← Back
Walk-up cooperative
322 EAST 11 STREET
MANHATTAN · East Village · BIN 1006441
💬 Discuss this project
1900Year Built
6Stories
C6Building Class
R8BZoning
10,794 sfGross Floor Area
25Units
Rent Stabilized119 Open Violations ▸
Walk-up cooperative · 2,369 sf lot · 4.56 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction21p · 2 filings · 20 docs
Floor 618p · 2 filings · 20 docs
Floor 523p · 2 filings · 20 docs
Floor 418p · 2 filings · 20 docs
Floor 321p · 2 filings · 20 docs
Floor 229p · 2 filings · 20 docs
Floor 138p · 3 filings · 20 docs
Cellar11p · 1 filing · 20 docs
Basement1p · 1 filing · 3 docs
Sub-Basement12p · 2 filings · 18 docs
Site & exterior3p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TOWER BROKERAGE4207/08/2026
S J CONSTRUCTION SERVIC507/08/2026
S & J CONSTRUCTION SERVIC403/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ATELIER NEW YORK ARCHITECTURE303/21/2026
KUSHNER STUDIOS303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ELITE ILLUSION CONSTRUCTGeneral Contractor907/08/2026
IDEAL CONSTRUCTION & DESIGNGeneral Contractor704/09/2026
S & J CONSTRUCTION SVCGeneral Contractor407/08/2026
PLBG P & H INCPlumbing207/08/2026
RICHARD NEUElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ATELIER NY ARCHITECTURE2438707/13/2026
KENDALL ENGINEERING PC4154204/14/2025
INTEGRITY CONSULTING SERV666108/15/2023
Building Lifecycle
All (147)Filed (19)Permit Issued (13)Signed Off (7)Violation (60)Inspection (10)Objection (8)Special Inspection (30)
08/24/2026
Objection resolved — Resolved
08/24/2026
Objection resolved — Resolved
08/18/2026
Objection resolved — Resolved
08/11/2026
Objection raised — Admin
08/11/2026
Objection raised — Scope
08/11/2026
Objection raised — Structural
07/13/2026
Filed — Alteration CO
FILED FOR THE INSTALLATION OF NEW ROOF DECK AND TO OBTAIN NEW CERTIFICATE OF OCCUPANCY.
M00889127-P2
05/04/2026
Special inspection requirement — Tenant Protection Plan Compliance
05/04/2026
Special inspection requirement — Exterior lighting power
Anatole Plotkin
05/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anatole Plotkin
05/04/2026
Special inspection requirement — Energy Code Compliance Inspections
Anatole Plotkin
05/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
Anatole Plotkin
04/29/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/06/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
03/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
03/26/2026
Special inspection requirement — Exterior lighting power
Anatole Plotkin
03/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anatole Plotkin
03/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
Anatole Plotkin
03/26/2026
Special inspection requirement — Energy Code Compliance Inspections
Anatole Plotkin
03/03/2026
Filed — Alteration CO
FILED FOR THE INSTALLATION OF NEW ROOF DECK AND TO OBTAIN NEW CERTIFICATE OF OCCUPANCY.
M00889127-P1
01/16/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/18/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
12/05/2025
Permit issued — General Construction
M00889127-I1-GC
12/02/2025
Signed off — Alteration
PLUMBING WORK IN APARTMENTS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806705-I1
12/02/2025
Signed off — Alteration
RENOVATION OF APARTMENTS. PARTITION CHANGES TO NON-LOAD-BEARING WALLS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806681-I1
11/24/2025
Signed off — Alteration
M00881251-I1
11/20/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/05/2025
Permit issued — Boiler Equipment
M00881251-I1-BE
07/23/2025
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
07/15/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/09/2025
Signed off — Alteration
RENOVATION OF APARTMENTS. PARTITION CHANGES TO NON-LOAD-BEARING WALLS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806681-S1
07/07/2025
Permit issued — Plumbing
M00806705-I1-PL
07/02/2025
Signed off — Alteration CO
FILED FOR THE INSTALLATION OF NEW ROOF DECK AND TO OBTAIN NEW CERTIFICATE OF OCCUPANCY.
