💬 Discuss this project
0Year Built
—Stories
V1Building Class
R7AZoning
0 sfGross Floor Area
0Units
Zoned commercial or Manhattan residential · Owner of record: NYC Housing Preservation and Development · 1,682 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofLemor Development GroupUnder Construction12p · 5 filings · 20 docs
BulkheadResidential structural framingUnder Construction1p · 1 filing · 13 docs
Floor 4Lemor Development GroupUnder Construction12p · 4 filings · 20 docs
Floor 3Lemor Development GroupUnder Construction11p · 4 filings · 20 docs
Floor 2Lemor Development GroupUnder Construction11p · 4 filings · 20 docs
Floor 1Iris Lemor HarlemUnder Construction16p · 5 filings · 20 docs
CellarLemor Development GroupUnder Construction13p · 4 filings · 20 docs
Site & exteriorLemor Development GroupUnder Construction9p · 2 filings · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Lemor Development Group1110/21/2026
NYC Department of Housing Preservation and Development506/28/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Paul Perdek, Prof. Engineering310/20/2026
Cityscape409/17/2026
Pronto103/12/2026
Ettinger Engineering Associates308/29/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
William Vitacco Associates403/21/2026
DVA Advisors103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Foremost Contracting & BUGeneral Contractor208/30/2026
Rockledge ScaffoldScaffold210/21/2026
Kepler Electrical ContElectrical103/21/2026
Foremost Contracting & BUScaffold107/08/2026
Reliable Plumbing & HeatingPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
American Construction Tes9731609/17/2026
Building Lifecycle
All (70)Filed (11)Permit Issued (6)Objection (40)Special Inspection (13)
10/20/2026
Filed — Alteration
TEMPORARY ROOF / OVERHEAD PROTECTION AT ADJOINING PROPERTIES DURING NB CONST, FILED SEP. ROOF / OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01470004-I1
10/20/2026
Filed — Alteration
TEMPORARY ROOF / OVERHEAD PROTECTION AT ADJOINING PROPERTIES DURING NB CONST, FILED SEP. ROOF / OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01470004-S2
10/20/2026
Filed — Alteration
TEMPORARY ROOF / OVERHEAD PROTECTION AT ADJOINING PROPERTIES DURING NB CONST, FILED SEP. ROOF / OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01470004-S1
10/20/2026
Permit issued — Construction Fence
M01470004-I1-FN
10/20/2026
Permit issued — Protection and Mechanical Methods
M01470004-S2-PMM
09/24/2026
Special inspection requirement — Post-installed Anchors
09/17/2026
Filed — Alteration
Structural work in conjunction with NB# 121207979
M00419428-P1
09/17/2026
Special inspection requirement — Post-installed Anchors
08/27/2026
Permit issued — Support of Excavation
M00575459-I1-SE
08/24/2026
Filed — Alteration
SOE work in conjunction with NB# 121207979
M00575459-P1
08/12/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
EDWIN HOPKINS
08/05/2026
Special inspection requirement — Final
EDWIN HOPKINS
08/05/2026
Special inspection requirement — Post-installed Anchors
EDWIN HOPKINS
08/05/2026
Special inspection requirement — Concrete - Cast-In-Place
EDWIN HOPKINS
08/05/2026
Special inspection requirement — Structural Cold-Formed Steel
EDWIN HOPKINS
06/18/2026
Permit issued — Plumbing
M00350113-I1-PL
04/22/2026
Permit issued — Structural
M00419428-I1-ST
04/15/2026
Permit issued — Construction Fence
M01369566-I1-FN
03/12/2026
Filed — Alteration
M01369566-I1
08/29/2025
Filed — Alteration
M00350125-I1
02/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
EDWIN HOPKINS
01/24/2025
Objection raised — Other
01/24/2025
Objection resolved — Addressed
01/22/2025
Filed — Alteration
SOE work in conjunction with NB# 121207979
M00575459-I1
03/24/2022
Filed — Alteration
M00350113-I1
03/13/2022
Objection raised — Other
03/13/2022
Objection resolved — Addressed
03/13/2022
Objection raised — Structural
03/13/2022
Objection resolved — Addressed
03/13/2022
Objection raised — Other
03/13/2022
Objection resolved — Addressed
03/13/2022
Objection raised — Admin
03/13/2022
Objection resolved — Addressed
03/07/2022
Filed — Alteration
Structural work in conjunction with NB# 121207979
M00419428-I1
03/04/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
EDWIN HOPKINS
02/18/2022
Special inspection requirement — Concrete - Cast-In-Place
EDWIN HOPKINS
02/18/2022
Special inspection requirement — Structural Cold-Formed Steel
EDWIN HOPKINS
10/26/2020
Special inspection requirement — Final
EDWIN HOPKINS
05/18/2020
Special inspection requirement — Sprinkler Systems
EDWIN HOPKINS
05/13/2020
Objection raised — Fire_Protection
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Inspections
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Scope
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Inspections
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Zoning
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Mechanical
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Scope
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Structural
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Structural
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Admin
05/13/2020
Objection resolved — Resolved
05/13/2020
Objection raised — Zoning
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedRockledge Scaffold10/20/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedRockledge Scaffold10/20/2026
DOB NOWSupport of ExcavationPermit IssuedForemost Contracting & BU08/27/2026
