← Back
MANHATTAN
The Matteo Condominium
323 EAST 79 STREET · Upper East Side-Yorkville · BIN 1049249
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
LL97 Covered0 Open Violations
Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentCivilGeneral
Floor 72p · 1 filing · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Site & exterior8 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNERS REP2207/08/2026
ROCK GROUP NY1107/08/2026
BOOMERANG BUILDING FUND907/08/2026
SR79903/21/2026
MA1707/08/2026
BOOMERRANG 79603/21/2026
SPRUCE CAPITAL PARTNERS303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/16/2021$13.7M—SR 79 LLC → BOOMERANG 79 LLC— not available
11/15/2017$12.8M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAUL PERDEK, PROF. ENG. PLLC1303/23/2023
KN3 ENGINEERING LLC111/24/2021
LU ENGINEERING SERVICE PC311/22/2021
HPL ENGINEERING P.C.107/09/2021
ASIF JAMIL, RA205/29/2019
SOUTH BAY ENGINEERING PLLC105/23/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION2803/21/2026
H Z BUILDING NY803/21/2026
GREEN STUDIO403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CORE SCAFFOLD SYSTEMS INC.General Contractor2007/08/2026
ROCK GROUP NY CORPGeneral Contractor807/08/2026
SUNLIGHT CONSTRUCTION AAGeneral Contractor507/08/2026
H&Z BUILDING CONSULTING IGeneral Contractor407/08/2026
JEM CONTRACTING CORPGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LEO Y LEE ASSOCIATES2481401/21/2023
AR-TECH ENGINEERING, P.C.6659206/02/2022
ROYAL CONSTRUCTION P.E. S462311/22/2021
Building Lifecycle
All (95)Filed (21)Permit Issued (19)Signed Off (9)Violation (8)Objection (18)Special Inspection (20)
11/09/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00843075-I1
09/11/2023
Signed off — Alteration
Proposed construction fence. No change to use, egress or occupancy under this application.
M00141701-I1
08/30/2023
Signed off — Alteration
SUPPORT OF EXCAVATION (SOE) WORK AS PER PLANS FILED. IN CONJUNCTION WITH NB JOB#123253273.
M00530603-I1
08/21/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00637083-I1
08/21/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657528-I1
08/21/2023
Signed off — Alteration
PROPOSED TEMPORARY CONSTRUCTION FENCE WORK AT OSP IN CONJUNCTION WITH NB APPLICATION #123253273.
M00549527-I1
08/21/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-I1
08/21/2023
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00637055-I1
03/23/2023
Filed — Alteration
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00843075-I1
03/23/2023
Permit issued — Protection and Mechanical Methods
M00843075-I1-PMM
02/08/2023
Special inspection requirement — Post-installed Anchors
Leo Lee
02/08/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
01/31/2023
Objection resolved — Addressed
01/27/2023
Permit issued — Protection and Mechanical Methods
M00657537-I1-PM
01/27/2023
Objection raised — Scope
01/21/2023
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-P5
01/20/2023
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657528-P3
01/17/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
01/17/2023
Special inspection requirement — Post-installed Anchors
Leo Lee
01/10/2023
Permit issued — Construction Fence
M00549527-I1-FN
01/04/2023
Permit issued — Supported Scaffold
M00657528-I1-SF
11/21/2022
Permit issued — Sidewalk Shed
M00637055-I1-SH
11/21/2022
Permit issued — Protection and Mechanical Methods
M00637083-I1-PM
09/26/2022
Objection raised — Scope
09/26/2022
Objection resolved — Addressed
09/25/2022
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657528-P2
09/25/2022
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-P4
09/13/2022
Special inspection requirement — Post-installed Anchors
Leo Lee
09/13/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
09/06/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/06/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/2022
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-P3
08/22/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
08/22/2022
Special inspection requirement — Post-installed Anchors
Leo Lee
06/07/2022
Objection resolved — Addressed
06/07/2022
Objection resolved — Addressed
06/06/2022
Objection raised — Scope
06/06/2022
Objection raised — Scope
06/02/2022
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-P2
05/23/2022
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-P1
05/23/2022
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657528-P1
05/22/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
ALBERTO ROMAN
05/22/2022
Special inspection requirement — Post-installed Anchors
ALBERTO ROMAN
02/10/2022
