← Back
Office with commercial, 7-19 stories
323 HUDSON STREET
MANHATTAN · BIN 1010375
💬 Discuss this project
1967Year Built
10Stories
O6Building Class
M1-6Zoning
193,813 sfGross Floor Area
5Units
LL97 Covered0 Open ViolationsFISP: SAFE
Office with commercial, 7-19 stories · Owner of record: DWF VI 325 HUDSON, LLC · 19,470 sf lot · 9.95 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction50p · 16 filings · 20 docs
Bulkhead1p · 1 filing · 4 docs
Penthouse2p · 1 filing · 20 docs
Floor 1047p · 6 filings · 20 docs
Floor 939p · 2 filings · 20 docs
Floor 840p · 3 filings · 20 docs
Floor 71p · 1 filing · 20 docs
Floor 619p · 2 filings · 20 docs
Floor 517p · 1 filing · 20 docs
Floor 417p · 1 filing · 20 docs
Floor 356p · 3 filings · 20 docs
Floor 2Under Construction21p · 2 filings · 20 docs
Floor 124p · 4 filings · 20 docs
Cellar62p · 13 filings · 20 docs
2 jobs · most recent 08/26/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/26/2026Permit IssuedCLEARESULT CONSULTING INCAir Conditioning Systems
Cooling
Trane ×2
12/28/2025Permit IssuedTISHMAN INTERIORS CORPAir Conditioning Systems
Cooling
Liebert VS070KDA0E045D0 20 tons · Crac Unit ×4
2 jobs · most recent 01/23/2026
FiledStatusContractorScope
01/23/2026Signed-offPSI PARTNERS, LLC64 heads
08/16/2022——1 outlets
1 job · most recent 01/23/2026
FiledStatusContractorScope
01/23/2026———
21 jobs · most recent 01/29/2026
General Wiring
FiledStatusContractorScope
01/29/2026Permit IssuedRX ELECTRIC INC—
01/29/2026Permit IssuedRX ELECTRIC INCGeneral Wiring
07/12/2024CompleteCENTRIFUGAL ELECTRIC LLCGeneral Wiring
07/12/2024CompleteCENTRIFUGAL ELECTRIC LLC—
05/01/2024CompleteCENTRIFUGAL ELECTRIC LLC—
10/11/2023CompleteALLIANCE ELEVATOR COMPANY—
08/24/2023Permit IssuedRAINBOW ELECTRIC CO., INC—
08/24/2023Permit IssuedRAINBOW ELECTRIC CO., INC—
10/27/2022CompleteALLIANCE ELEVATOR COMPANY—
10/26/2022CompleteALLIANCE ELEVATOR COMPANY—
09/26/2022CompleteANTHONY G FERRY INC—
04/07/2021CompleteDIANE ELECTRIC INC.General Wiring
04/07/2021CompleteDIANE ELECTRIC INC.General Wiring
10/02/2020CompleteBIGMAN BROS., INC.General Wiring
07/30/2020CompleteUNI-LITE ELECTRIC, LLCGeneral Wiring
1 job · most recent 01/23/2026
FiledStatusContractorScope
01/23/2026Signed-offCLUNE CONSTRUCTION CO LP1 scope_items
1 job · most recent 09/27/2022
Fence
FiledStatusContractorScope
09/27/2022Permit IssuedROCKLEDGE SCAFFOLD CORPFence
1 job · most recent 12/14/2023
Suspended Scaffold (SC)
FiledStatusContractorScope
12/14/2023Permit IssuedTITAN CONST SERVICES LLCSuspended Scaffold (SC)
Building Lifecycle
All (300)Filed (65)Permit Issued (75)Signed Off (33)Facade (FISP) (6)Violation (7)Inspection (42)Objection (42)Special Inspection (30)
08/31/2026
Permit issued — Mechanical Systems
M01436429-I1-MS
08/26/2026
Filed — Alteration
Filing herewith for two 30-ton energy recovery chillers and repurpose 170-ton Dry Cooler
M01436429-I1
08/13/2026
Signed off — Alteration
Filing herewith for sprinkler modification as per plans.
