| Owner | Filings | Most Recent |
|---|---|---|
| GPG MANAGEMENT | 9 | 07/08/2026 |
| JJS BUILDERS | 13 | 07/08/2026 |
| GPG 314 E. 91 LLC | 2 | 03/22/2026 |
| GPG 314 E. 91ST LLC | 1 | 03/22/2026 |
| JJG BUILDERS | 1 | 03/22/2026 |
| AXIAK CONSTRUCTION | 1 | 03/22/2026 |
| J&G CONSTRUCTION INC | 1 | 03/21/2026 |
| USA CONSTRUCTION & PAINTING | 3 | 03/21/2026 |
| CARYL YORK REALTY | 2 | 03/21/2026 |
| J G GENERAL CONTRACTING | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/29/2018 | $6.2M | — | CARYL YORK REALTY CORP. → GPG 314 E. 91 LLC | $698/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MARK GOULD ARCHITECT | 8 | 11/02/2022 |
| GREEN DESIGN | 7 | 09/04/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 8 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JJS BUILDERS | General Contractor | 6 | 07/08/2026 |
| AXIAK CONSTRUCTION CORP | General Contractor | 3 | 07/08/2026 |
| RULLO, ANTHONY | Electrical | 2 | 03/21/2026 |
| FRANK FODERA | Electrical | 2 | 03/21/2026 |
| MARTY ALLEN ELEC'L CO.,IN | Electrical | 2 | 03/21/2026 |
| LOTUS METROPOLITAN CONSTRUCTION | General Contractor | 2 | 07/08/2026 |
| COURTESY PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| SYED-NAQVI ALTAF | Electrical | 1 | 03/21/2026 |
| VISHWADAT MATAPERSAD | Electrical | 1 | 03/21/2026 |
| SYED-NAQVI, ALTAF | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MARK GOULD ARCHITECT | 1933 | 8 | 11/02/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | AXIAK CONSTRUCTION | 11/30/2022 |
| DOB NOW | Mechanical Systems | Signed-off | AXIAK CONSTRUCTION | 04/28/2021 |
| DOB NOW | Plumbing | Signed-off | EDGECOMBE PLBG & HTG INC | 04/22/2021 |
| DOB NOW | Mechanical Systems | Signed-off | LOTUS METROPOLITAN CONSTR | 04/20/2021 |
| DOB NOW | General Construction | Signed-off | LOTUS METROPOLITAN CONSTR | 04/19/2021 |
| DOB NOW | Plumbing | Signed-off | EDGECOMBE PLBG & HTG INC | 06/08/2020 |
| DOB NOW | Sidewalk Shed | Permit Issued | JJS BUILDERS | 03/26/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | JJS BUILDERS | 03/21/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | JJS BUILDERS | 03/05/2019 |
| DOB NOW | Sidewalk Shed | Permit Issued | JJS BUILDERS | 03/05/2019 |
| BIS | OT | ISSUED | AXIAK CONSTRUCTION CORP | 03/10/2020 |
| BIS | PL | ISSUED | COURTESY PLUMBING INC | 05/30/2019 |
| BIS | OT | ISSUED | AXIAK CONSTRUCTION CORP | 05/23/2019 |
| BIS | OT | ISSUED | JJS BUILDERS | 04/01/2019 |
| BIS | PL | ISSUED | COURTESY PLUMBING INC | 02/19/2019 |
| BIS | MH | ISSUED | BUILD TO FIT CORP | 02/12/2019 |
| BIS | PL | ISSUED | COURTESY PLUMBING INC | 11/02/2018 |
| BIS | OT | ISSUED | AP-TECH CONTRACTING CORP | 11/16/2017 |
| BIS | PL | ISSUED | COURTESY PLUMBING INC | 07/22/2016 |
| BIS | PL | ISSUED | A. M. PLUMBING COMPANY | 08/19/2015 |
| BIS | OT | ISSUED | JZB CONSTRUCTION CO LLC | 07/21/2015 |
| BIS | FB | ISSUED | ROCKWAY FUEL OIL CORP | 12/29/2014 |
| BIS | EQ | ISSUED | J & G GNRL CONTRACT CORP | 08/10/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2021 | Permit Issued | PAUL M. & SON'S ELECL CON | General Wiring |
| 03/04/2019 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2019 | Permit Issued | JJS BUILDERS | Scaffold |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/08/2021 | Interior lighting power | Mark Gould | energy_progress |
| 09/08/2021 | Lighting in dwelling units | Mark Gould | energy_progress |
| 09/08/2021 | Final | Mark Gould | progress |
| 09/08/2021 | Energy Code Compliance Inspections | Mark Gould | progress |
| 09/08/2021 | Fire-Resistance Rated Construction | Mark Gould | progress |
| 09/08/2021 | Fire-Resistant Penetrations and Joints | Mark Gould | special |
| 07/23/2021 | Lighting in dwelling units | Mark Gould | energy_progress |
| 07/23/2021 | Fire-Resistant Penetrations and Joints | Mark Gould | special |
| 07/23/2021 | Fire-Resistant Penetrations and Joints | Mark Gould | special |
| 07/23/2021 | Energy Code Compliance Inspections | Mark Gould | progress |
| 07/23/2021 | Final | Mark Gould | progress |
| 07/23/2021 | Fire-Resistance Rated Construction | Mark Gould | progress |
| 07/23/2021 | Interior lighting power | Mark Gould | energy_progress |
| 11/05/2020 | HVAC insulation and sealing | Mark Gould | energy_progress |
| 11/05/2020 | Final | Mark Gould | progress |
| 11/05/2020 | Fire-Resistant Penetrations and Joints | Mark Gould | special |
| 11/05/2020 | Mechanical Systems | Mark Gould | special |
| 11/26/2019 | HVAC insulation and sealing | Mark Gould | energy_progress |
| 11/26/2019 | Final | Mark Gould | progress |
| 11/26/2019 | Mechanical Systems | Mark Gould | special |