Permit issued — Protection and Mechanical Methods
M00657537-I1-PM
01/19/2022
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00637055-P1
01/19/2022
Permit issued — Construction Fence
M00549527-I1-FN
01/14/2022
Permit issued — Construction Fence
M00549527-I1-FN
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection resolved — Addressed
01/06/2022
Permit issued — Supported Scaffold
M00657528-I1-SF
01/06/2022
Objection raised — Structural
01/06/2022
Objection raised — Structural
01/06/2022
Objection raised — Scope
01/06/2022
Objection raised — Other
01/05/2022
Filed — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657528-I1
01/05/2022
Filed — Alteration
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00657537-I1
11/26/2021
Permit issued — Sidewalk Shed
M00637055-I1-SH
11/26/2021
Permit issued — Protection and Mechanical Methods
M00637083-I1-PM
Latest 60 of 95 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsSigned-offJEM CONTRACTING CORP03/23/2023
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC01/27/2023
DOB NOWConstruction FenceSigned-offH&Z BUILDING CONSULTING I01/10/2023
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC01/04/2023
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC11/21/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC11/21/2022
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC02/10/2022
DOB NOWConstruction FenceSigned-offH&Z BUILDING CONSULTING I01/19/2022
DOB NOWConstruction FenceSigned-offSUNLIGHT CONSTRUCTION AA01/14/2022
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC01/06/2022
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC11/26/2021
DOB NOWProtection and Mechanical MethodsSigned-offCORE SCAFFOLD SYSTEMS INC11/26/2021
DOB NOWEarth WorkSigned-offH&Z BUILDING CONSULTING I08/10/2021
DOB NOWEarth WorkSigned-offSUNLIGHT CONSTRUCTION AA06/16/2021
DOB NOWSupported ScaffoldSigned-offROCK GROUP NY CORP03/18/2021
DOB NOWSupported ScaffoldSigned-offROCK GROUP NY CORP03/18/2021
DOB NOWConstruction FenceSigned-offSUNLIGHT CONSTRUCTION AA02/18/2021
DOB NOWSidewalk ShedSigned-offROCK GROUP NY CORP05/23/2019
DOB NOWSidewalk ShedSigned-offROCK GROUP NY CORP05/23/2019
BIS—ISSUEDCONSTRUCTION MNGT. AA,LLC08/28/2023
BIS—ISSUEDH&Z BUILDING CONSULTING I03/15/2023
BISSDISSUEDDYNAMIC PLBNG & SPRKR COR11/29/2022
BISPLISSUEDFULL CIRCLE PLUMBING CORP.11/27/2022
BIS—ISSUEDH&Z BUILDING CONSULTING I03/18/2022
BIS—ISSUEDH&Z BUILDING CONSULTING I03/18/2022
BIS—ISSUEDH&Z BUILDING CONSULTING I03/02/2022
BIS—ISSUEDH&Z BUILDING CONSULTING I03/02/2022
BIS—ISSUEDSUNLIGHT CONSTRUCTION AA02/03/2022
BIS—ISSUEDSUNLIGHT CONSTRUCTION AA12/10/2021
BIS—ISSUEDSUNLIGHT CONSTRUCTION AA12/10/2021
BISSDISSUEDDYNAMIC PLBNG & SPRKR COR11/30/2021
BISPLISSUEDFULL CIRCLE PLUMBING CORP.11/24/2021
BIS—ISSUEDSUNLIGHT CONSTRUCTION AA09/23/2021
BIS—ISSUEDSUNLIGHT CONSTRUCTION AA09/08/2021
BIS—ISSUEDALBA SERVICES INC04/07/2021
BISOTISSUEDALBA SERVICES INC05/09/2019
BISPLISSUEDPOLGANO PLUMBING INC12/07/2016
BISFPISSUEDCHIEF FIRE PREV.& MECH CO06/23/2016
BISOTISSUEDCHIEF FIRE PREVENTION & MECH06/03/2016
BISEQISSUEDH & B CONSTRUCTION NY INC06/17/2009
+ 7 more permits on file
4 projects · most recent 11/29/2021
FiledStatusContractorScope
11/29/2021CompleteV. VASS ELECTRIC CORP—
11/22/2021CompleteV. VASS ELECTRIC CORP—
04/14/2021CompleteALBA ELECTRIC CORP—
04/22/2019CompleteTOP SHELF ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
02/08/2023Post-installed AnchorsLeo Leespecial
02/08/2023Structural Stability – Alterations of existing buildingsLeo Leespecial
01/17/2023Structural Stability – Alterations of existing buildingsLeo Leespecial
01/17/2023Post-installed AnchorsLeo Leespecial
09/13/2022Post-installed AnchorsLeo Leespecial
09/13/2022Structural Stability – Alterations of existing buildingsLeo Leespecial
08/22/2022Structural Stability – Alterations of existing buildingsLeo Leespecial
08/22/2022Post-installed AnchorsLeo Leespecial
05/22/2022Structural Stability – Alterations of existing buildingsALBERTO ROMANspecial
05/22/2022Post-installed AnchorsALBERTO ROMANspecial
11/22/2021UnderpinningEBRAHIM MIANDOABIspecial
11/22/2021FinalEBRAHIM MIANDOABIprogress
11/22/2021Excavations - Sheeting, Shoring, and BracingEBRAHIM MIANDOABIspecial
11/22/2021Structural Stability – Alterations of existing buildingsEBRAHIM MIANDOABIspecial
11/19/2021Excavations - Sheeting, Shoring, and BracingEBRAHIM MIANDOABIspecial
11/19/2021Structural Stability – Alterations of existing buildingsEBRAHIM MIANDOABIspecial
11/19/2021UnderpinningEBRAHIM MIANDOABIspecial
11/19/2021FinalEBRAHIM MIANDOABIprogress
05/30/2019Finalasif jamilprogress
05/30/2019Preliminaryasif jamilprogress
