| Owner | Filings | Most Recent |
|---|---|---|
| 711 E | 30 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/20/2025 | $1.1M | — | Private party → 317 E LLC | $343/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NIKOLAI KATZ ARCHITECT | 6 | 05/13/2026 |
| VASILIOS ARTEMIOU PE | 5 | 01/28/2026 |
| AG ENGINEERING PLLC | 1 | 11/25/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 20 | 03/21/2026 |
| ZV Drafting | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 4 | 04/09/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 07/08/2026 |
| B&B MECH PLBG & HTG LLC | Plumbing | 1 | 07/08/2026 |
| EMPIRE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 10 | 05/13/2026 |
| SHAHRISH SHUVO ENGINEERIN | 8524 | 1 | 12/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | MJH CONSTRUCTION CORP | 01/26/2026 |
| DOB NOW | Plumbing | Signed-off | EMPIRE PLUMBING INC | 12/30/2025 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 12/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 12/20/2025 |
| DOB NOW | Plumbing | Signed-off | TARGET PIPING NY LLC | 12/19/2025 |
| DOB NOW | Sprinklers | Signed-off | TARGET PIPING NY LLC | 12/19/2025 |
| DOB NOW | Construction Fence | Signed-off | MJH CONSTRUCTION CORP | 11/26/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Signed-off | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Signed-off | PIPING & PLUMBING SOLUTIO | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/19/2026 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Signed-off | MJH CONSTRUCTION CORP | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/24/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/13/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/07/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 03/09/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/06/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/20/2026 | Pass-Final SP - Up to 9 Requested Floors | Pass | View ↗ |
| 02/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/12/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/08/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/26/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/12/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 05/12/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Permanent certificate | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 05/12/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 05/12/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 05/12/2026 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 03/10/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 03/10/2026 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 03/10/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 03/10/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 03/10/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Permanent certificate | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 03/10/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |