| Owner | Filings | Most Recent |
|---|---|---|
| 320 WEST 77 LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/07/2022 | $5.0M | — | — → — | $931/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| A&D ENGINEERING, PLLC | 10 | 08/10/2026 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 5 | 10/01/2025 |
| ISSAC AND STERN ARCHITECTS, PC | 5 | 09/23/2025 |
| RIGID STRUCTURAL DESIGN, LLC | 2 | 07/10/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 36 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TOMCHRIS CONTRACTING CORP | General Contractor | 12 | 07/15/2026 |
| HIGH QUALITY RENOVATION I | General Contractor | 9 | 07/08/2026 |
| INTERSYSTEMS INSTAL S&S | General Contractor | 6 | 06/28/2026 |
| ASPECT PLBNG&HTNG CO LLC | Plumbing | 3 | 06/28/2026 |
| ALLSTATE SPRINKLER LLC | Fire Protection | 2 | 07/08/2026 |
| PROCORE MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| TROADIO MENENDEZ | Electrical | 1 | 03/21/2026 |
| OUTFRONT MEDIA LLC | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MILROSE CONSULTANTS LLC | 2003 | 17 | 08/10/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 07/14/2026 |
| DOB NOW | Plumbing | Permit Issued | ASPECT PLBNG&HTNG CO LLC | 06/22/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | HIGH QUALITY RENOVATION I | 03/09/2026 |
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 11/26/2025 |
| DOB NOW | Structural | Permit Issued | TOMCHRIS CONTRACTING CORP | 11/26/2025 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 09/29/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HIGH QUALITY RENOVATION I | 08/21/2025 |
| DOB NOW | Structural | Permit Issued | TOMCHRIS CONTRACTING CORP | 08/15/2025 |
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 08/15/2025 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 07/11/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEMS INSTAL S&S | 07/11/2025 |
| DOB NOW | Plumbing | Permit Issued | ASPECT PLBNG&HTNG CO LLC | 03/19/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HIGH QUALITY RENOVATION I | 01/23/2025 |
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 01/13/2025 |
| DOB NOW | Foundation | Permit Issued | TOMCHRIS CONTRACTING CORP | 11/22/2024 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 10/25/2024 |
| DOB NOW | Structural | Permit Issued | TOMCHRIS CONTRACTING CORP | 10/15/2024 |
| DOB NOW | General Construction | Permit Issued | TOMCHRIS CONTRACTING CORP | 10/09/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | HIGH QUALITY RENOVATION I | 08/29/2024 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEMS INSTAL S&S | 07/10/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | INTERSYSTEMS INSTAL S&S | 07/10/2024 |
| DOB NOW | Boiler Equipment | Signed-off | NEW YORK HEATING CORP | 06/11/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | HIGH QUALITY RENOVATION I | 05/31/2024 |
| DOB NOW | General Construction | Permit Issued | HIGH QUALITY RENOVATION I | 03/26/2024 |
| DOB NOW | Plumbing | Permit Issued | ASPECT PLBNG&HTNG CO LLC | 01/30/2024 |
| DOB NOW | Plumbing | Permit Issued | PROCORE MECHANICAL CORP | 09/07/2023 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY RENOVATION I | 08/07/2023 |
| BIS | BL | ISSUED | COMBIND OIL CORP. | 03/05/2009 |
| BIS | BL | ISSUED | GEORGE BOMZER & SON INC. | 11/07/1991 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/10/2026 | Permit Issued | TOMCHRIS CONTRACTING CORP | Heating and Air Conditioning Systems, Heating Systems | Heat / Cool Daikin FXMQ48PBVJU 54,000 BTU · Vrf Indoor ×6 FXMQ36PBVJU 40,000 BTU · Vrf Indoor ×3 MXZ-SM48NAM2 50,000 BTU · Heat Pump Outdoor ×1 RXTQ36TAVJ9 40,000 BTU · Vrf Outdoor ×8 RTXQ48TAVJU 52,000 BTU · Vrf Outdoor ×4 PK12NMVJU 10,900 BTU · Vrf Indoor ×2 Mitsubishi Electric MXZ-SM36NAM2 41,000 BTU · Condensing Unit ×4 MUZ-GL12NA 12,000 BTU · Heat Pump Outdoor ×1 MXZ-SM48NAM2 48,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Signed-off | ALLSTATE SPRINKLER LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | ASPECT PLBNG&HTNG CO LLC | Gas, Storm, Water/Sanitary |
| 08/23/2023 | Permit Issued | PROCORE MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2025 | Permit Issued | AURORA ELECL CONTG INC | — |
| 12/12/2024 | Permit Issued | GLENDALE ELECTL CONTNG IN | General Wiring |
| 08/09/2023 | Complete | GLENDALE ELECTL CONTNG IN | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2026 | Permit Issued | TOMCHRIS CONTRACTING CORP | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Signed-off | INTERSYSTEMS INSTAL S&S | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/17/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/16/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/26/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/14/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/05/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/30/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/20/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/20/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 09/20/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/03/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/23/2026 | Maintenance information | Christopher Drutjons | energy_progress |
| 07/23/2026 | HVAC-R and service water heating equipment | Christopher Drutjons | energy_progress |
| 07/23/2026 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 07/23/2026 | Heating Systems | Christopher Drutjons | special |
| 07/23/2026 | Mechanical Systems | Christopher Drutjons | special |
| 07/23/2026 | Structural Stability – Alterations of existing buildings | Christopher Drutjons | special |
| 07/23/2026 | Energy Code Compliance Inspections | Christopher Drutjons | progress |
| 07/23/2026 | Final | Christopher Drutjons | progress |
| 07/23/2026 | Fire-Resistance Rated Construction | Christopher Drutjons | progress |
| 07/23/2026 | Shutoff dampers | Christopher Drutjons | energy_progress |
| 07/23/2026 | HVAC-R and service water heating system controls | Christopher Drutjons | energy_progress |
| 07/23/2026 | HVAC-R and service water piping design and insulation | Christopher Drutjons | energy_progress |
| 10/15/2025 | Maintenance information | Christopher Drutjons | energy_progress |
| 10/15/2025 | HVAC-R and service water heating system controls | Christopher Drutjons | energy_progress |
| 10/15/2025 | Fire-Resistant Penetrations and Joints | Christopher Drutjons | special |
| 10/15/2025 | Energy Code Compliance Inspections | Christopher Drutjons | progress |
| 10/15/2025 | HVAC-R and service water heating equipment | Christopher Drutjons | energy_progress |
| 10/15/2025 | HVAC-R and service water piping design and insulation | Christopher Drutjons | energy_progress |
| 10/06/2025 | Final | Christopher Drutjons | progress |
| 10/06/2025 | Maintenance information | Christopher Drutjons | energy_progress |
| 10/06/2025 | Shutoff dampers | Christopher Drutjons | energy_progress |
| 10/06/2025 | HVAC-R and service water heating equipment | Christopher Drutjons | energy_progress |
| 10/06/2025 | HVAC-R and service water heating system controls | Christopher Drutjons | energy_progress |
| 10/06/2025 | HVAC-R and service water piping design and insulation | Christopher Drutjons | energy_progress |
| 10/06/2025 | Energy Code Compliance Inspections | Christopher Drutjons | progress |