M00889127-S1
07/02/2025
Special inspection requirement — Fenestration air leakage
Anatole Plotkin
07/02/2025
Special inspection requirement — Energy Code Compliance Inspections
Anatole Plotkin
07/02/2025
Special inspection requirement — Fire-Resistance Rated Construction
Anatole Plotkin
07/02/2025
Special inspection requirement — Lighting in dwelling units
Anatole Plotkin
07/02/2025
Special inspection requirement — Air barrier - visual inspection
Anatole Plotkin
07/02/2025
Special inspection requirement — Fenestration areas
Anatole Plotkin
07/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Anatole Plotkin
07/02/2025
Special inspection requirement — Final
Anatole Plotkin
07/02/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Anatole Plotkin
07/01/2025
Filed — Alteration
RENOVATION OF APARTMENTS. PARTITION CHANGES TO NON-LOAD-BEARING WALLS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806681-P5
06/20/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
04/21/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
04/15/2025
Special inspection requirement — HVAC-R and service water heating system controls
KEVIN KENDALL
04/15/2025
Special inspection requirement — Maintenance information
KEVIN KENDALL
04/15/2025
Special inspection requirement — Mechanical Systems
KEVIN KENDALL
04/15/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
KEVIN KENDALL
04/15/2025
Special inspection requirement — Final
KEVIN KENDALL
04/15/2025
Special inspection requirement — HVAC-R and service water heating equipment
KEVIN KENDALL
04/14/2025
Filed — Alteration
RENOVATION OF APARTMENTS. PARTITION CHANGES TO NON-LOAD-BEARING WALLS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806681-P4
04/14/2025
Filed — Alteration
PLUMBING WORK IN APARTMENTS AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
M00806705-P4
04/05/2025
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00835516-I1
04/05/2025
Signed off — Alteration
PROPOSED INSTALLATION OF DEBRIS CHUTE AS PER PLANS. CHUTE SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00835667-I1
02/07/2025
Permit issued — General Construction
M00806681-I1-GC
02/06/2025
Permit issued — General Construction
M00889127-I1-GC
01/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
KEVIN KENDALL
01/28/2025
Special inspection requirement — Final
KEVIN KENDALL
Latest 60 of 147 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedIDEAL CONSTRUCTION & DESI12/05/2025
DOB NOWBoiler EquipmentSigned-offOLYMPIAN FUEL OIL CORP11/05/2025
DOB NOWPlumbingSigned-offPLBG P & H INC07/07/2025
DOB NOWGeneral ConstructionSigned-offIDEAL CONSTRUCTION & DESI02/07/2025
DOB NOWGeneral ConstructionPermit IssuedIDEAL CONSTRUCTION & DESI02/06/2025
DOB NOWMechanical SystemsSigned-offELITE ILLUSION CONSTRUCT05/21/2024
DOB NOWGeneral ConstructionPermit IssuedELITE ILLUSION CONSTRUCT04/05/2024
DOB NOWStructuralSigned-offELITE ILLUSION CONSTRUCT04/04/2024
DOB NOWGeneral ConstructionSigned-offELITE ILLUSION CONSTRUCT10/23/2023
DOB NOWPlumbingSigned-offPLBG P & H INC04/05/2023
DOB NOWGeneral ConstructionSigned-offELITE ILLUSION CONSTRUCT03/28/2023
DOB NOWProtection and Mechanical MethodsSigned-offS & J CONSTRUCTION SVC03/02/2023
DOB NOWSidewalk ShedSigned-offS & J CONSTRUCTION SVC02/28/2023
4 projects · most recent 07/15/2026
General Wiring
FiledStatusContractorScope
07/15/2026Permit IssuedMARTINEZ ELECTRICAL CONTGeneral Wiring
08/05/2025CompleteLAURA ELEC'L LIGHTING &—
08/17/2023CompleteSUPREME ELECTRIC CORPGeneral Wiring
03/02/2023CompleteRICHARD NEU—
1 project · most recent 07/13/2026
Steel
FiledStatusContractorScope
07/13/2026Permit IssuedIDEAL CONSTRUCTION & DESISteel
