1931Year Built
5Stories
O2Building Class
C4-4Zoning
33,208 sfGross Floor Area
3Units
LL97 Covered2 Open Violations ▸
Office only, 2-6 stories · Owner of record: BOOMCOMMUNITY SERVICES, INC. · 6,005 sf lot · 5.53 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalCivil
Permit Issued — active, not yet Signed-off
RoofUnder Construction22p · 5 filings · 20 docs
Floor 5Under Construction18p · 1 filing · 8 docs
Floor 4Under Construction18p · 1 filing · 8 docs
Floor 3Under Construction18p · 1 filing · 8 docs
Floor 2
Floor 1
CellarUnder Construction20p · 2 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
3991 SAXON AVE409/13/2026
ARGUS COMMUNITY707/08/2026
BOOM COMMUNITY SERVICES1403/22/2026
T-MOBILE303/22/2026
BROOK HOUSE REALTY4203/22/2026
OWNER OF PREMISES103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/16/2016$5.0M—— → —$149/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
XPDITE GROUP LLC207/07/2026
PRAMODRAY SHAH, P.E.106/25/2026
ELEVATED ENGINEERING, PLLC102/12/2026
A SAXON DESIGN GROUP112/15/2022
DEWBERRY ENGINEERS INC107/29/2020
BRAD E. COHEN, PE107/14/2020
E2 PROJECT MANAGEMENT LLC101/28/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CONSTRUCTION PERMIT SERVICES303/21/2026
CCM CONSULTING GROUP, INC.103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GOTHAM COMMUNICATIONS LLCGeneral Contractor303/21/2026
LEONE CONSTRUCTION, INCGeneral Contractor203/21/2026
ODYSSIA GLOBAL COMM. CORPGeneral Contractor203/21/2026
WALTER MARINElectrical103/21/2026
AMP COMMUNICATIONS LLCGeneral Contractor104/09/2026
MJH CONSTRUCTION CORPGeneral Contractor107/02/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616206/25/2026
ELEVATED ENGINEERING PLLC3692102/12/2026
R MARSAC CONSULTING LLC329312/15/2022
Building Lifecycle
All (108)Filed (8)Permit Issued (6)Signed Off (4)Violation (58)Objection (14)Special Inspection (18)
07/07/2026
Filed — Alteration
APPLICATION FILED HEREWITH FOR THE INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE
X01427578-I1
06/30/2026
Permit issued — General Construction
X01406972-S2-GC
06/30/2026
Special inspection requirement — Metering
06/25/2026
Filed — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AND EXISTING FIVE STORY COMMUNIFY FACILITY BUILDING INTO A EIGHTY-EIGHT FAMILY RESIDENTIAL BUILDING
X01406972-S2
06/25/2026
Objection resolved — Open
06/25/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
06/10/2026
Objection raised — Other
06/05/2026
Objection resolved — Addressed
05/29/2026
Objection raised — Other
05/27/2026
Objection raised — Other
05/27/2026
Objection resolved — Addressed
05/25/2026
Filed — Alteration CO
APPLICATION FILED HEREWITH TO CONVERT AND EXISTING FIVE STORY COMMUNIFY FACILITY BUILDING INTO A EIGHTY-EIGHT FAMILY RESIDENTIAL BUILDING
X01406972-I1
05/25/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Exterior lighting power
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Lighting in dwelling units
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Lighting controls
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Electrical motors and elevators
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Protection of exposed foundation insulation
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
05/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
04/13/2026
Signed off — Alteration
X01357757-I1
03/23/2026
Permit issued — Mechanical Systems
X01357757-I1-MS
02/12/2026
Filed — Alteration
X01357757-I1
08/02/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/01/2023
Signed off — Alteration
X08049921-I1
04/07/2023
Permit issued — Antenna
X08049921-I1-AN
12/15/2022
Filed — Alteration
X08049921-I1
06/02/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/29/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/12/2021
Signed off — Alteration
Modification to existing AT&T site. Replace 6 antennas and install 3 new RRH units on roof. Retrofit 1 existing equipment cabinet in existing equipment room. All in conformance with TPPN 5/98. No change in use, egress, or occupancy.
X00347665-I1
03/03/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/03/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/19/2020
Permit issued — Antenna
X00347665-I1-AN
08/03/2020
Objection raised — Other
08/03/2020
Objection resolved — Addressed
08/03/2020
Objection raised — 1998-AN AC 28-103.14.1-Adminis
08/03/2020
Objection resolved — Addressed
08/03/2020
Objection raised — 1998-AN BC 501.3-Building Code
08/03/2020
Objection resolved — Addressed
08/03/2020
Objection raised — 2014-AN AC 28-104.7.1-Administ
08/03/2020
Objection resolved — Addressed
07/29/2020
Filed — Alteration
Modification to existing AT&T site. Replace 6 antennas and install 3 new RRH units on roof. Retrofit 1 existing equipment cabinet in existing equipment room. All in conformance with TPPN 5/98. No change in use, egress, or occupancy.
