Whole building & multi-floor projectsNewmark Holdings LLC1 filing
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
2 documents
RoofSuper Nova 330 LLC c/o GFP REAL ESTATE, LLC2p · 4 filings · 18 docs
ArchitectureEquipmentFire ProtectionPlumbingStructural
Issued Permit Scope
Supported Scaffold
Propose to file for facade restoration. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
SUBSEQUENT APPLICATION FOR MODIFICATION OF SPRINKLER FIXTURES AS PER PLAN. THERE IS NO CHANGE TO USE, EGRESS, OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
11 documents · 1 drawing sheet
modifications of plumbing and sprinkler system
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
BulkheadSuper Nova 330 LLC c/o GFP REAL ESTATE, LLC1p · 1 filing · 6 docs
Architecture
Propose to file for facade restoration. No change in use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Floor 21Malin+goetz18p · 2 filings · 11 docs
ArchitectureEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Plumbing · Supported Scaffold
plumbing and sprinkler modification
On file for this project
3 documents · 17 drawing sheets
interior renovations partition, doors, millwork
On file for this project
8 documents · 1 drawing sheet
Floor 20
Floor 19Newmark Holdings LLC6p · 1 filing · 3 docs
ArchitectureDMEquipmentPlumbingStructural
Issued Permit Scope
General Construction · Supported Scaffold
APPLICATION FILED FOR MODIFICATIONS OF PARTITIONS, DOORS, FRAMES AND FLOORS. NO CHANGE TO USE EGRESS OR OCCUPANCY PROPOSED UNDER THIS APPLICATION. jm
On file for this project
3 documents · 6 drawing sheets
Floor 18Multi tenant floor construction1p · 1 filing · 3 docs
EquipmentPlumbingStructural
Issued Permit Scope
Supported Scaffold
No filed description on record for this project.
On file for this project
3 documents · 12 drawing sheets
Floor 17
Floor 16
Floor 15Newmark Holdings LLC41p · 5 filings · 18 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
modification to mechanical system
On file for this project
15 documents · 20 drawing sheets
Application filed for interior renovation, partitions, walls, door, floors,
On file for this project
5 documents · 1 drawing sheet
Modifications to plumbing and sprinkler system
On file for this project
4 documents · 14 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 14Newmark Holdings LLC20p · 1 filing · 20 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Supported Scaffold
SUBSEQUENT APPLICATION FOR MODIFICATION OF PLUMBING AND SPRINKLER FIXTURES AS PER PLAN. THERE IS NO CHANGE TO USE, EGRESS, OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
23 documents · 20 drawing sheets
Floor 13
Floor 12
Floor 11Newmark Holdings LLC39p · 6 filings · 18 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Supported Scaffold
mechanical modifications, modification to ductwork
On file for this project
5 documents · 7 drawing sheets
modifications of plumbing and sprinkler system
On file for this project
3 documents · 14 drawing sheets
interior renovation to include drywall, partition, floor , doors
On file for this project
6 documents · 6 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6Architectural RecordUnder Construction57p · 3 filings · 20 docs
ArchitectureElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
Sprinkler work as per drawings filed herewith.
On file for this project
46 documents · 33 drawing sheets
Propose to perform interior renovations. No change in use, egress or occupancy.
On file for this project
4 documents · 8 drawing sheets
SUBSEQUENT APPLICATION FOR MODIFICATION OF PLUMBING AND SPRINKLER FIXTURES AS PER PLAN. NEW HOT WATER HEATERS. THERE IS NO CHANGE TO USE, EGRESS, OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
19 documents · 34 drawing sheets
Floor 5Newmark Holdings LLC5p · 1 filing · 18 docs
ArchitectureEquipmentFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Supported Scaffold
Filing herewith for the renovations of 5th floor. Modifications to existing plumbing, sprinkler and mechanical system.
