| Owner | Filings | Most Recent |
|---|---|---|
| BRONSTEIN PROPERTIES | 29 | 07/08/2026 |
| PRATT CONSTRUCTION | 12 | 07/08/2026 |
| HALSTEAD MANAGEMENT | 11 | 07/08/2026 |
| PENMARK REALTY | 8 | 03/21/2026 |
| CONTINENTAL CONDOMINIUM | 7 | 03/21/2026 |
| 321 EAST 48 ST MANHATTAN 10017 | 4 | 03/21/2026 |
| DISH WIRELESS | 3 | 03/22/2026 |
| CONTINENTAL CONDOMINIUM CO PENM | 2 | 03/21/2026 |
| HALSTEAD PROPERTY MGMT. | 1 | 03/22/2026 |
| BAYSIDE CONTRACTING, INC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MAN ARCHITECTURE PC | 3 | 06/01/2026 |
| NEW YORK ENGINEERING ASSOC., P.C. | 4 | 12/18/2025 |
| WEI STUDIO | 3 | 12/05/2025 |
| DINA VEDMED ARCHITECT | 6 | 10/17/2025 |
| CHEUNG SHOWMAN ARCHITECTS | 1 | 12/30/2024 |
| GAVIRIA ENGINEERING | 1 | 04/28/2023 |
| ASHRAF CORP | 5 | 08/20/2021 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 07/27/2021 |
| JOEL PHAGOO P.E. PLLC | 1 | 10/02/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| NEW YORK ENGINEERING | 4 | 03/21/2026 |
| DINA VEDMED ARCHITECT | 6 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 1 | 03/21/2026 |
| Rigid Structural Design, LLC | 5 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| INTERSYSTEM INSTALLATION | General Contractor | 16 | 07/08/2026 |
| DYNAMIC INSTALLATION CORP. | General Contractor | 13 | 07/08/2026 |
| PRAT ENTERPRISES CORP | General Contractor | 7 | 07/08/2026 |
| HERCULES HOME IMPROVEMENT | General Contractor | 7 | 07/08/2026 |
| PRATT CONSTRUCTION & REST | General Contractor | 3 | 03/21/2026 |
| ATLANTIC EAST COMM CORP | General Contractor | 3 | 03/21/2026 |
| A & S MASTER ELEC'L CORP | Electrical | 2 | 03/22/2026 |
| CALRAY GAS HEAT CORP | Plumbing | 2 | 07/08/2026 |
| MIKE CATSIMALIS PLBG&HTG | Plumbing | 2 | 07/08/2026 |
| HOWARD WEISS | Electrical | 1 | 03/21/2026 |
| AXCEL ELECTRIC CO., INC. | Electrical | 1 | 03/22/2026 |
| RK DESIGN INC | General Contractor | 1 | 07/08/2026 |
| BYPASS MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| PETER MICELI PLUMBING | Plumbing | 1 | 07/08/2026 |
| STUART MOSKOWITZ | Electrical | 1 | 03/21/2026 |
| MOSKOWITZ STUART | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GROUP PROJECTS ARCHITECTU | 7696 | 3 | 06/01/2026 |
| NEW YORK ENGINEERING ASSO | 851 | 4 | 12/18/2025 |
| WEI STUDIO | 7998 | 3 | 12/05/2025 |
| CHANDA ENG. CONSULTANT PC | 6842 | 4 | 10/17/2025 |
| KMB DESIGN GROUP, LLC | 513 | 1 | 04/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | HERCULES HOME IMPROVEMENT | 02/19/2026 |
| DOB NOW | Plumbing | Signed-off | PETER MICELI PLUMBING | 12/18/2025 |
| DOB NOW | General Construction | Signed-off | HERCULES HOME IMPROVEMENT | 11/25/2025 |
| DOB NOW | Plumbing | Signed-off | MIKE CATSIMALIS PLBG&HTG | 09/16/2025 |
| DOB NOW | General Construction | Signed-off | HERCULES HOME IMPROVEMENT | 09/09/2025 |
| DOB NOW | Plumbing | Signed-off | BYPASS MECHANICAL CORP | 07/10/2025 |
| DOB NOW | General Construction | Permit Issued | HERCULES HOME IMPROVEMENT | 07/02/2025 |
| DOB NOW | Plumbing | Signed-off | CALRAY GAS HEAT CORP | 04/10/2025 |
| DOB NOW | Boiler Equipment | Signed-off | CALRAY GAS HEAT CORP | 03/27/2025 |
| DOB NOW | General Construction | Signed-off | RK DESIGN INC | 01/23/2025 |
| DOB NOW | Plumbing | Signed-off | MIKE CATSIMALIS PLBG&HTG | 09/17/2024 |
| DOB NOW | General Construction | Signed-off | HERCULES HOME IMPROVEMENT | 09/04/2024 |
| DOB NOW | Antenna | Signed-off | ATLANTIC EAST COMM CORP | 05/23/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PRAT ENTERPRISES CORP | 10/26/2022 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEM INSTALLATION | 09/26/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | INTERSYSTEM INSTALLATION | 09/26/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 09/07/2022 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | INTERSYSTEM INSTALLATION | 07/06/2022 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEM INSTALLATION | 07/06/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | PRAT ENTERPRISES CORP | 10/26/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PRAT ENTERPRISES CORP | 08/13/2021 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEM INSTALLATION | 07/30/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | INTERSYSTEM INSTALLATION | 07/30/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 07/28/2021 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | INTERSYSTEM INSTALLATION | 06/25/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | PRATT CONSTRUCTION & RES* | 06/24/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 06/11/2021 |
