| Owner | Filings | Most Recent |
|---|---|---|
| Florida Man Development | 53 | 10/13/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/15/2023 | $3.6M | — | Private party → Florida Man Development | $666/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Michael House Architect | 6 | 08/20/2026 |
| D'Antonio Consulting Engineers | 6 | 08/05/2025 |
| Ashraf | 2 | 07/16/2025 |
| Silman | 3 | 03/20/2025 |
| Bilow Engineering | 4 | 03/17/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Nexus Consulting NYC | 17 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| New Reliant Construction | General Contractor | 7 | 04/09/2026 |
| Triboro Construction Associates | General Contractor | 7 | 07/08/2026 |
| KMN Builders | General Contractor | 2 | 04/09/2026 |
| Alpha Scaffolding | Scaffold | 2 | 07/08/2026 |
| QMB Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| QMB Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Ans Consultants | 1768 | 15 | 08/20/2026 |
| Michael House Architect | 7910 | 6 | 08/20/2026 |
| D'Antonio Consulting Engineering | 931 | 6 | 08/05/2025 |
| Impact Concrete & Control | 864 | 2 | 03/20/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | New Reliant Construction | 09/08/2025 |
| DOB NOW | Supported Scaffold | Signed-off | Alpha Scaffolding | 07/17/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | Alpha Scaffolding | 06/24/2025 |
| DOB NOW | Mechanical Systems | Signed-off | New Reliant Construction | 04/21/2025 |
| DOB NOW | Foundation | Signed-off | Triboro Construction Associates | 03/13/2025 |
| DOB NOW | Support of Excavation | Signed-off | Triboro Construction Associates | 03/13/2025 |
| DOB NOW | Foundation | Signed-off | Triboro Construction Associates | 03/13/2025 |
| DOB NOW | General Construction | Permit Issued | Triboro Construction Associates | 03/13/2025 |
| DOB NOW | Plumbing | Signed-off | QMB Plumbing & Heating | 03/12/2025 |
| DOB NOW | Sprinklers | Signed-off | QMB Plumbing & Heating | 03/12/2025 |
| DOB NOW | General Construction | Permit Issued | Triboro Construction Associates | 02/28/2025 |
| DOB NOW | Foundation | Signed-off | KMN Builders | 07/24/2024 |
| DOB NOW | Support of Excavation | Signed-off | KMN Builders | 07/23/2024 |
| DOB NOW | Structural | Signed-off | New Reliant Construction | 11/30/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/20/2026 | Signed-off | New Reliant Construction | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAM2-U1 42,000 BTU · Heat Pump Outdoor ×8 PEFY-P12NMAU-E4 13,500 BTU · Vrf Indoor ×4 PEFY-P24NMAU-E4 27,000 BTU · Vrf Indoor ×4 PVFY-P12NAMU-E1 13,500 BTU · Vrf Indoor ×4 PVFY-P12NAMU-E4 6,700 BTU · Vrf Indoor ×2 PVFY-P18NAMU-E1 20,000 BTU · Vrf Indoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | QMB Plumbing & Heating | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | QMB Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2026 | Complete | KJK Electric | General Wiring |
| 06/23/2025 | Complete | Richard Neu | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/20/2026 | Signed-off | New Reliant Construction | Steel, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/05/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/02/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/20/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/08/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/08/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/08/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/03/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/28/2026 | Fire-Resistant Penetrations and Joints | MICHAEL HOUSE | special |
| 08/28/2026 | Interior lighting power | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Metering | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Fenestration areas | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Lighting in dwelling units | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Fenestration air leakage | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Maintenance information | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Lighting controls | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Exterior lighting power | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Fenestration and door U-factor and product ratings | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Insulation placement and R values | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Air barrier - visual inspection | MICHAEL HOUSE | energy_progress |
| 08/28/2026 | Energy Code Compliance Inspections | MICHAEL HOUSE | progress |
| 08/28/2026 | Fire-Resistance Rated Construction | MICHAEL HOUSE | progress |
| 08/28/2026 | Structural Stability – Alterations of existing buildings | ATULKUMAR SHAH, PE | special |
| 08/19/2026 | Structural Stability – Alterations of existing buildings | ATULKUMAR SHAH, PE | special |
| 08/19/2026 | Metering | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Lighting controls | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Lighting in dwelling units | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Fenestration air leakage | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Fenestration and door U-factor and product ratings | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Exterior lighting power | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Interior lighting power | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Insulation placement and R values | MICHAEL HOUSE | energy_progress |
| 08/19/2026 | Fenestration areas | MICHAEL HOUSE | energy_progress |