M01347845-I1
07/26/2026
Special inspection requirement — Final
Benjamin Plotnick
07/26/2026
Special inspection requirement — Mechanical Systems
Benjamin Plotnick
07/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Benjamin Plotnick
07/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
Benjamin Plotnick
07/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
Benjamin Plotnick
07/26/2026
Special inspection requirement — Maintenance information
Benjamin Plotnick
07/26/2026
Special inspection requirement — Energy Code Compliance Inspections
Benjamin Plotnick
06/26/2026
Signed off — Alteration
Filing herewith for interior fit-out of the 10th floor as per plans filed herewith.
M01347191-I1
06/01/2026
Permit issued — Sprinklers
M00817597-I1-EW-SP
05/08/2026
Filed — Alteration CO
Filing herewith to change the use on the 3rd, 5th & 6th floors.
M00664241-P6
05/04/2026
Permit issued — Antenna
M00000729-I1-AN
03/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
GIORGI KHARDZEISHVILI
03/17/2026
Special inspection requirement — Sprayed fire-resistant materials
GIORGI KHARDZEISHVILI
02/27/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/04/2026
Permit issued — Sprinklers
M01347845-I1-EW-SP
02/02/2026
Signed off — Alteration
Filing herewith for cap and removal of two boilers. Boiler numbers 10000200633N0001 & 10000200634N0002
M01338926-I1
01/29/2026
Permit issued — Mechanical Systems
M01347191-I1-MS
01/23/2026
Filed — Alteration
Filing herewith for sprinkler modification as per plans.
M01347845-I1
01/23/2026
Filed — Alteration
Filing herewith for interior fit-out of the 10th floor as per plans filed herewith.
M01347191-I1
01/16/2026
Special inspection requirement — Sprinkler Systems
Nicolas Crosetto
01/16/2026
Special inspection requirement — Post-installed Anchors
Nicolas Crosetto
01/16/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Nicolas Crosetto
01/13/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/06/2026
Permit issued — Plumbing
M01338926-I1-PL
12/31/2025
Permit issued — Mechanical Systems
M01336917-I1-MS
12/30/2025
Filed — Alteration
Filing herewith for cap and removal of two boilers. Boiler numbers 10000200633N0001 & 10000200634N0002
M01338926-I1
12/28/2025
Filed — Alteration
Filing for the removal and replacement of (4) AC units and related ducts.
M01336917-I1
12/18/2025
Special inspection requirement — HVAC-R and service water heating system controls
EUGENE BIFULCO
12/18/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
EUGENE BIFULCO
12/18/2025
Special inspection requirement — Maintenance information
EUGENE BIFULCO
12/18/2025
Special inspection requirement — Mechanical Systems
EUGENE BIFULCO
12/18/2025
Special inspection requirement — Final
EUGENE BIFULCO
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/23/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/11/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF / OVERHEAD PROTECTION AT ADJACENT PROPERTIES DURING BLDG ALTERATION, FILED SEP. ROOF / OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M08007706-I1
09/11/2025
Signed off — Alteration
INSTALLATION OF WORK DECK AND MONORAIL IN ACCORDANCE WITH NYCC CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M00807896-I1
09/11/2025
Signed off — Alteration
TEMPORARY CRASH DECK AS PER DRAWINGS. CRASH DECK SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M08007661-S1
09/11/2025
Signed off — Alteration
INSTALLATION OF SUPPORTED SCAFFOLDING IN ACCORDANCE WITH NYC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
M00859950-I1
09/11/2025
Signed off — Alteration
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M08006094-I1
09/11/2025
Signed off — Alteration
TEMPORARY CRASH DECK AS PER DRAWINGS. CRASH DECK SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M08007661-I1
06/10/2025
Signed off — Alteration
Installation of two new Boilers
M00833817-I1
05/29/2025
Permit issued — Antenna
M00000729-I1-AN
04/08/2025
Signed off — Alteration
Modification to existing HVAC systems as per plans filed herewith.
