← Back
Elevator co-op, conversion from loft/warehouse
33 BLEECKER STREET
MANHATTAN · BIN 1008449
💬 Discuss this project
1884Year Built
6Stories
D0Building Class
M1-5/R7XZoning
25,132 sfGross Floor Area
13Units
LL97 CoveredRent Stabilized0 Open ViolationsFDNY Report ↗
Elevator co-op, conversion from loft/warehouse · Owner of record: 33 BLECKER STREET CORP · 5,438 sf lot · 4.62 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Roof3p · 3 filings · 20 docs
Floor 41p · 1 filing · 6 docs
Floor 39p · 4 filings · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 1Under Construction6p · 1 filing · 15 docs
Cellar1p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MISRA GROUP5409/13/2026
33 BLECKER STREET CORP5603/22/2026
OWNER OF 33 BLEEKER STREE103/22/2026
33 BLEECKER ST OWNER S CO103/22/2026
CHAPTER103/22/2026
NEW VISION ENTERPRISES403/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LLOYD NOEL BUILDING CONSULTANT1303/21/2026
JENNY FLORES EXPEDITING303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LOYAL GENERAL CONTRACTINGGeneral Contractor707/08/2026
SABI CONSTRUCTION USA INCGeneral Contractor307/08/2026
TJS NY INCGeneral Contractor303/21/2026
T.S.M. MECHANICAL CORPGeneral Contractor208/12/2026
LEARDON BOILER WORKS INCGeneral Contractor203/21/2026
ALL VISION GENERAL CONST*General Contractor107/08/2026
HELLO CHAPTER LLCGeneral Contractor104/09/2026
FIU CORP DBA FIU ELECTRICElectrical103/22/2026
HORBRIDGE PLUMBING & HEATINGPlumbing107/08/2026
GOTHAM WIRING LICENSEDElectrical103/22/2026
RODRIGUEZ, MAYDAElectrical103/21/2026
SCHONDORF MICHAELElectrical103/21/2026
EXPERT FIRE SPRINKLER,LLCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK CONSULTING SERVICES, I6198106/15/2026
WD ENGINEERING PLLC9204106/15/2026
TECC DESIGNS AND SOLUTION7184105/29/2026
AZA ENGINEERING LLC7235103/17/2026
RYAN SPECIAL ENGINEERING2018303/12/2026
REFORM ARCHITECTURE PLLC9444303/02/2026
MISRA & ASSOCIATES, P.C.3265501/08/2024
AUTOMATED DESIGN CONSULTA895105/18/2023
BAZINI ENGINEERING, P.C.1808111/05/2020
Building Lifecycle
All (124)Filed (21)Permit Issued (14)Signed Off (8)Violation (34)Inspection (5)Objection (12)Special Inspection (30)
08/11/2026
Permit issued — Mechanical Systems
M01406172-I1-MS
07/14/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
06/30/2026
Objection resolved — Addressed
06/26/2026
Permit issued — Structural
M01370799-S1-ST
06/15/2026
Filed — Alteration
Installation of new Mechanical system for ground level retail space. No change of use, egress or occupancy.
M01370799-S1
06/15/2026
Objection resolved — Addressed
06/11/2026
Special inspection requirement — Tenant Protection Plan Compliance
WALIUR RAHMAN
06/10/2026
Permit issued — Mechanical Systems
M01370799-I1-MS
06/10/2026
Special inspection requirement — Final
William DiMitri
06/10/2026
Special inspection requirement — Structural Steel - Details
William DiMitri
06/09/2026
Objection raised — Cost
06/09/2026
Objection raised — Scope
05/29/2026
Filed — Alteration
MECHANICAL SYSTEM INSTALLATION FOR PROPOSED BUILDING APARTMENT UNIT AS PER PER PLANS HERE WITHIN. NO CHANGE IN EGRESS, USE OR OCCUPANCY.