▾Documents — 156 on file (BIS + DOB NOW)
▸Plans & Drawings23
▸DOB NOWPlans/Sketch18
09/03/2026M00549527-I1Request digital key ↗
09/03/2026M00530603-P2Request digital key ↗
09/03/2026M00530603-P1Request digital key ↗
Showing 3 of 18 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00157849-I1Request digital key ↗
08/15/2026M00157849-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/05/2026M00157849-I1Request digital key ↗
08/15/2026M00157849-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/14/2026M00141701-I1Request digital key ↗
▸Applications & Permits30
▸BISPLAN / WORK APPROVAL APPLICATION20
09/12/2023122794878Open ↗
09/12/2023120058356Open ↗
09/12/2023101626803Open ↗
Showing 3 of 20 on file for this type
▸BISWORK PERMIT APPLICATION6
04/07/2021123362280Open ↗
12/13/2016122794878Open ↗
06/27/2016122794878Open ↗
Showing 3 of 6 on file for this type
▸BISPLACE OF ASSEMBLY2
08/19/2015122070052Open ↗
07/24/2014122070052Open ↗
▸BISPLACE OF ASSEMBLY SIGN OFF1
09/08/2015122070052Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation1
08/31/2021123785840Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
04/07/2021123362280Open ↗
▸Seals & Professional Certifications52
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/05/2026M00157849-I1Open ↗
09/05/2026M00157849-P1Open ↗
09/03/2026M00530603-P1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature16
09/29/2026M00657537-I1Open ↗
09/29/2026M00657537-I1Open ↗
08/28/2026M00530603-I1Open ↗
Showing 3 of 16 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
10/21/2016122742112Open ↗
10/21/2016122742112Open ↗
06/27/2016122794878Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/28/2026M00530603-I1Open ↗
08/24/2026M00157849-I1Open ↗
08/24/2026M00157849-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
06/03/2016122742112Open ↗
06/08/2009120058356Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
06/03/2016122742112Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
03/21/2019140832320Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/08/2009120058356Open ↗
▸Trade Schedules & Equipment5
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
04/07/2021123362280Open ↗
▸BISELECTRIC CUT-OFF1
04/07/2021123362280Open ↗
▸BISDEP STORMWATER/SEWER CERTIFICATION (HCP/SCP)1
04/07/2021123362280Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
06/07/2016122794878Open ↗
▸BISSCHEDULE B - PLUMBING1
03/21/2019140832320Open ↗
▸Safety & Tenant Protection7
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
04/07/2021123362280Open ↗
04/07/2021123362280Open ↗
04/07/2021123362280Open ↗
▸BISSTREET TREE CHECKLIST2
10/11/2019123785840Open ↗
06/08/2009120058356Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
04/07/2021123362280Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
04/07/2021123362280Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
04/07/2021123362280Open ↗
06/07/2016122794878Open ↗
06/03/2016122742112Open ↗
▸BISRODENT CONTROL1
04/07/2021123362280Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
06/08/2009120058356Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
10/21/2016122742112Open ↗
10/21/2016122742112Open ↗
06/03/2016122742112Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/21/2016122742112Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
03/21/2019140832320Open ↗
▸Approvals, Objections & Sign-offs6
▸BISLETTERS - SUPPORTING DOCUMENTATION3
04/07/2021123362280Open ↗
04/07/2021123362280Open ↗
09/08/2015122070052Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/21/2016122742112Open ↗
▸BISLANDMARKS APPROVAL1
04/07/2021123362280Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/08/2009120058356Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
02/11/2019123667479Open ↗
10/21/2016122742112Open ↗
06/07/2016122794878Open ↗
Showing 3 of 4 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE1
04/07/2021123362280Open ↗
▸Filing & Intake Forms14
▸BISEFILING COVER SHEET6
10/11/2019123785840Open ↗
02/11/2019123667479Open ↗
01/18/2019123362280Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION3
08/31/2021123785840Open ↗
05/01/2019140832320Open ↗
03/21/2019140832320Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT32
08/31/2021123785840Open ↗
10/11/2019123785840Open ↗
▸BISBOROUGH INTAKE FORM2
04/07/2021123362280Open ↗
04/07/2021123362280Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
02/15/2019140832320Open ↗
▸Other Documents3
▸BISCOMMUNITY BOARD NOTIFICATION1
04/07/2021123362280Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
08/31/2021123785840Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026M00530603-I1Open ↗