| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/29/2021 | $1.6M | — | Private party → Private party | $651/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CORDERO ARCHITECTURE PLLC | 10 | 07/31/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EC FRAMING INC | General Contractor | 4 | 07/08/2026 |
| R.J.C. MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | EC FRAMING INC | 10/23/2023 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 12/14/2022 |
| DOB NOW | Plumbing | Signed-off | R.J.C. MECHANICAL CORP | 01/17/2022 |
| DOB NOW | General Construction | Signed-off | EC FRAMING INC | 01/07/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/15/2022 | Complete | OCNYC ELECL CONTNG INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/17/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/24/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/20/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/12/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/18/2021 | Final | — | progress |
| 12/18/2021 | Lighting in dwelling units | — | energy_progress |
| 12/18/2021 | Metering | — | energy_progress |