| Owner | Filings | Most Recent |
|---|---|---|
| DAYTON TOWERS | 5 | 04/12/2026 |
| PHOENIX SUTTON STR INC | 5 | 03/22/2026 |
| QUEENSVIEW | 20 | 03/22/2026 |
| QUEENVIEW | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| COWLEY ENGINEERING, PC | 1 | 05/30/2025 |
| ENTHINK ENGINEERS LLC | 3 | 02/23/2023 |
| MERRITT ENGINEERING CONSULTANTS, DPC | 1 | 02/14/2023 |
| HOWARD L ZIMMERMAN ARCH & ENG DPC | 1 | 01/06/2021 |
| ROYAL ENGINEERING, P.C | 1 | 08/03/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| MERRITT ENGINEERING CONSULTANT DPC | 2 | 03/21/2026 |
| NYPL | 1 | 03/21/2026 |
| THERESA VOLTAGGIO | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EXO INDUSTRIES CORP | General Contractor | 5 | 07/08/2026 |
| MNR GROUP INC | General Contractor | 2 | 03/21/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BUILDING CONSULTING ENGIN | 1034 | 2 | 05/30/2025 |
| COWLEY ENGINEERING | 186 | 1 | 05/30/2025 |
| MERRITT ENGINEERING CONSU | 460 | 1 | 02/14/2023 |
| HOWARD L ZIMMERMAN ARCHIT | 1712 | 1 | 01/06/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Signed-off | SSD INTERIOR INC | 06/17/2025 |
| DOB NOW | General Construction | Permit Issued | MNR GROUP INC | 06/17/2025 |
| DOB NOW | General Construction | Signed-off | EXO INDUSTRIES CORP | 04/14/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | EXO INDUSTRIES CORP | 01/20/2023 |
| DOB NOW | Construction Fence | Signed-off | EXO INDUSTRIES CORP | 01/20/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | PHOENIX SUTTON STR INC | 08/07/2019 |
| BIS | OT | ISSUED | QUEENSVIEW INC. | 04/07/2021 |
| BIS | OT | ISSUED | AVARGA CONTRACTING CORP | 01/08/2020 |
| BIS | OT | ISSUED | EBRO CONSTRUCTION | 02/12/2008 |
| BIS | EQ | ISSUED | EBRO RESTORATION CORP | 02/10/2008 |
| BIS | OT | ISSUED | EBRO CONSTRUCTION | 05/29/2007 |
| BIS | EQ | ISSUED | STEEL INDUSTRIES | 05/29/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2021 | — | — | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/20/2023 | Complete | RICHARD NEU | — |
| 01/10/2023 | Complete | K & R ELECTRIC CO., INC. | General Wiring |
| 07/31/2019 | Permit Issued | ELPO ELECTRICAL CONTG INC | — |
| 03/11/2018 | Permit Issued | NEE ELECTRICAL, LLC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/20/2025 | Final | Eric Cowley | progress |
| 05/20/2025 | Masonry | Eric Cowley | special |
| 05/20/2025 | Post-installed Anchors | Eric Cowley | special |
| 05/20/2025 | Structural Stability – Alterations of existing buildings | Eric Cowley | special |
| 05/20/2025 | Tenant Protection Plan Compliance | TONY ONYEAGORO | special |
| 05/20/2025 | Wall Panels, Curtain Walls, and Veneers | Eric Cowley | special |
| 12/15/2022 | Energy Code Compliance Inspections | Christopher Krepcio | progress |
| 12/15/2022 | Air barrier - visual inspection | Christopher Krepcio | energy_progress |
| 12/15/2022 | Insulation placement and R values | Christopher Krepcio | energy_progress |
| 12/15/2022 | Masonry | Christopher Krepcio | special |
| 12/15/2022 | Construction Operations Influencing Adjacent Structures | TONY ONYEAGORO | special |
| 12/15/2022 | Structural Stability – Alterations of existing buildings | Christopher Krepcio | special |
| 12/15/2022 | Tenant Protection Plan Compliance | TONY ONYEAGORO | special |
| 12/15/2022 | Final | Christopher Krepcio | progress |
| 01/06/2021 | Fire-Resistant Penetrations and Joints | Jon Colatrella | special |
| 08/03/2019 | Final | BRIAN T. O'CONNOR | progress |