Roof11p · 4 filings · 19 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
APPLICATION FILED FOR FACADE REPAIRS AS PER COMMENTS HERE WITHIN. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
On file for this project
6 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Mechanical systems - Radon Mitigation System
On file for this project
4 documents
Latest 3 of 4 filings on this floor.
Floor 84p · 1 filing · 3 docs
EquipmentStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 74p · 1 filing · 3 docs
EquipmentStructural
Issued Permit Scope
Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 617p · 2 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
REPLACE ALL REGISTERS IN KIND AND PROVIDE FIRE DAMPER AT FLOORS 2 THRU 6 WITHIN THE G LINE BATHROOMS AS PER PLANS FILED.
On file for this project
22 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 517p · 2 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
REPLACE ALL REGISTERS IN KIND AND PROVIDE FIRE DAMPER AT FLOORS 2 THRU 6 WITHIN THE G LINE BATHROOMS AS PER PLANS FILED.
On file for this project
22 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 417p · 2 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
REPLACE ALL REGISTERS IN KIND AND PROVIDE FIRE DAMPER AT FLOORS 2 THRU 6 WITHIN THE G LINE BATHROOMS AS PER PLANS FILED.
On file for this project
22 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 317p · 2 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
REPLACE ALL REGISTERS IN KIND AND PROVIDE FIRE DAMPER AT FLOORS 2 THRU 6 WITHIN THE G LINE BATHROOMS AS PER PLANS FILED.
On file for this project
22 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 218p · 2 filings · 20 docs
ArchitectureEquipmentMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Supported Scaffold
REPLACE ALL REGISTERS IN KIND AND PROVIDE FIRE DAMPER AT FLOORS 2 THRU 6 WITHIN THE G LINE BATHROOMS AS PER PLANS FILED.
On file for this project
22 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents
Floor 1Under Construction6p · 2 filings · 10 docs
MechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
Reinforcing and replacing areas of damaged slab at the 1st Floor, Basement & Cellar. No change in use, zoning, or egress.
On file for this project
6 documents · 1 drawing sheet
Mechanical systems - Radon Mitigation System
On file for this project
4 documents · 1 drawing sheet
CellarUnder Construction2p · 1 filing · 6 docs
Structural
Issued Permit Scope
Structural
Reinforcing and replacing areas of damaged slab at the 1st Floor, Basement & Cellar. No change in use, zoning, or egress.
On file for this project
6 documents · 1 drawing sheet
Sub-BasementUnder Construction1p · 1 filing · 6 docs
Structural
Issued Permit Scope
Structural
Reinforcing and replacing areas of damaged slab at the 1st Floor, Basement & Cellar. No change in use, zoning, or egress.
On file for this project
6 documents
Site & exterior18p · 5 filings · 20 docs
ArchitectureEquipmentGeneralStructural
Issued Permit Scope
General Construction · Sidewalk Shed · Supported Scaffold
APPLICATION FILED FOR FACADE REPAIRS AS PER COMMENTS HERE WITHIN. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION
On file for this project
6 documents · 8 drawing sheets
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 4 drawing sheets
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
3 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.