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
04/29/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/06/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/16/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/18/2025Fail-Final CND-Occupancy InspectionFailView ↗
11/20/2025Pass-Final Boiler Equipment InspectionPassView ↗
07/23/2025No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
07/15/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/20/2025Fail-Final General Construction Non-Directive 14FailView ↗
04/21/2025Fail-Final General Construction Non-Directive 14FailView ↗
11/17/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 63
DateRequirementInspectorRole
05/04/2026Fire-Resistance Rated ConstructionAnatole Plotkinprogress
05/04/2026Exterior lighting powerAnatole Plotkinenergy_progress
05/04/2026Tenant Protection Plan Compliance—special
05/04/2026Fire-Resistant Penetrations and JointsAnatole Plotkinspecial
05/04/2026Energy Code Compliance InspectionsAnatole Plotkinprogress
03/26/2026Exterior lighting powerAnatole Plotkinenergy_progress
03/26/2026Fire-Resistant Penetrations and JointsAnatole Plotkinspecial
03/26/2026Fire-Resistance Rated ConstructionAnatole Plotkinprogress
03/26/2026Tenant Protection Plan Compliance—special
03/26/2026Energy Code Compliance InspectionsAnatole Plotkinprogress
07/02/2025Fenestration and door U-factor and product ratingsAnatole Plotkinenergy_progress
07/02/2025Air barrier - visual inspectionAnatole Plotkinenergy_progress
07/02/2025Fenestration air leakageAnatole Plotkinenergy_progress
07/02/2025Fire-Resistance Rated ConstructionAnatole Plotkinprogress
07/02/2025Lighting in dwelling unitsAnatole Plotkinenergy_progress
07/02/2025Energy Code Compliance InspectionsAnatole Plotkinprogress
07/02/2025FinalAnatole Plotkinprogress
07/02/2025Fire-Resistant Penetrations and JointsAnatole Plotkinspecial
07/02/2025Fenestration areasAnatole Plotkinenergy_progress
04/15/2025HVAC-R and service water piping design and insulationKEVIN KENDALLenergy_progress
04/15/2025Maintenance informationKEVIN KENDALLenergy_progress
04/15/2025FinalKEVIN KENDALLprogress
04/15/2025Mechanical SystemsKEVIN KENDALLspecial
04/15/2025HVAC-R and service water heating system controlsKEVIN KENDALLenergy_progress
04/15/2025HVAC-R and service water heating equipmentKEVIN KENDALLenergy_progress
Latest 25 of 63.
▾Documents — 119 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch19
09/01/2026M00806705-P1Request digital key ↗
09/01/2026M00806705-P2Request digital key ↗
09/01/2026M00806705-P3Request digital key ↗
Showing 3 of 19 on file for this type
▸Seals & Professional Certifications76
▸DOB NOWProgress Inspector Seal & Signature49
09/27/2026M00806681-P2Open ↗
09/27/2026M00806681-P2Open ↗
09/27/2026M00806681-P2Open ↗
Showing 3 of 49 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature19
09/01/2026M00806705-I1Open ↗
09/01/2026M00806705-P1Open ↗
09/01/2026M00806705-P2Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/27/2026M00806681-P2Open ↗
08/29/2026M00806681-P3Open ↗
08/28/2026M00889127-S1Open ↗
Showing 3 of 8 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist3
08/29/2026M00889127-P1Open ↗
08/29/2026M00889127-I1Open ↗
08/14/2026M00889127-P2Open ↗
▸Environmental & Asbestos17
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
09/01/2026M00806705-P1Open ↗
09/01/2026M00806705-P2Open ↗
09/01/2026M00806705-P3Open ↗
Showing 3 of 17 on file for this type
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M00806681-S1Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification3
08/29/2026M00889127-P1Open ↗
08/29/2026M00889127-I1Open ↗
08/14/2026M00889127-P2Open ↗