M01406172-I1
05/29/2026
Special inspection requirement — HVAC-R and service water heating system controls
ARTHUR NISONOV
05/29/2026
Special inspection requirement — HVAC-R and service water heating equipment
ARTHUR NISONOV
05/29/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
ARTHUR NISONOV
05/29/2026
Special inspection requirement — Maintenance information
ARTHUR NISONOV
05/28/2026
Permit issued — Mechanical Systems
M01370799-I1-MS
05/21/2026
Special inspection requirement — Mechanical Systems
ARTHUR NISONOV
05/21/2026
Special inspection requirement — Final
ARTHUR NISONOV
04/29/2026
Violation issued (HPD, closed)
A
04/08/2026
Objection raised — Inspections
04/08/2026
Objection raised — Other
04/08/2026
Objection raised — Cost
04/08/2026
Objection raised — Inspections
03/23/2026
Signed off — Alteration
HEREBY FILING FOR THE RENOVATION OF UNIT 4A. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01151867-S1
03/23/2026
Signed off — Alteration
HEREBY FILING FOR THE RENOVATION OF UNIT 4A. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01151867-I1
03/17/2026
Filed — Alteration
Installation of new Mechanical system for ground level retail space. No change of use, egress or occupancy.
M01370799-I1
03/12/2026
Filed — Alteration
RELOCATE EXISTING AIR COOLED HEAT PUMP CONDENSING UNIT FROM APT # 3C WINDOW TO EXISTING DUNNAGE AT ROOF. PROVIDE NEW REFRIGERANT PIPING, DISCONNECT, ETC.
M01369153-I1
03/12/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — Final
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — Energy Code Compliance Inspections
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — Tenant Protection Plan Compliance
Artem Zolotarev
03/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — HVAC-R and service water heating system controls
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — Mechanical Systems
Dionisio Cortes Ortega
03/12/2026
Special inspection requirement — HVAC-R and service water heating equipment
Dionisio Cortes Ortega
03/11/2026
Special inspection requirement — Final
Artem Zolotarev
03/11/2026
Special inspection requirement — Mechanical Systems
Artem Zolotarev
03/02/2026
Filed — Alteration
HEREBY FILING FOR THE RENOVATION OF UNIT 4A. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01151867-P1
02/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — Mechanical Systems
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — Final
Dionisio Cortes Ortega
02/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
Dionisio Cortes Ortega
01/26/2026
Permit issued — Mechanical Systems
M01151867-S1-MS
12/30/2025
Filed — Alteration
HEREBY FILING FOR THE RENOVATION OF UNIT 4A. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01151867-S1
09/25/2025
Violation issued (FDNY_NOV, closed)
06/04/2025
Violation issued (HPD, closed)
A
01/07/2025
Permit issued — General Construction
M01151867-I1-GC
12/20/2024
Objection resolved — Addressed
12/20/2024
Objection resolved — Addressed
12/12/2024
Objection raised — Other
12/12/2024
Objection raised — Other
12/06/2024
Filed — Alteration
HEREBY FILING FOR THE RENOVATION OF UNIT 4A. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01151867-I1
12/05/2024
Special inspection requirement — Final
Dionisio Cortes Ortega
12/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dionisio Cortes Ortega
12/05/2024
Special inspection requirement — Energy Code Compliance Inspections
Dionisio Cortes Ortega
Latest 60 of 124 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offT.S.M. MECHANICAL CORP08/11/2026
DOB NOWStructuralPermit IssuedSABI CONSTRUCTION USA INC06/26/2026
DOB NOWMechanical SystemsPermit IssuedSABI CONSTRUCTION USA INC06/10/2026
DOB NOWMechanical SystemsPermit IssuedSABI CONSTRUCTION USA INC05/28/2026