X00347665-I1
07/16/2020
Permit issued — Boiler Equipment
X00340764-I1-BE
07/14/2020
Filed — Alteration
X00340764-I1
10/19/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/21/2019
Signed off — Alteration
X00069486-I1
02/12/2019
Permit issued — Antenna
X00069486-I1-AN
02/12/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/12/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
01/28/2019
Filed — Alteration
X00069486-I1
07/18/2018
Violation issued (ECB, closed)
Construction
Latest 60 of 108 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP06/30/2026
DOB NOWMechanical SystemsSigned-offAMP COMMUNICATIONS LLC03/23/2026
DOB NOWAntennaSigned-offGOTHAM COMMUNICATIONS LLC04/07/2023
DOB NOWAntennaSigned-offODYSSIA GLOBAL COMM. CORP11/19/2020
DOB NOWBoiler EquipmentPermit IssuedEAST COAST PETROLEUM INC07/16/2020
DOB NOWAntennaSigned-offHI-TECH C.O.M. CO02/12/2019
BISOTISSUEDV B CONSTRUCTION LLC12/02/2019
BISOTISSUEDBOOM!HEALTH07/13/2018
BISOTISSUEDBOOM!HEALTH06/01/2018
BIS—ISSUEDCOYLE CONTRACTING CORP09/13/2017
BISOTISSUEDDYNAMIC CONSTRUCTION SERV08/09/2017
BISPLISSUEDADVANCED PLUMBING MECH04/27/2017
BISSPISSUEDADVANCED PLBG, MECH & SPR04/18/2017
BISPLISSUEDREEM PLBG & HTG CORP04/18/2017
BISMHISSUEDCOYLE CONTRACTING CORP03/16/2017
BIS—ISSUEDCOYLE CONTRACTING CORP02/17/2017
BISSPISSUEDADVANCED PLBG, MECH & SPR04/06/2016
BISPLISSUEDADVANCED PLUMBING MECH04/06/2016
BISMHISSUEDVANGUARD CONSTRUCTION AND12/08/2015
BISOTISSUEDVANGUARD CONSTRUCTION AND12/04/2015
BISSPISSUEDCAPITOL FIRE SPKL CO,INC08/28/2015
BISPLISSUEDWILLIAM C. GERAKARIS P&H08/24/2015
BISOTISSUEDVANGUARD CONSTRUCTION AND08/17/2015
BISMHISSUEDVANGUARD CONSTRUCTION AND08/17/2015
BISEQISSUEDBILLY ENTERPRISES INC02/25/2015
BISSPISSUEDADVANCED PLBG, MECH & SPR02/17/2015
BISPLISSUEDCOURTESY PLUMBING INC11/18/2014
BISOTISSUEDGALCON ENTERPRISES INC11/07/2014
BISOTISSUEDGALCON ENTERPRISES INC08/29/2014
BISOTISSUEDGALCON ENTERPRISES INC08/21/2014
BISOTISSUEDBECHTEL INFRASTRUCTURE AN02/18/2014
BISMHISSUEDTECHNICAL SOLUTIONS LLC11/20/2013
BISOTISSUEDVERTICAL SOLUTIONS INC03/29/2011
BISOTISSUEDTEG PARTNERS LLC01/12/2010
BISOTISSUEDODYSSIA GLOBAL COMM. CORP07/13/2001
BISOTISSUEDTRIPLE G CONSTRUCTION CORP01/22/2001
BISOTISSUEDBROOK HOUSE FURNITURE CORP.02/11/1997
BISBLISSUEDBROOK FUEL OIL CORP02/28/1994
BISSPISSUEDCAPITOL FIRE SPRINKLER06/04/1991
2 projects · most recent 10/24/2018
General Wiring
FiledStatusContractorScope
10/24/2018CompleteAMP ELECTRICGeneral Wiring
10/24/2018CompleteAMP ELECTRIC—
1 project · most recent 07/07/2026
FiledStatusContractorScope
07/07/2026——1 scope_items
1 project · most recent 07/07/2026
Fence
FiledStatusContractorScope
07/07/2026——Fence
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
06/30/2026Metering—energy_progress
06/25/2026Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
05/25/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
05/25/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
05/25/2026Exterior lighting powerSHAHRIAR QUAYYUMenergy_progress
05/25/2026Fenestration areasSHAHRIAR QUAYYUMenergy_progress
05/25/2026Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
05/25/2026Fenestration and door U-factor and product ratingsSHAHRIAR QUAYYUMenergy_progress
05/25/2026Exterior Insulation and Finish Systems (EIFS)SHAHRIAR QUAYYUMspecial
05/25/2026Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
05/25/2026Lighting in dwelling unitsSHAHRIAR QUAYYUMenergy_progress
05/25/2026Lighting controlsSHAHRIAR QUAYYUMenergy_progress
05/25/2026Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
05/25/2026Maintenance informationSHAHRIAR QUAYYUMenergy_progress
05/25/2026Electrical motors and elevatorsSHAHRIAR QUAYYUMenergy_progress
05/25/2026Protection of exposed foundation insulationSHAHRIAR QUAYYUMenergy_progress
05/25/2026Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
05/25/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
▾Documents — 487 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch6
08/26/2026X00069486-I1Request digital key ↗
08/23/2026X08049921-I1Request digital key ↗
08/17/2026X01357757-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Antenna1
08/15/2026X00347665-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Boiler Equipment1
08/26/2026X00340764-I1Request digital key ↗
▸Applications & Permits92
▸BISPLAN / WORK APPROVAL APPLICATION54
12/30/2019220720762Open ↗
12/27/2019220720762Open ↗
11/25/2019220720762Open ↗
Showing 3 of 54 on file for this type
