| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/03/2025 | Signed-off | ROCK & HAMMER CONSTRUCTIO | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Fujitsu AOU60RLAVM4 60,000 BTU · Heat Pump Outdoor ×1 Ventilation Ac Infinity AI-CLA4 50 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/15/2026 | Permit Issued | DOYLE BROS PLBG & HTG INC | Gas |
| 06/03/2025 | Signed-off | PREMIER FLOW PLBG AND HTG | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/26/2025 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 10/16/2024 | Complete | RIVIERA ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/03/2025 | Signed-off | ROCK & HAMMER CONSTRUCTIO | Steel |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/19/2023 | $1.2M | — | Private party → Private party | $519/sf building |
| 06/04/2021 | $150K | — | — → — | $65/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| DOWNTOWN ENGINEERS | 5 | 06/15/2026 |
| CORTNEY WALLESTON ARCHITECT, PC | 3 | 10/16/2025 |
| NY BUILDING ASSOCIATES INC | 2 | 03/11/2025 |
| A DEGREE OF FREEDOM STRUCTURAL ENGI | 3 | 09/16/2024 |
| NEW YORK ENGINEERS LLC | 1 | 08/08/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| CLARKE CONSTRUCTION CONSULTANTS | 11 | 03/21/2026 |
| BROOKLYN SOLARWORKS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ROCK & HAMMER CONSTRUCTIO | General Contractor | 6 | 07/08/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 2 | 03/21/2026 |
| MILLENNIUM HVAC NY INC | General Contractor | 1 | 07/08/2026 |
| DOYLE BROS PLBG & HTG INC | Plumbing | 1 | 07/04/2026 |
| PREMIER FLOW PLBG AND HTG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CORTNEY WALLESTON ARCHITE | 3881 | 6 | 06/15/2026 |
| MB INSPECTIONS, CORP. | 8703 | 2 | 05/31/2025 |
| NEW YORK ENGINEERS, P.C. | 3868 | 4 | 05/31/2025 |
| NKM ENGINEERING PLLC | 6244 | 2 | 03/11/2025 |
| A DEGREE OF FREEDOM STRUC | 925 | 3 | 09/16/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | DOYLE BROS PLBG & HTG INC | 07/02/2026 |
| DOB NOW | Structural | Signed-off | ROCK & HAMMER CONSTRUCTIO | 10/09/2025 |
| DOB NOW | General Construction | Permit Issued | ROCK & HAMMER CONSTRUCTIO | 10/09/2025 |
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 02/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MILLENNIUM HVAC NY INC | 02/10/2025 |
| DOB NOW | Structural | Signed-off | ROCK & HAMMER CONSTRUCTIO | 10/15/2024 |
| DOB NOW | General Construction | Permit Issued | ROCK & HAMMER CONSTRUCTIO | 10/11/2024 |
| DOB NOW | Plumbing | Signed-off | GALICJA PLBG AND HTG.CORP | 09/27/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/17/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/30/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 07/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/26/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/03/2026 | Fire-Resistant Penetrations and Joints | Cortney Walleston | special |
| 11/06/2025 | Fenestration and door U-factor and product ratings | Cortney Walleston | energy_progress |
| 11/06/2025 | Energy Code Compliance Inspections | Cortney Walleston | progress |
| 11/06/2025 | Fire-Resistance Rated Construction | Cortney Walleston | progress |
| 11/06/2025 | Fire-Resistant Penetrations and Joints | Cortney Walleston | special |
| 11/06/2025 | Air barrier - visual inspection | Cortney Walleston | energy_progress |
| 11/06/2025 | Fenestration air leakage | Cortney Walleston | energy_progress |
| 11/06/2025 | Insulation placement and R values | Cortney Walleston | energy_progress |
| 11/06/2025 | Lighting in dwelling units | Cortney Walleston | energy_progress |
| 11/06/2025 | Fenestration areas | Cortney Walleston | energy_progress |
| 10/14/2025 | Fenestration air leakage | Cortney Walleston | energy_progress |
| 10/14/2025 | Insulation placement and R values | Cortney Walleston | energy_progress |
| 10/14/2025 | Fenestration areas | Cortney Walleston | energy_progress |
| 10/14/2025 | Air barrier - visual inspection | Cortney Walleston | energy_progress |
| 10/14/2025 | Fenestration and door U-factor and product ratings | Cortney Walleston | energy_progress |
| 10/14/2025 | Lighting in dwelling units | Cortney Walleston | energy_progress |
| 10/14/2025 | Fire-Resistance Rated Construction | Cortney Walleston | progress |
| 10/14/2025 | Energy Code Compliance Inspections | Cortney Walleston | progress |
| 10/14/2025 | Fire-Resistant Penetrations and Joints | Cortney Walleston | special |
| 06/13/2025 | Ventilation and air distribution system | Michael Tobias | energy_progress |
| 06/13/2025 | HVAC-R and service water heating system controls | Michael Tobias | energy_progress |
| 06/13/2025 | HVAC-R and service water piping design and insulation | Michael Tobias | energy_progress |
| 06/13/2025 | Mechanical Systems | Michael Tobias | special |
| 06/13/2025 | Post-installed Anchors | BORIS BALKHIYEV | special |
| 06/13/2025 | Fire-Resistant Penetrations and Joints | Michael Tobias | special |