M00772207-I1
04/04/2025
Signed off — Alteration
Modification to existing HVAC system as plans filed herewith.
M00802978-I1
03/27/2025
Signed off — Alteration
Modification to existing sprinkler system, standpipe and plumbing fixtures as per plans.
M00806507-I1
03/26/2025
Signed off — Alteration
Modification to existing sprinkler system and plumbing fixtures as per plans filed herewith.
M00772210-I1
03/13/2025
Signed off — Alteration
Filing herewith for sprinkler heads as per plans filed herewith.
M00731375-I1
03/05/2025
Signed off — Alteration
Installation of non load bearing partitions as per plans filed herewith. No change in use egress or occupancy.
M00670432-I1
03/04/2025
Signed off — Alteration
Installation of non load bearing partitions as per plans filed herewith. No change in use egress or occupancy.
M00670230-I1
03/04/2025
Signed off — Alteration
Filing herewith for HVAC ductwork and mechanical as per plans filed herewith.
M00731302-I1
03/04/2025
Signed off — Alteration
Modification to existing mechanical system as per plans
M00731451-I1
03/03/2025
Signed off — Alteration
Installation of sprinkler heads as per plans filed herewith.
M00734071-I1
03/03/2025
Signed off — Alteration
Installation of non load bearing partitions as per plans filed herewith. No change in use egress or occupancy.
M00754057-I1
02/19/2025
Signed off — Alteration
Scope to include new ground floor storefront at southeast corner (Hunson & Vandam Streets), exterior demotion at associated area, and new awning at 30- 10 wide, 12 - 11 above sidewalk, and projecting 5 from the building line.
M00725600-I1
02/12/2025
Filed — Alteration
Modification to existing sprinkler system and plumbing fixtures as per plans filed herewith.
M00772210-P5
02/12/2025
Signed off — Alteration
New MEP shafts, modifications of existing shafts, column reinforcing, exterior roof MEP support structure modifications and additions.
M00768102-I1
02/12/2025
Permit issued — Sprinklers
M00734071-I1-EW-SP
Latest 60 of 300 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DIVCOWEST2909/13/2026
DWF VI 325 HUDSON1009/01/2026
DIVCO WEST REAL ESTATE SERVICES15107/08/2026
JAMESTOWN2707/08/2026
CEPRINE CONSTRUCTION1107/08/2026
JAMESTOWN 325 HUDSON, L.P.2703/22/2026
CEBNTRY 21 DEPT STORE103/22/2026
CENTURY 21 DEPT STORE103/22/2026
CENTURY 21 DEPARTMENT103/22/2026
QUTRON SYSTEMS INC.103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/20/2021$134.1M—JAMESTOWN 325 HUDSON, L.P. → DWF VI 325 HUDSON, LLC$692/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PAE NEW YORK ENGINEERS108/26/2026
PERKINS and WILL1205/08/2026
MG ENGINEERING D.P.C.201/23/2026
JAROS BAUM & BOLLES5012/30/2025
CHARLES B BREEN112/28/2025
JAMES H. FAHEY210/17/2024
SURFACE DESIGN210/11/2024
VOCON612/26/2023
PAUL PERDEK, PROF. ENG. PLLC909/29/2023
PATUXENT ENGINEERING LLC309/12/2023
LEON SKVIRSKY PE208/25/2023
MOED DE ARMAS & SHANNON210/27/2022
MCNAMARA SALVIA507/07/2022
RYAN SOAMES ENGINEERING607/17/2020
KZ ENGINEERING, P.C205/24/2019
MICHAEL L. PINSKE106/26/2018
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PAVARINI MCGOVERN LLCGeneral Contractor4407/08/2026
ROCKLEDGE SCAFFOLD CORPGeneral Contractor2107/08/2026
TRISTATE PLBG SVCS CORPPlumbing1207/08/2026
PEAK FIRE PROTECTION LLCFire Protection807/08/2026
CEPRINE CONSTRUCTION INCGeneral Contractor807/08/2026
TRISTATE PLBG SVCS CORPFire Protection607/08/2026
CHESTER STRUGATSElectrical403/21/2026
UNISPACE OF BOSTON LLCGeneral Contractor407/08/2026