DOB NOWPlumbingPermit IssuedReliable Plumbing & Heating06/18/2026
DOB NOWStructuralPermit IssuedForemost Contracting & BU04/22/2026
DOB NOWConstruction FencePermit IssuedForemost Contracting & BU04/15/2026
1 project · most recent 05/11/2020
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/11/2020——Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
— LSN090HSV5 9,000 BTU · Vrf Indoor ×1
LSU90HSV5 9,000 BTU · Vrf Outdoor ×1
Heating
Ephoca APE10N3H2 10,500 BTU · Ptac ×7
3 projects · most recent 10/20/2026
General Wiring
FiledStatusContractorScope
10/20/2026Permit IssuedAnthony G Ferry—
06/26/2026Permit IssuedKepler Electrical Cont1 meters, 1 new_meters
12/21/2025Permit IssuedKepler Electrical ContGeneral Wiring
2 projects · most recent 09/17/2026
Concrete
FiledStatusContractorScope
09/17/2026Permit IssuedForemost Contracting & BUConcrete
08/24/2026Permit IssuedForemost Contracting & BU2 scope_items
1 project · most recent 10/20/2026
Fence Sidewalk Shed
FiledStatusContractorScope
10/20/2026Permit IssuedRockledge ScaffoldFence, Sidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
09/24/2026Post-installed Anchors—special
09/17/2026Post-installed Anchors—special
08/12/2026Excavations - Sheeting, Shoring, and BracingEDWIN HOPKINSspecial
08/05/2026FinalEDWIN HOPKINSprogress
08/05/2026Post-installed AnchorsEDWIN HOPKINSspecial
08/05/2026Concrete - Cast-In-PlaceEDWIN HOPKINSspecial
08/05/2026Structural Cold-Formed SteelEDWIN HOPKINSspecial
02/18/2025Fire-Resistant Penetrations and JointsEDWIN HOPKINSspecial
03/04/2022Fire-Resistant Penetrations and JointsEDWIN HOPKINSspecial
02/18/2022Concrete - Cast-In-PlaceEDWIN HOPKINSspecial
02/18/2022Structural Cold-Formed SteelEDWIN HOPKINSspecial
10/26/2020FinalEDWIN HOPKINSprogress
05/18/2020Sprinkler SystemsEDWIN HOPKINSspecial
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Iris Lemor HarlemOtherFloor 1
Project M01369566 Alteration · Permit Entire · 03/12/2026
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 90 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch6
10/21/2026M01470004-I1Request digital key ↗
10/21/2026M01470004-S1Request digital key ↗
10/21/2026M01470004-S2Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Structural2
09/02/2026M00419428-P1Request digital key ↗
09/02/2026M00419428-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
08/21/2026M00350125-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00347995-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/02/2026M00350113-I1Request digital key ↗
▸Applications & Permits11
▸BISPLAN / WORK APPROVAL APPLICATION10
02/19/2026121207979Open ↗
04/03/2025121207979Open ↗
03/24/2025121207979Open ↗
Showing 3 of 10 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
02/23/2022141007568Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM2
06/14/2022121207979Open ↗
05/06/2022121207979Open ↗
▸Seals & Professional Certifications21
▸DOB NOWDPL-1: Design Professional Seal & Signature12
10/21/2026M01470004-S2Open ↗
10/21/2026M01470004-I1Open ↗
10/21/2026M01470004-S1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
10/05/2026M00419428-P1Open ↗
09/23/2026M00575459-P1Open ↗
09/01/2026M00419428-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
10/05/2026M00419428-P1Open ↗
09/01/2026M00419428-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
02/23/2022141007568Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/23/2022141007568Open ↗
▸Trade Schedules & Equipment1
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
05/06/2022121207979Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
02/03/2026121207979Open ↗
▸BISBPP: STREET TREES SITE PLAN1
02/23/2022141007568Open ↗
▸BISSTREET TREE CHECKLIST1
05/06/2022121207979Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
02/03/2026121207979Open ↗
06/14/2022121207979Open ↗
05/06/2022121207979Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY5
07/11/2022121207979Open ↗
05/06/2022121207979Open ↗
05/06/2022121207979Open ↗
Showing 3 of 5 on file for this type
▸BISSOIL REPORT1
05/06/2022121207979Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
05/06/2022121207979Open ↗
▸Approvals, Objections & Sign-offs21
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter6
09/02/2026M00419428-P1Open ↗
09/02/2026M00419428-I1Open ↗
08/25/2026M00575459-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
09/02/2026M00419428-P1Open ↗
09/02/2026M00419428-I1Open ↗
08/25/2026M00575459-P1Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE4
05/05/2022121207979Open ↗
02/09/2022121207979Open ↗
02/07/2022121207979Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)3
09/02/2026M00419428-I1Open ↗
08/13/2026M00575459-I1Open ↗
08/13/2026M01369566-I1Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)2
05/06/2022121207979Open ↗
02/23/2022141007568Open ↗
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL1
05/06/2022121207979Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION4
07/11/2022121207979Open ↗
07/11/2022121207979Open ↗
07/11/2022121207979Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET1
06/02/2020121207979Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/23/2022141007568Open ↗
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
07/11/2022121207979Open ↗
▸BISPLOT DIAGRAM1
06/14/2022121207979Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
05/06/2022121207979Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll1
08/13/2026M00347995-I1Open ↗