On file for this project
27 documents · 5 drawing sheets
Floor 4
Floor 33rd floor suite 302 tenant layout4p · 1 filing · 4 docs
ArchitectureDMEquipmentPlumbingStructural
Issued Permit Scope
General Construction · Supported Scaffold
APPLICATION FILED FOR MODIFICATIONS OF PARTITIONS, DOORS, FRAMES AND PANTRY. NO CHANGE TO USE EGRESS OR OCCUPANCY PROPOSED UNDER THIS APPLICATION. jm
On file for this project
4 documents · 4 drawing sheets
Floor 2Newmark Holdings LLC17p · 1 filing · 11 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers · Supported Scaffold
SUBSEQUENT APPLICATION FOR MODIFICATION OF SPRINKLER FIXTURES AS PER PLAN. THERE IS NO CHANGE TO USE, EGRESS, OR OCCUPANCY FILED UNDER THIS APPLICATION.
On file for this project
11 documents · 17 drawing sheets
Floor 1The Canuck 202 9th Avenue LLC11p · 9 filings · 20 docs
ArchitectureEquipmentMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sign · Supported Scaffold
UPDATE THE GAS FIRED COOKING EQUIPMENT AND FIRE SUPPRESSION SHUT OFF ON 1ST FLOOR AS SHOWN IN DRAWINGS. THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents · 2 drawing sheets
Remove existing booths and benches. Replace in new configuration.
On file for this project
7 documents
RENOVATION OF EXISTING EATING AND DRINKING ESTABLISHMENT, INCLUDING REMOVAL AND INSTALLATIONOF PARTITION, PLUMBING FIXTURE AND STORE FRONT PARTIAL; REPLACEMENT OF CEILING TILES. NOCHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICA
On file for this project
23 documents · 7 drawing sheets
Latest 3 of 9 filings on this floor.
MezzanineNewmark Holdings LLC5p · 4 filings · 20 docs
ArchitectureDMMechanical
Issued Permit Scope
General Construction · Mechanical Systems
RENOVATION OF EXISTING EATING AND DRINKING ESTABLISHMENT, INCLUDING REMOVAL AND INSTALLATIONOF PARTITION, PLUMBING FIXTURE AND STORE FRONT PARTIAL; REPLACEMENT OF CEILING TILES. NOCHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICA
On file for this project
23 documents · 2 drawing sheets
REMOVE INTERIOR PARTITION, FLOORING AND MILLWORK
On file for this project
3 documents · 1 drawing sheet
REMOVE ALL EXISTING BASE BUILDING SUPPLY AIR, RETURN AIR AND EXHAUST AIR, DUCTWORK WITH ALL ASSOCIATED DIFFUSERS, TERMINAL BOXES, CONTROLS,COLLARS, DAMPERS, RETURN/EXHAUST GRILLES AND CONTROLS
On file for this project
5 documents
Latest 3 of 4 filings on this floor.
CellarNewmark Holdings LLC20p · 5 filings · 20 docs
ArchitectureMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
UPDATE THE GAS FIRED COOKING EQUIPMENT AND FIRE SUPPRESSION SHUT OFF ON 1ST FLOOR AS SHOWN IN DRAWINGS. THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents
RENOVATION OF EXISTING EATING AND DRINKING ESTABLISHMENT, INCLUDING REMOVAL AND INSTALLATIONOF PARTITION, PLUMBING FIXTURE AND STORE FRONT PARTIAL; REPLACEMENT OF CEILING TILES. NOCHANGE IN USE, OCCUPANCY AND MEANS OF EGRESS IS INVOLVED UNDER THIS APPLICA
On file for this project
23 documents · 1 drawing sheet
REMOVE INTERIOR PARTITION, FLOORING AND MILLWORK
On file for this project
3 documents
Latest 3 of 5 filings on this floor.
Site & exteriorSuper Nova 330 LLC c/o GFP REAL ESTATE, LLC7 filings · 18 docs
ArchitectureElectricalEquipmentGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · General Construction · Sidewalk Shed · Sign · Supported Scaffold
Propose to file for facade restoration. No change in use, egress or occupancy.
On file for this project
6 documents · 7 drawing sheets
INSTALLATION OF SIDEWALK SHED IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
On file for this project
2 documents · 12 drawing sheets
ERECT AN ILLUMINATED SIGN ON WALL. NOT WITHIN VIEW OF ARTERIAL HIGHWAY OR PUBLIC PARK 1/2 ACRE OR MORE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.