← Back
Two stories - detached, small or mid-size
33-61 167 STREET
QUEENS · BIN 4118806
💬 Discuss this project
1935Year Built
2.5Stories
A1Building Class
R2AZoning
2,490 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · Owner of record: GAO ZHANG TRUST · 6,000 sf lot · 0.42 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof2p · 1 filing · 7 docs
Floor 21p · 1 filing · 7 docs
Floor 1
Cellar2p · 1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/16/2022$1.4M—Private party → Private party$542/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FANG ARCHITECT104/27/2026
Building Lifecycle
All (41)Filed (1)Objection (17)Special Inspection (23)
06/30/2026
Objection raised — Fire_Protection
06/30/2026
Objection raised — Zoning
06/30/2026
Objection raised — Scope
06/30/2026
Objection raised — Admin
06/30/2026
Objection resolved — Addressed
06/30/2026
Objection raised — Structural
06/30/2026
Objection raised — Scope
06/30/2026
Objection raised — Scope
06/30/2026
Objection raised — Other
06/30/2026
Objection raised — Zoning
06/30/2026
Objection raised — Zoning
06/30/2026
Objection raised — Fire_Protection
06/30/2026
Objection raised — Mechanical
06/30/2026
Objection raised — Fire_Protection
06/30/2026
Objection raised — Fire_Protection
06/30/2026
Objection raised — Inspections
06/30/2026
Objection raised — Energy
04/27/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
FILED HORIZONTAL & VERTICAL EXTENSION TO EXISTING BUILDING AND CONVERT TO 1-FAMILY WITH ANCILLARY DWELLING UNIT. THE ADU IS LOCATED WITHIN THE PRIMARY DWELLING ON THE 1ST FLOOR.
Q01389279-I1
04/24/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
04/24/2026
Special inspection requirement — Maintenance information
04/24/2026
Special inspection requirement — Electric vehicle service equipment requirements
04/24/2026
Special inspection requirement — Masonry
04/24/2026
Special inspection requirement — Concrete - Cast-In-Place
04/21/2026
Special inspection requirement — Structural Wood Frame
04/21/2026
Special inspection requirement — Air barrier — testing
04/21/2026
Special inspection requirement — Protection of exposed foundation insulation
04/21/2026
Special inspection requirement — Interior lighting power
04/21/2026
Special inspection requirement — Air barrier - visual inspection
04/21/2026
Special inspection requirement — Insulation placement and R values
04/21/2026
Special inspection requirement — Structural Steel - Details
04/21/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/21/2026
Special inspection requirement — Energy Code Compliance Inspections
04/21/2026
Special inspection requirement — Fire-Resistance Rated Construction
04/21/2026
Special inspection requirement — Fenestration areas
04/21/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
04/21/2026
Special inspection requirement — Metering
04/21/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
04/21/2026
Special inspection requirement — Fenestration air leakage
04/21/2026
Special inspection requirement — Permanent certificate
04/17/2026
Special inspection requirement — Footing and Foundation
04/17/2026
Special inspection requirement — Final
Nothing on file for this building.
1 project · most recent 04/27/2026
Steel Wood
FiledStatusContractorScope
04/27/2026——Steel, Wood
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
04/24/2026Excavations - Sheeting, Shoring, and Bracing—special
04/24/2026Maintenance information—energy_progress
04/24/2026Electric vehicle service equipment requirements—energy_progress
04/24/2026Masonry—special
04/24/2026Concrete - Cast-In-Place—special
04/21/2026Structural Wood Frame—progress
04/21/2026Air barrier — testing —energy_progress
04/21/2026Protection of exposed foundation insulation—energy_progress
04/21/2026Interior lighting power—energy_progress
04/21/2026Air barrier - visual inspection—energy_progress
04/21/2026Insulation placement and R values—energy_progress
04/21/2026Structural Steel - Details—special
04/21/2026Fire-Resistant Penetrations and Joints—special
04/21/2026Energy Code Compliance Inspections—progress
04/21/2026Fire-Resistance Rated Construction—progress
04/21/2026Fenestration areas—energy_progress
04/21/2026Structural Stability – Alterations of existing buildings—special
04/21/2026Metering—energy_progress
04/21/2026Fenestration and door U-factor and product ratings—energy_progress
04/21/2026Fenestration air leakage—energy_progress
04/21/2026Permanent certificate—energy_progress
04/17/2026Footing and Foundation—progress
04/17/2026Final—progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/15/2026Q01389279-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026Q01389279-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q01389279-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026Q01389279-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026Q01389279-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026Q01389279-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/15/2026Q01389279-I1Open ↗