| Owner | Filings | Most Recent |
|---|---|---|
| 69-70 Associates | 27 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KMB Design Group | 2 | 12/22/2023 |
| Pace Engineering | 1 | 04/14/2022 |
| Ashraf | 1 | 02/17/2022 |
| Baileys Engineering | 1 | 12/11/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| Construction Permit Services | 2 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Danico Services | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J.N.H. Construction | Scaffold | 2 | 07/08/2026 |
| Vema Group | Scaffold | 2 | 07/08/2026 |
| C.T.C. Electrical Contractors | Electrical | 1 | 03/22/2026 |
| J.N.H. Construction | General Contractor | 1 | 04/09/2026 |
| North Jersey Atms | General Contractor | 1 | 07/08/2026 |
| Hudson Plumbing & MCH | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KMB Design Group | 513 | 2 | 12/22/2023 |
| Pace Engineering | 1679 | 1 | 04/14/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | North Jersey Atms | 05/22/2026 |
| DOB NOW | Plumbing | Permit Issued | Hudson Plumbing & MCH | 05/15/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | J.N.H. Construction | 08/09/2023 |
| DOB NOW | General Construction | Signed-off | J.N.H. Construction | 04/28/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | J.N.H. Construction | 02/18/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Vema Group | 04/22/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Vema Group | 12/11/2018 |
| BIS | OT | ISSUED | Telcom Engineering GP | 02/03/2015 |
| BIS | OT | ISSUED | Best Energy Power | 08/31/2012 |
| BIS | FS | ISSUED | G. Bauer | 07/30/2012 |
| BIS | OT | ISSUED | Dun Rite Commercial | 11/29/2006 |
| BIS | FB | ISSUED | G Bauer | 08/15/2005 |
| BIS | PL | ISSUED | L&J PLG & Heating Co of NY | 03/07/2001 |
| BIS | MH | ISSUED | Tech-Nel Electric | 02/15/2001 |
| BIS | OT | ISSUED | Tech-Nel Electric | 02/15/2001 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/22/2023 | Permit Issued | North Jersey Atms | Generators | Generators Kohler KG50 50 kW · Generator ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Complete | Net Power Electric | General Wiring |
| 03/07/2022 | Complete | Fibertek Data & Electric | General Wiring |
| 01/25/2022 | Complete | Green Source Electrical | — |
| 01/05/2021 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 12/31/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 11/16/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 08/25/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 07/28/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 07/22/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 02/19/2020 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 10/02/2019 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 06/21/2019 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 02/27/2019 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| 12/11/2018 | Permit Issued | Borowide Elect'l Contractors | — |
| 02/01/2018 | Permit Issued | C.T.C. Electrical Contractors | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/22/2023 | Tenant Protection Plan Compliance | Ekata Shah | special |
| 07/06/2022 | Final | Ekata Shah | progress |
| 07/06/2022 | Mechanical Systems | Ekata Shah | special |
| 04/13/2022 | Energy Code Compliance Inspections | Baris Acar | progress |
| 03/07/2022 | Structural Stability – Alterations of existing buildings | Baris Acar | special |
| 03/07/2022 | Masonry | Baris Acar | special |
| 03/07/2022 | Final | Baris Acar | progress |
| 11/29/2018 | Final | PAUL BAILEY | progress |