| DOB NOW | Supported Scaffold | Signed-off | INTERSYSTEM INSTALLATION | 05/27/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 06/11/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 07/23/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 12/27/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | DYNAMIC INSTALLATION CORP | 10/03/2018 |
| BIS | OT | ISSUED | PRAT ENTERPRISES CORP | 10/26/2022 |
| BIS | OT | ISSUED | PRAT ENTERPRISES CORP | 10/22/2021 |
| BIS | OT | ISSUED | PRATT CONSTRUCTION & REST | 06/16/2021 |
| BIS | BL | ISSUED | COPPER SERVICES, LLC | 08/14/2019 |
| BIS | PL | ISSUED | COPPER SERVICES, LLC | 08/14/2019 |
| BIS | OT | ISSUED | OM GENERAL CONTRACTORS CO | 05/23/2019 |
| BIS | OT | ISSUED | A & E GENERAL PAINTING IN | 06/11/2018 |
| BIS | PL | ISSUED | ALL DAY PLUMBING & HEATING | 03/28/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Signed-off | PETER MICELI PLUMBING | Gas, Water/Sanitary |
| 12/18/2025 | Signed-off | SANITARY PLBG & HTG CORP | Gas, Water/Sanitary |
| 10/17/2025 | Signed-off | PLUMBING WORKS CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/24/2026 | Permit Issued | A & S MASTER ELEC'L CORP | General Wiring |
| 09/24/2026 | Permit Issued | A & S MASTER ELEC'L CORP | General Wiring |
| 09/16/2026 | Permit Issued | IKAROS ELECTRICAL ENT INC | General Wiring |
| 07/06/2026 | Permit Issued | IKAROS ELECTRICAL ENT INC | General Wiring |
| 05/13/2026 | Complete | AXCEL ELECTRIC CO., INC. | — |
| 05/13/2026 | Complete | AXCEL ELECTRIC CO., INC. | — |
| 03/11/2026 | Complete | AXCEL ELECTRIC CO., INC. | — |
| 03/11/2026 | Complete | AXCEL ELECTRIC CO., INC. | — |
| 03/04/2026 | Complete | A & S MASTER ELEC'L CORP | General Wiring |
| 03/04/2026 | Complete | A & S MASTER ELEC'L CORP | General Wiring |
| 12/25/2025 | Complete | A & S MASTER ELEC'L CORP | General Wiring |
| 12/10/2025 | Complete | EMPIRE LIC ELECL CONTRS | General Wiring |
| 08/11/2025 | Complete | A & S MASTER ELEC'L CORP | General Wiring |
| 08/04/2025 | Complete | A & S MASTER ELEC'L CORP | General Wiring |
| 03/15/2025 | Complete | AXCEL ELECTRIC CO., INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Signed-off | HERCULES HOME IMPROVEMENT | Tenant Protection Plan 72 Hour |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/05/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/14/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/09/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 12/02/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 11/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/19/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/18/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 08/19/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/11/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/12/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/07/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/02/2026 | Fire-Resistant Penetrations and Joints | Jonathan Man | special |
| 07/02/2026 | Fire-Resistance Rated Construction | Jonathan Man | progress |
| 07/02/2026 | Energy Code Compliance Inspections | Jonathan Man | progress |
| 07/02/2026 | Lighting in dwelling units | Jonathan Man | energy_progress |
| 07/02/2026 | Final | Jonathan Man | progress |
| 07/02/2026 | Tenant Protection Plan Compliance | Jonathan Man | special |
| 12/19/2025 | Tenant Protection Plan Compliance | LOUIS ARENA | special |
| 12/19/2025 | Energy Code Compliance Inspections | LOUIS ARENA | progress |
| 12/19/2025 | Fire-Resistant Penetrations and Joints | LOUIS ARENA | special |
| 12/15/2025 | Energy Code Compliance Inspections | LOUIS ARENA | progress |
| 12/15/2025 | Tenant Protection Plan Compliance | LOUIS ARENA | special |
| 12/15/2025 | Fire-Resistant Penetrations and Joints | LOUIS ARENA | special |
| 12/08/2025 | Fire-Resistant Penetrations and Joints | Ruoyu Wei | special |
| 12/08/2025 | Tenant Protection Plan Compliance | Ruoyu Wei | special |
| 10/20/2025 | Fire-Resistant Penetrations and Joints | KARTIK CHANDA | special |
| 10/20/2025 | Energy Code Compliance Inspections | Dina Vedmed | progress |
| 08/29/2025 | Interior lighting power | Ruoyu Wei | energy_progress |
| 08/29/2025 | Lighting controls | Ruoyu Wei | energy_progress |
| 08/29/2025 | Lighting in dwelling units | Ruoyu Wei | energy_progress |
| 08/27/2025 | Tenant Protection Plan Compliance | Ruoyu Wei | special |
| 08/27/2025 | Energy Code Compliance Inspections | Ruoyu Wei | progress |
| 08/27/2025 | Fire-Resistant Penetrations and Joints | Ruoyu Wei | special |
| 08/24/2025 | Final | Ruoyu Wei | progress |
| 07/09/2025 | Tenant Protection Plan Compliance | Jonathan Man | special |
| 06/10/2025 | Lighting in dwelling units | Dina Vedmed | energy_progress |