ASCO SPRINKLER CO.,INCFire Protection407/08/2026
DLM CONTRACTORS INCGeneral Contractor307/08/2026
TITAN CONSTRUCTION SERVICGeneral Contractor303/21/2026
JULIAN SPRINKLER CORPFire Protection207/08/2026
MICHAEL LIGUORIElectrical203/21/2026
ACTIVE SIGNSScaffold207/08/2026
RC3 ELECTRIC, LLCGeneral Contractor207/08/2026
A&A PLUMBING CORPPlumbing107/08/2026
INNOVATIVE HEATING SOLUTIPlumbing107/08/2026
BRESLAW MARCGeneral Contractor103/21/2026
BIGMAN BROS., INC.Electrical103/22/2026
FERNANDEZ, WILLIAMElectrical103/21/2026
HEMNAUTH, SUDESHElectrical103/21/2026
JOSEPH DUGGANElectrical103/21/2026
MATRONE ANTHONYElectrical103/21/2026
WALTON, MARCElectrical103/21/2026
ALLSTATE SPRINKLER LLCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MILROSE CONSULTANTS LLC2003108/26/2026
ATLAS ATC ENGINEERING INC80115705/08/2026
MEP INSPECTIONS, INC1102201/23/2026
CROSSCHECK INSPECTION SER544112/28/2025
ATLANTIC ENGINEERINGLABOR13812702/12/2025
SURFACE DESIGN PROFESSION3968210/11/2024
DOMANI INSPECTION SERVICE843308/28/2023
ALAN D MARCUS, PE1761207/17/2020
BECKER ENGINEERING, PC633207/16/2020
STRUCTURAL CONSULTING SER1919104/03/2020
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedCLEARESULT CONSULTING INC08/31/2026
DOB NOWSprinklersSigned-offWHITESTONE PLUMBING CORP06/01/2026
DOB NOWAntennaPermit IssuedRC3 ELECTRIC, LLC05/04/2026
DOB NOWSprinklersSigned-offMORA FIRE PROTECTION LLC02/04/2026
DOB NOWMechanical SystemsSigned-offCLUNE CONSTRUCTION CO LP01/29/2026
DOB NOWPlumbingSigned-offTRISTATE PLBG SVCS CORP01/06/2026
DOB NOWMechanical SystemsPermit IssuedTISHMAN INTERIORS CORP12/31/2025
DOB NOWAntennaPermit IssuedRC3 ELECTRIC, LLC05/29/2025
DOB NOWSprinklersSigned-offTRISTATE PLBG SVCS CORP02/12/2025
DOB NOWSuspended ScaffoldPermit IssuedTITAN CONST SERVICES LLC05/13/2024
DOB NOWSupported ScaffoldSigned-offROCKLEDGE SCAFFOLD CORP04/19/2024
DOB NOWStandpipeSigned-offTRISTATE PLBG SVCS CORP01/29/2024
DOB NOWSuspended ScaffoldPermit IssuedTITAN CONST SERVICES LLC01/04/2024
DOB NOWPlumbingSigned-offTRISTATE PLBG SVCS CORP12/27/2023
DOB NOWPlumbingSigned-offTRISTATE PLBG SVCS CORP12/26/2023
DOB NOWSprinklersSigned-offTRISTATE PLBG SVCS CORP12/26/2023
DOB NOWSupported ScaffoldSigned-offROCKLEDGE SCAFFOLD CORP12/26/2023
DOB NOWSprinklersSigned-offTRISTATE PLBG SVCS CORP12/26/2023
DOB NOWSprinklersSigned-offTRISTATE PLBG SVCS CORP12/26/2023
DOB NOWStructuralSigned-offPAVARINI MCGOVERN LLC10/30/2023
DOB NOWStructuralSigned-offPAVARINI MCGOVERN LLC10/30/2023
DOB NOWStructuralSigned-offPAVARINI MCGOVERN LLC10/30/2023
DOB NOWGeneral ConstructionSigned-offTITAN CONSTRUCTION SERVIC10/11/2023
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP10/10/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedROCKLEDGE SCAFFOLD CORP10/02/2023
DOB NOWSignSigned-offACTIVE SIGNS INC10/02/2023
DOB NOWSignSigned-offACTIVE SIGNS INC10/02/2023
DOB NOWSprinklersSigned-offTRISTATE PLBG SVCS CORP10/02/2023
DOB NOWMechanical SystemsSigned-offPAVARINI MCGOVERN LLC09/29/2023
DOB NOWGeneral ConstructionSigned-offPAVARINI MCGOVERN LLC09/29/2023
DOB NOWMechanical SystemsSigned-offPAVARINI MCGOVERN LLC09/29/2023
DOB NOWGeneral ConstructionSigned-offPAVARINI MCGOVERN LLC09/29/2023
DOB NOWSprinklersSigned-offPEAK FIRE PROTECTION LLC09/28/2023
DOB NOWGeneral ConstructionSigned-offPAVARINI MCGOVERN LLC09/28/2023
DOB NOWSprinklersSigned-offPEAK FIRE PROTECTION LLC09/28/2023
DOB NOWMechanical SystemsSigned-offPAVARINI MCGOVERN LLC09/28/2023