▸BISWORK PERMIT APPLICATION33
12/03/2019220720762Open ↗
07/16/2018220658811Open ↗
06/04/2018220645657Open ↗
Showing 3 of 33 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPLACE OF ASSEMBLY2
07/20/2017220558830Open ↗
Showing 1 of 2 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
08/22/2017220558830Open ↗
▸Seals & Professional Certifications95
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION61
11/25/2019220720762Open ↗
03/05/2019220658811Open ↗
02/25/2019220645657Open ↗
Showing 3 of 61 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT12
11/25/2019220720762Open ↗
07/16/2018220658811Open ↗
04/26/2018220645657Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST11
11/25/2019220720762Open ↗
07/16/2018220658811Open ↗
04/26/2018220645657Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/26/2026X00069486-I1Open ↗
08/26/2026X00340764-I1Open ↗
08/26/2026X00347665-I1Open ↗
Showing 3 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
09/19/2026X01406972-S2Open ↗
▸Trade Schedules & Equipment25
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE8
08/18/2017220524519Open ↗
Showing 1 of 8 on file for this type
▸BISEQUIPMENT USE PERMITS7
11/14/2018220333823Open ↗
Showing 1 of 7 on file for this type
▸BISSELF-CERT PLUMBING NOTICE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT3
11/14/2018220333823Open ↗
Showing 1 of 3 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
08/01/2018220468170Open ↗
08/11/2017220468358Open ↗
▸BISSCHEDULE B - PLUMBING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
08/22/2017220558830Open ↗
▸Safety & Tenant Protection10
▸BISTenant Protection Plan and Notes4
11/25/2019220720762Open ↗
07/25/2018220645657Open ↗
07/25/2018220658811Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM3
11/25/2019220720762Open ↗
Showing 1 of 3 on file for this type
▸DOB NOWStreet Tree Checklist2
08/16/2026X01406972-S2Open ↗
08/15/2026X01406972-I1Open ↗
▸BISSTREET TREE CHECKLIST1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos16
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
07/05/2018220468358Open ↗
06/04/2018220645657Open ↗
Showing 2 of 8 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/26/2026X00069486-I1Open ↗
08/26/2026X00340764-I1Open ↗
08/17/2026X01357757-I1Open ↗
Showing 3 of 5 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance31
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS23
11/25/2019220720762Open ↗
03/05/2019220658811Open ↗
02/25/2019220645657Open ↗
Showing 3 of 23 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
11/25/2019220720762Open ↗
03/05/2019220658811Open ↗
02/25/2019220645657Open ↗
Showing 3 of 7 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports4
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
07/23/2019220526955Open ↗
▸BISHYDRO FLOW TEST LETTER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs87
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST46
09/12/2019220526955Open ↗
07/23/2019220526955Open ↗
04/26/2019220526955Open ↗
Showing 3 of 46 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION33
11/25/2019220720762Open ↗
11/25/2019220720762Open ↗
11/25/2019220720762Open ↗
Showing 3 of 33 on file for this type
▸BISSUPERSEDING LETTER3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
03/06/2019220526955Open ↗
01/14/2019220526955Open ↗
Showing 2 of 3 on file for this type
▸BISFA LETTER OF DEFECT : FD-FALD1
02/12/2018220526955Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership38
▸BISCOST AFFIDAVIT35
11/25/2019220720762Open ↗
11/25/2019220720762Open ↗
03/05/2019220658811Open ↗
Showing 3 of 35 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE3
12/03/2019220720762Open ↗
Showing 1 of 3 on file for this type
▸Filing & Intake Forms76
▸BISADDITIONAL INFORMATION30
12/30/2019220720762Open ↗
12/27/2019220720762Open ↗
11/25/2019220720762Open ↗
Showing 3 of 30 on file for this type
▸BISBOROUGH INTAKE FORM29
09/12/2019220526955Open ↗
07/23/2019220526955Open ↗
03/22/2019220654771Open ↗
Showing 3 of 29 on file for this type
▸BISEFILING COVER SHEET16
11/25/2019220720762Open ↗
07/16/2018220658811Open ↗
04/26/2018220645657Open ↗
Showing 3 of 16 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Other Documents5
▸BISFA SELF CERT DEFECT : FD-FASC2
11/08/2017220526955Open ↗
11/06/2017220468170Open ↗
▸BISPLOT DIAGRAM2
09/12/2019220526955Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWProperty Ownership Certification1
08/15/2026X01406972-I1Open ↗