DOB NOWMechanical SystemsSigned-offT.S.M. MECHANICAL CORP01/26/2026
DOB NOWGeneral ConstructionSigned-offHELLO CHAPTER LLC01/07/2025
DOB NOWGeneral ConstructionSigned-offLOYAL GENERAL CONTRACTING10/08/2024
DOB NOWGeneral ConstructionSigned-offLOYAL GENERAL CONTRACTING12/05/2023
DOB NOWMechanical SystemsSigned-offALL VISION GENERAL CONST*06/16/2023
DOB NOWSprinklersSigned-offEXPERT FIRE SPRINKLER,LLC06/06/2023
DOB NOWGeneral ConstructionSigned-offLOYAL GENERAL CONTRACTING10/24/2022
DOB NOWPlumbingSigned-offHORBRIDGE PLUMBING & HEAT10/21/2022
DOB NOWGeneral ConstructionSigned-offTJS NY INC03/02/2022
DOB NOWMechanical SystemsSigned-offLEARDON BOILER WORKS INC11/05/2020
BIS—ISSUEDWASOFF PLUMBING & UTILITY CO12/09/2025
BIS—ISSUEDWASOFF PLUMBING & UTILITY CO11/15/2024
BIS—ISSUEDWASOFF PLUMBING & UTILITY CO12/18/2023
BIS—ISSUEDMANHATTAN PREMIER CONSTR10/07/2022
BISPLISSUEDRVM PLUMBING CORP03/14/2022
BIS—ISSUEDMANHATTAN PREMIER CONSTR10/26/2021
BISPLISSUEDRENEW PLUMBING CORP08/17/2021
BIS—ISSUEDMANHATTAN PREMIER CONSTR03/01/2021
BISPLISSUEDMEGA PLBG CORP05/11/2020
BISMHISSUEDMETROBUILD LLC02/11/2020
BISBLISSUEDLEARDON BOILER WORKS.INC06/25/2019
BISOTISSUEDLEARDON BOILER WORKS INC06/14/2019
BISOTISSUEDSNS ORGNIZATION LTD05/10/2019
BISPLISSUEDMEGA PLBG CORP05/06/2019
BISSPISSUEDTMS PLUMBING & HTG CORP04/15/2019
BISPLISSUEDARCH PLUMBING & HTNG CORP04/09/2019
BISOTISSUEDMETROBUILD LLC02/15/2019
BISMHISSUEDMETROBUILD LLC02/15/2019
BISMHISSUEDMETROBUILD LLC01/24/2019
BISOTISSUEDMETROBUILD LLC01/24/2019
BISOTISSUEDTJS NY INC08/09/2018
BISPLISSUEDMEGA PLBG CORP05/02/2018
BISPLISSUEDMEGA PLBG CORP05/03/2017
BISOTISSUEDBLOCK STUDIO INC05/02/2017
BISOTISSUEDBUILD AD CONTRACTING, LTD10/28/2016
BISOTISSUEDBLOCK STUDIO INC08/19/2016
+ 24 more permits on file
2 projects · most recent 06/15/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
06/15/2026Permit IssuedSABI CONSTRUCTION USA INCHeating and Air Conditioning Systems
Heat / Cool
Sigma SDSH096D2 8 tons · Fan Coil Indoor ×2
05/29/2026Signed-offT.S.M. MECHANICAL CORPHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-SM48NL 4 tons · Heat Pump Outdoor ×1
6 projects · most recent 06/21/2026
General Wiring
FiledStatusContractorScope
06/21/2026CompleteEMPIRE LIC ELECL CONTRSGeneral Wiring
02/13/2025CompleteFIU CORP DBA FIU ELECTRICGeneral Wiring
01/15/2025CompleteFIU CORP DBA FIU ELECTRIC—
04/23/2024CompleteEMPIRE LIC ELECL CONTRSGeneral Wiring
11/10/2022Permit IssuedGOTHAM WIRING LICENSEDGeneral Wiring
12/04/2019CompleteGIA ELECTRICAL CORPGeneral Wiring
1 project · most recent 06/15/2026
Steel
FiledStatusContractorScope
06/15/2026Permit IssuedSABI CONSTRUCTION USA INCSteel
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
07/14/2026Pass-Final PL - UndergroundPassView ↗
04/23/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/20/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/15/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/10/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 66
DateRequirementInspectorRole
06/11/2026Tenant Protection Plan ComplianceWALIUR RAHMANspecial
06/10/2026Structural Steel - DetailsWilliam DiMitrispecial
06/10/2026FinalWilliam DiMitriprogress
05/29/2026HVAC-R and service water piping design and insulationARTHUR NISONOVenergy_progress
05/29/2026Maintenance informationARTHUR NISONOVenergy_progress
05/29/2026HVAC-R and service water heating system controlsARTHUR NISONOVenergy_progress
05/29/2026HVAC-R and service water heating equipmentARTHUR NISONOVenergy_progress
05/21/2026FinalARTHUR NISONOVprogress
05/21/2026Mechanical SystemsARTHUR NISONOVspecial
03/12/2026Tenant Protection Plan ComplianceArtem Zolotarevspecial
03/12/2026Fire-Resistant Penetrations and JointsDionisio Cortes Ortegaspecial