DOB NOWSidewalk ShedSigned-offROCKLEDGE SCAFFOLD CORP09/25/2023
DOB NOWConstruction FencePermit IssuedROCKLEDGE SCAFFOLD CORP09/25/2023
DOB NOWPlumbingSigned-offTRISTATE PLBG SVCS CORP08/30/2023
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP08/30/2023
+ 60 more permits on file
▾Field Inspections (DOB CAP) — 46
DateTypeResultReport
02/27/2026Pass-Final CND-Occupancy InspectionPassView ↗
01/13/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/23/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/27/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/16/2024Fail-Final SP - Up to 3 Requested FloorsFailView ↗
10/16/2024Pass-Final SD - Up to 3 Requested FloorsPassView ↗
10/16/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
09/30/2024Fail-Final SP - Up to 3 Requested FloorsFailView ↗
09/30/2024Pass-Final SD - Up to 3 Requested FloorsPassView ↗
09/30/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
05/06/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/06/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/06/2024Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
03/11/2024Fail-Final SP - Up to 3 Requested FloorsFailView ↗
03/11/2024Pass-Final SP - Up to 3 Requested FloorsPassView ↗
02/23/2024Fail-Final CND-Occupancy InspectionFailView ↗
01/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/24/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/24/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/24/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/24/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/12/2023Pass-Final Boiler Equipment InspectionPassView ↗
11/06/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/10/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/06/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
Latest 25 of 46.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
07/26/2026HVAC-R and service water piping design and insulationBenjamin Plotnickenergy_progress
07/26/2026Mechanical SystemsBenjamin Plotnickspecial
07/26/2026Energy Code Compliance InspectionsBenjamin Plotnickprogress
07/26/2026HVAC-R and service water heating system controlsBenjamin Plotnickenergy_progress
07/26/2026Maintenance informationBenjamin Plotnickenergy_progress
07/26/2026FinalBenjamin Plotnickprogress
07/26/2026HVAC-R and service water heating equipmentBenjamin Plotnickenergy_progress
03/17/2026Sprayed fire-resistant materialsGIORGI KHARDZEISHVILIspecial
03/17/2026Fire-Resistant Penetrations and JointsGIORGI KHARDZEISHVILIspecial
01/16/2026Fire-Resistant Penetrations and JointsNicolas Crosettospecial
01/16/2026Post-installed AnchorsNicolas Crosettospecial
01/16/2026Sprinkler SystemsNicolas Crosettospecial
12/18/2025Mechanical SystemsEUGENE BIFULCOspecial
12/18/2025Maintenance informationEUGENE BIFULCOenergy_progress
12/18/2025FinalEUGENE BIFULCOprogress
12/18/2025HVAC-R and service water heating system controlsEUGENE BIFULCOenergy_progress
12/18/2025HVAC-R and service water piping design and insulationEUGENE BIFULCOenergy_progress
01/10/2025Standpipe SystemsGIORGI KHARDZEISHVILIspecial
01/10/2025Sprinkler SystemsGIORGI KHARDZEISHVILIspecial
01/10/2025Post-installed AnchorsGIORGI KHARDZEISHVILIspecial
11/29/2024Energy Code Compliance InspectionsBenson Gillespieprogress
11/29/2024FinalBenson Gillespieprogress
11/29/2024MasonryMOLLY FORRspecial
11/29/2024Post-installed AnchorsMOLLY FORRspecial
11/29/2024Air barrier - visual inspectionBenson Gillespieenergy_progress
Latest 25 of 150.
