← Back
One story - permanent living quarter
33 MACORMAC PLACE
STATEN ISLAND · Mariner's Harbor-Arlington-Graniteville · BIN 5028591
💬 Discuss this project
1960Year Built
1Stories
A2Building Class
R3XZoning
912 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.23 FAR built · Flood zone X
Locations of Work
Electrical
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC103/24/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272103/24/2026
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
04/29/2026
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01375929-I1
03/30/2026
Permit issued — Solar
S01375929-I1-SL
03/24/2026
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01375929-I1
03/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
03/24/2026
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
03/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
03/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
03/20/2026
Special inspection requirement — Final
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/30/2026
1 project · most recent 03/24/2026
General Wiring
FiledStatusContractorScope
03/24/2026CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/24/2026Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
03/24/2026Air barrier - visual inspectionWalid Abdullaenergy_progress
03/20/2026Fire-Resistant Penetrations and JointsWalid Abdullaspecial
03/20/2026Energy Code Compliance InspectionsWalid Abdullaprogress
03/20/2026FinalWalid Abdullaprogress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026S01375929-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026S01375929-I1Open ↗
09/01/2026S01375929-I1Open ↗
09/01/2026S01375929-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026S01375929-I1Open ↗
09/01/2026S01375929-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026S01375929-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/17/2026S01375929-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026S01375929-I1Open ↗