03/12/2026Mechanical SystemsDionisio Cortes Ortegaspecial
03/12/2026Energy Code Compliance InspectionsDionisio Cortes Ortegaprogress
03/12/2026FinalDionisio Cortes Ortegaprogress
03/12/2026HVAC-R and service water heating system controlsDionisio Cortes Ortegaenergy_progress
03/12/2026HVAC-R and service water piping design and insulationDionisio Cortes Ortegaenergy_progress
03/12/2026HVAC-R and service water heating equipmentDionisio Cortes Ortegaenergy_progress
03/11/2026Mechanical SystemsArtem Zolotarevspecial
03/11/2026FinalArtem Zolotarevprogress
02/20/2026Fire-Resistant Penetrations and JointsDionisio Cortes Ortegaspecial
02/20/2026Energy Code Compliance InspectionsDionisio Cortes Ortegaprogress
02/20/2026FinalDionisio Cortes Ortegaprogress
02/20/2026HVAC-R and service water heating equipmentDionisio Cortes Ortegaenergy_progress
02/20/2026HVAC-R and service water piping design and insulationDionisio Cortes Ortegaenergy_progress
02/20/2026HVAC-R and service water heating system controlsDionisio Cortes Ortegaenergy_progress
Latest 25 of 66.
▾Documents — 476 on file (BIS + DOB NOW)
▸Plans & Drawings21
▸DOB NOWPlans/Sketch20
09/02/2026M00666269-I1Request digital key ↗
09/02/2026M00666269-P1Request digital key ↗
09/01/2026M08012463-P5Request digital key ↗
Showing 3 of 20 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00388550-I1Request digital key ↗
▸Applications & Permits97
▸BISWORK PERMIT APPLICATION44
12/18/2023123669654Open ↗
12/18/2023123669654Open ↗
11/02/2023123669654Open ↗
Showing 3 of 44 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION32
03/23/2022140854369Open ↗
03/21/2022140854369Open ↗
03/14/2022140854369Open ↗
Showing 3 of 32 on file for this type
▸DOB NOWLPC Approval/Permit20
09/02/2026M00666269-I1Open ↗
09/02/2026M00666269-P1Open ↗
08/18/2026M01370799-S1Open ↗
Showing 3 of 20 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
09/20/2016122867433Open ↗
▸Zoning, Tax Lot & Property Records1
▸BISZONING RESOLUTION DETERMINATION1
04/30/2019123669654Open ↗
▸Seals & Professional Certifications119
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION35
03/16/2020123592781Open ↗
03/16/2020123592781Open ↗
08/28/2019123592781Open ↗
Showing 3 of 35 on file for this type
▸DOB NOWProgress Inspector Seal & Signature33
09/27/2026M08012480-P1Open ↗
09/01/2026M01370799-I1Open ↗
09/01/2026M08012463-I1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature21
09/02/2026M00666269-I1Open ↗
09/02/2026M00666269-P1Open ↗
09/01/2026M08012480-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature19
09/01/2026M01370799-I1Open ↗
09/01/2026M01370799-I1Open ↗
09/01/2026M08012463-I1Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
06/13/2019140854369Open ↗
05/10/2019123737643Open ↗
09/20/2016122867433Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
05/10/2019123737643Open ↗
09/20/2016122867433Open ↗
Showing 2 of 3 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
06/13/2019140854369Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/13/2019140854369Open ↗
▸Trade Schedules & Equipment30
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE11
10/08/2019140854369Open ↗
09/27/2019140854369Open ↗
01/31/2019123669654Open ↗
Showing 3 of 11 on file for this type
▸BISSELF-CERT PLUMBING NOTICE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSCHEDULE B - PLUMBING5
06/13/2019140854369Open ↗
Showing 1 of 5 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BIS* BOILER (BL) SIGNOFF1
11/10/2023140854369Open ↗
▸BISPLUMBING (PL) SIGNOFF1
11/10/2023140854369Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
03/08/2021123592781Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
06/13/2019140854369Open ↗
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
11/10/2023140854369Open ↗
