸Cost, Insurance & Ownership6
▸BISPROJECT-SPECIFIC GL INSURANCE3
09/28/2023421811668Open ↗
04/11/2023421811677Open ↗
03/21/2023421811677Open ↗
▸BISDEPT OF FINANCE VERIFICATION3
09/29/2023421811668Open ↗
04/11/2023421811677Open ↗
03/21/2023421811677Open ↗
▸Filing & Intake Forms14
▸BISADDITIONAL INFORMATION7
09/29/2023421811668Open ↗
09/28/2023421811668Open ↗
04/11/2023421811677Open ↗
Showing 3 of 7 on file for this type
▸BISBOROUGH INTAKE FORM5
09/29/2023421811668Open ↗
04/11/2023421811677Open ↗
03/21/2023421811677Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET2
12/29/2022421811668Open ↗
11/21/2022421811677Open ↗
▸Other Documents11
▸DOB NOWSite Survey: Initial3
08/22/2026Q00803878-I1Open ↗
08/13/2026Q01256698-I1Open ↗
08/13/2026Q00803878-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/22/2026Q00803878-I1Open ↗
08/13/2026Q01256698-I1Open ↗
08/13/2026Q00803878-P1Open ↗
▸DOB NOWProperty Ownership Certification3
08/22/2026Q00803878-I1Open ↗
08/13/2026Q00803878-P1Open ↗
08/13/2026Q01256698-I1Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026Q08038050-I1Open ↗
08/13/2026Q08038915-I1Open ↗