▾Documents — 1,658 on file (BIS + DOB NOW)
▸Plans & Drawings108
▸DOB NOWPlans/Sketch98
09/03/2026M00624412-I1Contact architect ↗
09/03/2026M00624474-I1Contact architect ↗
09/03/2026M00624436-I1Contact architect ↗
Showing 3 of 98 on file for this type
▸DOB NOWPlans/Sketch - Antenna2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/05/2026M00260081-I1Contact architect ↗
09/04/2026M00361503-I1Contact architect ↗
▸DOB NOWPlans/Sketch - Sprinkler2
09/05/2026M00260098-I1Contact architect ↗
09/04/2026M00361514-I1Contact architect ↗
▸DOB NOWPlans/Sketch - Plumbing2
09/05/2026M00260094-I1Contact architect ↗
09/04/2026M00361512-I1Contact architect ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00164001-I1Contact architect ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/05/2026M00164010-I1Contact architect ↗
▸Applications & Permits241
▸BISPLAN / WORK APPROVAL APPLICATION153
02/12/2026103743736Open ↗
02/11/2026103743736Open ↗
02/06/2026103743736Open ↗
Showing 3 of 153 on file for this type
▸BISWORK PERMIT APPLICATION88
07/27/2020123704857Open ↗
07/14/2020140923179Open ↗
12/20/2019123868519Open ↗
Showing 3 of 88 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWFlood Zone Compliance2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWFlood Zone Design Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications514
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION136
12/30/2019123809076Open ↗
12/30/2019123809076Open ↗
12/20/2019123868519Open ↗
Showing 3 of 136 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature107
09/04/2026M00361514-I1Open ↗
09/04/2026M00361512-I1Open ↗
09/04/2026M00361503-I1Open ↗
Showing 3 of 107 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature87
09/29/2026M00833817-P2Open ↗
09/29/2026M00833817-P2Open ↗
09/23/2026M01336917-I1Open ↗
Showing 3 of 87 on file for this type
▸DOB NOWProgress Inspector Seal & Signature77
09/23/2026M00164010-I1Open ↗
09/23/2026M01336917-I1Open ↗
09/23/2026M01436429-I1Open ↗
Showing 3 of 77 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST43
10/27/2020123718325Open ↗
10/11/2020123718325Open ↗
12/20/2019123868519Open ↗
Showing 3 of 43 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT33
07/09/2020140923179Open ↗
12/20/2019123868519Open ↗
07/05/2019123822337Open ↗
Showing 3 of 33 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
07/09/2020140923179Open ↗
Showing 1 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
07/09/2020140923179Open ↗
Showing 1 of 3 on file for this type
▸BISProfessional and Owner Certification (POC3)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISApplicant / Owner Signature1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment120
▸BISSELF-CERT PLUMBING NOTICE29
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 29 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE21
07/05/2019123822337Open ↗
Showing 1 of 21 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT14
03/09/2021123718325Open ↗
03/02/2021123718325Open ↗
Showing 2 of 14 on file for this type
▸BISSCHEDULE B - PLUMBING13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISEQUIPMENT USE PERMITS12
03/09/2021123718325Open ↗
03/09/2021123718325Open ↗
03/09/2021123718325Open ↗
Showing 3 of 12 on file for this type
▸BISSPRINKLER INSP REPORT : FP-856
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISFIRE PROTECTION PLAN(FPP): FDNY APPROVAL2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos153
▸DOB NOWDEP ACP-5: Asbestos Assessment Report87