▸Safety & Tenant Protection10
▸BISTenant Protection Plan and Notes7
05/10/2019123737643Open ↗
01/31/2019123669654Open ↗
01/15/2019123655605Open ↗
Showing 3 of 7 on file for this type
▸BISSTREET TREE CHECKLIST1
01/31/2019123669654Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
12/11/2018123592781Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00388550-I1Open ↗
▸Environmental & Asbestos34
▸DOB NOWDEP ACP-5: Asbestos Assessment Report20
09/02/2026M00666269-I1Open ↗
09/02/2026M00666269-P1Open ↗
09/01/2026M08012480-P2Open ↗
Showing 3 of 20 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)11
06/13/2019140854369Open ↗
05/13/2019123737643Open ↗
01/31/2019123669654Open ↗
Showing 3 of 11 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Energy Compliance29
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS11
07/31/2019123737643Open ↗
07/31/2019123737643Open ↗
06/26/2017122763857Open ↗
Showing 3 of 11 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
10/31/2023140854369Open ↗
07/31/2019123737643Open ↗
06/26/2017122763857Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
11/02/2023140854369Open ↗
11/24/2021122709738Open ↗
06/13/2019140854369Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
11/10/2023140854369Open ↗
11/24/2021122709738Open ↗
▸BISENERGY CODE 1ST REVIEW COMPLETE2
04/30/2019123669654Open ↗
12/11/2018123592781Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
11/10/2023140854369Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
10/31/2023140854369Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/13/2019140854369Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY9
11/02/2023140854369Open ↗
10/31/2023140854369Open ↗
11/24/2021122709738Open ↗
Showing 3 of 9 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
11/10/2023140854369Open ↗
▸Approvals, Objections & Sign-offs45
▸BISLANDMARKS APPROVAL18
07/31/2019123737643Open ↗
06/13/2019140854369Open ↗
04/30/2019123669654Open ↗
Showing 3 of 18 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST13
11/13/2023140854369Open ↗
11/26/2021122709738Open ↗
06/03/2021123592781Open ↗
Showing 3 of 13 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISLANDMARKS SIGNOFF3
10/31/2023140854369Open ↗
11/26/2021122709738Open ↗
03/08/2021123592781Open ↗
▸BISSUPERSEDING LETTER2
12/18/2023123669654Open ↗
08/22/2018122709738Open ↗
▸BISFUEL BURNING (FB) SIGNOFF1
11/10/2023140854369Open ↗
▸BISFINAL1
11/10/2023140854369Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
03/15/2022140854369Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
01/31/2019123669654Open ↗
▸Cost, Insurance & Ownership30
▸BISCOST AFFIDAVIT27
06/01/2021123592781Open ↗
07/31/2019123737643Open ↗
06/13/2019140854369Open ↗
Showing 3 of 27 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
10/31/2023140854369Open ↗
▸BISHIC LICENSE OR AFFIDAVIT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
11/26/2021122709738Open ↗
▸Filing & Intake Forms45
▸BISADDITIONAL INFORMATION21
03/23/2022140854369Open ↗
06/01/2021123592781Open ↗
03/08/2021123592781Open ↗
Showing 3 of 21 on file for this type
▸BISEFILING COVER SHEET16
05/10/2019123737643Open ↗
01/31/2019123669654Open ↗
01/15/2019123655605Open ↗
Showing 3 of 16 on file for this type
▸BISBOROUGH INTAKE FORM6
03/01/2021123669654Open ↗
10/08/2019140854369Open ↗
09/27/2019140854369Open ↗
Showing 3 of 6 on file for this type
▸BISeFiling Job Application Cover Sheet2
06/13/2019140854369Open ↗
Showing 1 of 2 on file for this type
▸Other Documents5
▸DOB NOWProof of Historic Building2
08/13/2026M01151867-I1Open ↗
08/13/2026M01370799-I1Open ↗
▸BISPLOT DIAGRAM1
01/31/2019123669654Open ↗
▸BISCHIMNEYS AND VENTS1
11/10/2023140854369Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
03/08/2021123592781Open ↗