← Back
Other private school
Rainbowland Nursery School
33-11 77 STREET · Name © OpenStreetMap contributors · BIN 4028769
💬 Discuss this project
1930Year Built
2Stories
W8Building Class
R7-1Zoning
2,118 sfGross Floor Area
1Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
Other private school · Owner of record: 3311 77ST LLC · 3,152 sf lot · 0.67 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 26p · 2 filings · 20 docs
Floor 15p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JHELC2107/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STAVROS I. MALLIAROS, P.E., P.C.806/05/2026
IMA ENGINEERING, PC203/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
IMA ENGINEERING1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RR & VH PROPERTIES LTDGeneral Contractor303/21/2026
ROLAND MECHANICAL OF NY*General Contractor107/08/2026
BYPASS MECHANICAL CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519806/05/2026
Building Lifecycle
All (70)Filed (10)Permit Issued (3)Signed Off (1)Violation (2)Inspection (12)Objection (14)Special Inspection (28)
06/05/2026
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P8
06/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
06/02/2026
Special inspection requirement — Preliminary
Younes Abouyaala
06/02/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
06/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
05/13/2026
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P7
05/12/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
05/12/2026
Special inspection requirement — Preliminary
Younes Abouyaala
05/12/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
05/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/08/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/15/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/10/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/06/2026
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P5
02/05/2026
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
02/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
02/05/2026
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
02/05/2026
Special inspection requirement — Preliminary
Younes Abouyaala
12/26/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/03/2025
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P4
10/03/2025
Special inspection requirement — Preliminary
Younes Abouyaala
10/03/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
08/11/2025
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P3
06/23/2025
Special inspection requirement — Preliminary
Younes Abouyaala
06/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
06/23/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
06/23/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
05/22/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/11/2025
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P2
04/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
04/02/2025
Special inspection requirement — Preliminary
Younes Abouyaala
04/02/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
04/02/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
03/21/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/21/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/18/2025
Signed off — Alteration
REPLACE EXISTING FIXTURES, RELOCATE BATHROOM FIXTURE FOR ADA COMPLIANCE AND ADD ONE DRINKING FOUNTAIN
Q00992845-I1
03/18/2025
Permit issued — General Construction
Q00839992-I1-GC
03/14/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/06/2025
Filed — Alteration
REPLACE EXISTING FIXTURES, RELOCATE BATHROOM FIXTURE FOR ADA COMPLIANCE AND ADD ONE DRINKING FOUNTAIN
Q00992845-P1
03/04/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/08/2024
Filed — Alteration CO
CONVERT EXISTING HOUSE OF WORSHIP SPACE @ FIRST FLOOR INTO DAYCARE
Q00839992-P1
10/08/2024
Special inspection requirement — Preliminary
Younes Abouyaala
10/08/2024
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
10/08/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/08/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/20/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
09/11/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
09/10/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/04/2024
Permit issued — Plumbing
Q00992845-I1-PL
08/29/2024
Permit issued — General Construction
Q00839992-I1-GC
08/02/2024
Filed — Alteration
REPLACE EXISTING FIXTURES, RELOCATE BATHROOM FIXTURE FOR ADA COMPLIANCE AND ADD ONE DRINKING FOUNTAIN
Q00992845-I1
04/24/2023
Objection raised — Scope
04/24/2023
Objection resolved — Addressed
04/24/2023
Objection raised — Accessibility
04/24/2023
Objection resolved — Addressed
04/24/2023
Objection raised — Accessibility
04/24/2023
Objection resolved — Addressed
04/24/2023
Objection raised — Energy
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedRR & VH PROPERTIES LTD03/18/2025
DOB NOWPlumbingSigned-offBYPASS MECHANICAL CORP09/04/2024
DOB NOWGeneral ConstructionPermit IssuedROLAND MECHANICAL OF NY*08/29/2024
BISOTISSUEDN/A10/04/1996
BIS—ISSUEDWORLDCO CONST.CO03/31/1994
1 project · most recent 05/22/2025
FiledStatusContractorScope
05/22/2025CompleteTACTICAL ELECTRIC INC—
1 project · most recent 06/05/2026
FiledStatusContractorScope
06/05/2026Permit IssuedRR & VH PROPERTIES LTD1 scope_items
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
05/08/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/15/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/10/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/26/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/22/2025Pass-Final CND-Occupancy InspectionPassView ↗
03/21/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/14/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/04/2025Pass-Final CND-Occupancy InspectionPassView ↗
09/20/2024Fail-Final CND-Occupancy InspectionFailView ↗
09/11/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/10/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
06/02/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
06/02/2026PreliminaryYounes Abouyaalaprogress
06/02/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
06/02/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
05/12/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
05/12/2026PreliminaryYounes Abouyaalaprogress
05/12/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
05/12/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
02/05/2026Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
02/05/2026Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
02/05/2026Energy Code Compliance InspectionsYounes Abouyaalaprogress
02/05/2026PreliminaryYounes Abouyaalaprogress
10/03/2025PreliminaryYounes Abouyaalaprogress
10/03/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
10/03/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
10/03/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
06/23/2025PreliminaryYounes Abouyaalaprogress
06/23/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
06/23/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
06/23/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
04/02/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
04/02/2025PreliminaryYounes Abouyaalaprogress
04/02/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
04/02/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/08/2024PreliminaryYounes Abouyaalaprogress
Latest 25 of 28.
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/20/2026Q00992845-I1Request digital key ↗
08/20/2026Q00992845-P1Request digital key ↗
08/16/2026Q00839992-P7Request digital key ↗
Showing 3 of 10 on file for this type
▸Seals & Professional Certifications25
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/20/2026Q00992845-I1Open ↗
08/20/2026Q00992845-P1Open ↗
08/16/2026Q00839992-P8Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
08/31/2026Q00839992-P1Open ↗
08/31/2026Q00839992-P8Open ↗
08/26/2026Q00839992-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
08/31/2026Q00839992-P1Open ↗
08/31/2026Q00839992-P8Open ↗
08/26/2026Q00839992-P2Open ↗
Showing 3 of 7 on file for this type
▸Safety & Tenant Protection9
▸DOB NOWStreet Tree Checklist8
08/16/2026Q00839992-P8Open ↗
08/16/2026Q00839992-P7Open ↗
08/13/2026Q00839992-P3Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q00839992-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report10
08/20/2026Q00992845-I1Open ↗
08/20/2026Q00992845-P1Open ↗
08/16/2026Q00839992-P8Open ↗
Showing 3 of 10 on file for this type
▸Other Documents8
▸DOB NOWProperty Ownership Certification8
08/16/2026Q00839992-P8Open ↗
08/16/2026Q00839992-P7Open ↗
08/13/2026Q00839992-P2Open ↗
Showing 3 of 8 on file for this type