← Back
One family attached or semi-detached
32 SLATER BOULEVARD
STATEN ISLAND · New Dorp-Midland Beach · BIN 5053049
💬 Discuss this project
1975Year Built
2Stories
A5Building Class
R3-1Zoning
1,056 sfGross Floor Area
1Units
One family attached or semi-detached · 2,240 sf lot · 0.47 FAR built · Flood zone AE
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR107/01/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281107/01/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
11/21/2025
Signed off — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP,RAILED, GRID-TIED, 10 MODULES, 4.3KW
S01247160-I1
07/03/2025
Permit issued — Solar
S01247160-I1-SL
07/01/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP,RAILED, GRID-TIED, 10 MODULES, 4.3KW
S01247160-I1
06/25/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
06/25/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
06/25/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
06/25/2025
Special inspection requirement — Final
Mina Makar
06/25/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR07/03/2025
BISOTISSUEDMARK D. LIPTON ASSOCIATES01/20/1994
1 project · most recent 07/24/2025
FiledStatusContractorScope
07/24/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/25/2025Fire-Resistant Penetrations and JointsMina Makarspecial
06/25/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
06/25/2025Energy Code Compliance InspectionsMina Makarprogress
06/25/2025FinalMina Makarprogress
06/25/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026S01247160-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026S01247160-I1Open ↗
08/26/2026S01247160-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01247160-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026S01247160-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01247160-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01247160-I1Open ↗