| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/04/2025 | Permit Issued | WATSON'S PLBG, HTG, & BDG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2025 | Complete | EVERBRIGHT ELECTRIC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| SAL BUILDERS | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/20/2023 | $645K | — | Private party → Private party | $597/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS, P.C. | 4 | 09/04/2025 |
| NA | 2 | 08/06/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| LIQUID DESIGN STUDIO & ASSOCIATES | 8 | 03/21/2026 |
| BUILD TEAM | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EVERBRIGHT ELECTRIC INC | Electrical | 2 | 03/22/2026 |
| SAL BUILDERS INC | General Contractor | 2 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 2 | 07/08/2026 |
| LIONHEART CONSTRUCTION CO | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HSU & ASSOCIATES | 8025 | 6 | 09/04/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | WATSON'S PLBG, HTG, & BDG | 06/06/2025 |
| DOB NOW | General Construction | Signed-off | LIONHEART CONSTRUCTION CO | 05/16/2025 |
| DOB NOW | General Construction | Signed-off | SAL BUILDERS INC | 06/14/2024 |
| DOB NOW | Plumbing | Permit Issued | WATSON'S PLBG, HTG, & BDG | 05/21/2024 |
| DOB NOW | General Construction | Signed-off | SAL BUILDERS INC | 05/06/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/19/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/16/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/13/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/05/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/06/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/07/2025 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 10/07/2025 | Energy Code Compliance Inspections | Chih Hsu | progress |
| 09/02/2025 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 09/02/2025 | Energy Code Compliance Inspections | Chih Hsu | progress |
| 05/08/2025 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 05/08/2025 | Concrete - Cast-In-Place | Chih Hsu | special |
| 05/08/2025 | Fire-Resistance Rated Construction | Chih Hsu | progress |
| 05/08/2025 | Energy Code Compliance Inspections | Chih Hsu | progress |
| 05/22/2024 | Fire-Resistant Penetrations and Joints | Chih Hsu | special |
| 05/22/2024 | Energy Code Compliance Inspections | Chih Hsu | progress |