09/04/2026M00361514-I1Open ↗
09/04/2026M00361512-I1Open ↗
09/04/2026M00361503-I1Open ↗
Showing 3 of 87 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)34
07/09/2020140923179Open ↗
12/20/2019123868519Open ↗
07/05/2019123822337Open ↗
Showing 3 of 34 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'23
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 23 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
09/03/2026M00624412-I1Open ↗
08/29/2026M00883628-I1Open ↗
Showing 2 of 3 on file for this type
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance81
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS36
12/20/2019123868519Open ↗
12/20/2019123868519Open ↗
12/03/2019123822337Open ↗
Showing 3 of 36 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY14
07/01/2021122547226Open ↗
07/01/2021122547226Open ↗
03/16/2021122547226Open ↗
Showing 3 of 14 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS14
07/01/2021122547226Open ↗
07/01/2021122547226Open ↗
03/02/2021123718325Open ↗
Showing 3 of 14 on file for this type
▸BISTR8: Energy Code Progress Inspections5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWEN2: As Built Energy Analysis4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
07/09/2020140923179Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports21
▸BISTECHNICAL REPORT: RESPONSIBILITY18
07/01/2021122547226Open ↗
07/01/2021122547226Open ↗
03/16/2021122547226Open ↗
Showing 3 of 18 on file for this type
▸BISTECHNICAL REPORT: SOIL INSPECTION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs125
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST70
07/01/2021122547226Open ↗
05/13/2021122969305Open ↗
03/02/2021123718325Open ↗
Showing 3 of 70 on file for this type
▸BISADMINISTRATIVE OBJECTIONS26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 26 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE19
01/30/2026103743736Open ↗
09/12/2024103743736Open ↗
09/11/2024103743736Open ↗
Showing 3 of 19 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSUPERSEDING LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP Variance (V5) letter1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Cost, Insurance & Ownership124
▸BISCOST AFFIDAVIT124
07/01/2021122547226Open ↗
07/01/2021122547226Open ↗
05/13/2021122969305Open ↗
Showing 3 of 124 on file for this type
▸Filing & Intake Forms141
▸BISEFILING COVER SHEET74
12/20/2019123868519Open ↗
07/05/2019123822337Open ↗
07/05/2019123822337Open ↗
Showing 3 of 74 on file for this type
▸BISBOROUGH INTAKE FORM39
07/27/2020123704857Open ↗
02/21/2020103743736Open ↗
02/14/2020103743736Open ↗
Showing 3 of 39 on file for this type
▸BISADDITIONAL INFORMATION24
02/12/2026103743736Open ↗
02/06/2026103743736Open ↗
03/14/2024103743736Open ↗
Showing 3 of 24 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
07/09/2020140923179Open ↗
Showing 1 of 4 on file for this type
▸Other Documents19
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWProperty Ownership Certification5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWFlood Hazard Area Substantial Improvement Calculation3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSupporting Document: Fee Exempt1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWCalculations1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWLowest Floor Elevation Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWManufacturer's Specifications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type