← Back
Two stories - detached, small or mid-size
32 MAGUIRE AVENUE
STATEN ISLAND · BIN 5085488
💬 Discuss this project
1910Year Built
2Stories
A1Building Class
R3XZoning
1,610 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 6,960 sf lot · 0.23 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ETRECTE LLC205/08/2024
SANARK CONSULTING ENGINEERING D.P.C412/08/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SANARK CONSULTING ENGINEERING D P C803/21/2026
J B I CONSTRUCTION GROUP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J.B.I. CONSTRUCTION GROUPGeneral Contractor303/21/2026
SANTI LEMBO PLBG & HTGPlumbing207/08/2026
REGENCY HEATING & AIR CONGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ETRECTE LLC8116205/08/2024
Building Lifecycle
All (35)Filed (6)Permit Issued (5)Signed Off (5)Violation (4)Inspection (7)Special Inspection (8)
05/09/2024
Signed off — Alteration
INSTALLATION OF PV SYSTEM ON EXISTING ROOF TOP. NO CHANGES TO THE USE EGRESS OR OCCUPANCY.
S01015903-I1
05/08/2024
Filed — Alteration
INSTALLATION OF PV SYSTEM ON EXISTING ROOF TOP. NO CHANGES TO THE USE EGRESS OR OCCUPANCY.
S01015903-P1
05/08/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
VYACHESLAV NECHAYEV
05/08/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
VYACHESLAV NECHAYEV
05/08/2024
Special inspection requirement — Energy Code Compliance Inspections
VYACHESLAV NECHAYEV
05/08/2024
Special inspection requirement — Final
VYACHESLAV NECHAYEV
05/08/2024
Special inspection requirement — Air barrier - visual inspection
VYACHESLAV NECHAYEV
03/18/2024
Permit issued — Solar
S01015903-I1-SL
03/11/2024
Filed — Alteration
INSTALLATION OF PV SYSTEM ON EXISTING ROOF TOP. NO CHANGES TO THE USE EGRESS OR OCCUPANCY.
S01015903-I1
04/25/2022
Signed off — Alteration
Subsequent job to address plumbing objections.
S00544194-S3
04/19/2022
Signed off — Alteration
Subsequent job to address plumbing objections.
S00544194-S1
04/18/2022
Signed off — Alteration
Subsequent job to address plumbing objections.
S00544194-I1
04/18/2022
Signed off — Alteration
Subsequent job to address plumbing objections.
S00544194-S2
04/15/2022
Permit issued — General Construction
S00544194-S2-GC
01/31/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/25/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/14/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/09/2021
Permit issued — Plumbing
S00544194-S3-PL
12/08/2021
Filed — Alteration
Subsequent job to address plumbing objections.
S00544194-S3
12/08/2021
Special inspection requirement — Energy Code Compliance Inspections
REJEP KOLAR
12/07/2021
Filed — Alteration
Subsequent job to address plumbing objections.
S00544194-S2
12/07/2021
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
12/07/2021
Special inspection requirement — Final
REJEP KOLAR
09/20/2021
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/10/2021
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
08/31/2021
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/04/2021
Permit issued — Plumbing
S00544194-S1-PL
07/29/2021
Permit issued — General Construction
S00544194-I1-GC
07/14/2021
Filed — Alteration
Subsequent job to address plumbing objections.
S00544194-S1
07/13/2021
Special inspection requirement — Energy Code Compliance Inspections
REJEP KOLAR
07/09/2021
Filed — Alteration
Subsequent job to address plumbing objections.
S00544194-I1
12/07/2020
Violation issued (ECB, closed)
Construction
09/02/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/20/2020
Violation issued (ECB, closed)
Construction
01/21/2020
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offJ.B.I. CONSTRUCTION GROUP03/18/2024
DOB NOWGeneral ConstructionSigned-offREGENCY HEATING & AIR CON04/15/2022
DOB NOWPlumbingSigned-offSANTI LEMBO PLBG & HTG12/09/2021
DOB NOWPlumbingSigned-offSANTI LEMBO PLBG & HTG08/04/2021
DOB NOWGeneral ConstructionSigned-offPR07/29/2021
1 project · most recent 02/26/2024
FiledStatusContractorScope
02/26/2024CompleteJSP ELECTL CNTNG CORP—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
01/31/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/25/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/14/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/07/2021Pass-Final General Construction Non-Directive 14PassView ↗
09/20/2021Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/10/2021Pass-Final General Construction Non-Directive 14PassView ↗
08/31/2021Fail-Final General Construction Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
05/08/2024Fire-Resistant Penetrations and JointsVYACHESLAV NECHAYEVspecial
05/08/2024Structural Stability – Alterations of existing buildingsVYACHESLAV NECHAYEVspecial
05/08/2024Energy Code Compliance InspectionsVYACHESLAV NECHAYEVprogress
05/08/2024FinalVYACHESLAV NECHAYEVprogress
05/08/2024Air barrier - visual inspectionVYACHESLAV NECHAYEVenergy_progress
12/08/2021Energy Code Compliance InspectionsREJEP KOLARprogress
12/07/2021FinalREJEP KOLARprogress
07/13/2021Energy Code Compliance InspectionsREJEP KOLARprogress
▾Documents — 21 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/25/2026S00544194-S3Request digital key ↗
08/25/2026S00544194-S2Request digital key ↗
08/25/2026S00544194-S1Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/25/2026S00544194-I1Open ↗
08/25/2026S00544194-S3Open ↗
08/25/2026S00544194-S2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
08/29/2026S00544194-S2Open ↗
08/28/2026S00544194-S3Open ↗
08/25/2026S00544194-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026S01015903-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/21/2026S01015903-I1Open ↗
08/13/2026S01015903-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01015903-I1Open ↗